|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML23291A1562023-10-18018 October 2023 NRC Pre-Submittal Meeting Watts Bar & Sequoyah LAR, TVA Presentation Slides ML23264A0412023-09-27027 September 2023 NRC Pre-Submittal Meeting WBN Rebaseline LAR, TVA Presentation Slides ML23251A1212023-09-12012 September 2023 RHR Flow Rate Reduction During Mode 6 Operation at 23 Ft. Refueling Water Level Technical Specification Change NON-PROPRIETARY Slides ML23251A1252023-09-12012 September 2023 Pre-submittal Meeting for License Amendment Request, Modify the Watts Bar Nuclear Plant Unit 1 and Unit 2 Technical Specification Surveillance Requirement 3.9.5.1 ML23178A0832023-07-10010 July 2023 Pre-submittal Meeting Slides for License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML23128A2882023-05-0808 May 2023 TVA Nuclear Plants -2022 EOC Media Slides ML23052A0362023-02-22022 February 2023 February 22, 2023, Pre-Submittal Meeting for the License Amendment Request for Increased Tritium Production at Watts Bar (EPID L-2023-LRM-0010) - Meeting Slides ML23044A5182023-02-15015 February 2023 Pre-Submittal Meeting Slides for Expedited License Amendment Request Re Main Control Room Chiller Completion Time Extension ML23041A3562023-02-15015 February 2023 February 15, 2023 Pre-submittal Meeting for Expedited License Amendment Request Main Control Room (MCR) Chiller Completion Time Extension (EPID L-2022-LRM-0098) (Slides) ML22318A1042022-11-14014 November 2022 Pre-submittal Meeting for American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative WBN-2-ISI-01 Slide Presentation ML22157A4132022-06-0606 June 2022 Plants - Pre-Submittal Teleconference for Proposed Amendment Request Regarding the Change for the Sequoyah and Watts Bar Nuclear Plants Technical Specification 3.4.12 Meeting Slides ML22102A3032022-04-12012 April 2022 Pre-submittal Meeting for Request for Exemption from Requirements of 10 CFR 26.205(d)(4) and 10 CFR 26.205(d)(6) Slide Presentation ML22080A1662022-03-21021 March 2022 TVA Nuclear Plants -2021 EOC Media Loop Slides for Automatic Play ML21343A0282021-12-14014 December 2021 TVA Slide Presentation Regarding Pre-Submittal Meeting for Proposed Revision to Capsule Withdrawal Schedule ML21281A2282021-10-13013 October 2021 Tennessee Valley Authority Fleet Pre-Submittal Meeting for License Amendment Request to Change Emergency Action Level Scheme Presentation - October 13, 2021 (EPID L-2021-LRM-0096) (Slides) ML21250A3652021-09-0808 September 2021 Meeting Slides - Watts Bar Nuclear Plant Unit 2, Presubmittal Teleconference for Proposed License Amendment to Revise the Updated Final Safety Analyses Report (UFSAR) to Use a Tube Support Plate Locking/Displacement Analysis ML21217A2872021-08-19019 August 2021 TVA Slides - Pre-Submittal Meeting for Proposed License Amendment Request Re Application to Modify Technical Specification 3.7.8 Essential Raw Cooling Water (ERCW) System, to Support Permanent Shutdown Board ML21229A1992021-08-19019 August 2021 Mid-Cycle SG Outage Strategy (EPID L-2021-LRM-0067) (Slides) ML21231A0972021-08-18018 August 2021 TVA Slides - Pre-Submittal Meeting for Proposed LAR Regarding Application to Modify Watts Bar Units 1 and 2 Technical Specification 3.7.8, Essential Raw Cooling Water (ERCW) System, to Support Permanent Shutdown Board Cleaning ML21117A0722021-04-27027 April 2021 Meeting Slides for April 28, 2021 Meeting with TVA ML21096A1312021-04-0707 April 2021 Pre-submittal Meeting for Inservice Testing (IST) Program Request for One-Time Extension of Test Frequency of WBN Unit 1 Group 6 Relief Valves ML21041A1552021-02-11011 February 2021 Meeting Slides for February 11, 2021 Meeting with TVA ML20345A0262020-12-10010 December 2020 Replacement Steam Generator Project Planned License Amendment Request (Lars). LAR Descriptions and Submittal Schedule Meeting Slides ML20329A3722020-11-24024 November 2020 Pre-Submittal Teleconference for Proposed License Amendment Request Regarding Technical Specification 5.9.9, Steam Generator Tube Inspection Report, to Use Popcd Methodology ML20302A1232020-10-28028 October 2020 Pre-Submittal Meeting Slides Non-Voluntary Application to Modify WBN Unit 1 and Unit 2 TS Surveillance Requirement 3.6.15.4, Shield Building ML20239A8672020-08-27027 August 2020 Pre-Submittal Meeting Slides License Amendment Request for Technical Specification 5.7.2.19 ML20175A0552020-06-23023 June 2020 TVA Slides for June 23, 2020, Emergency Plan Change Presubmittal Meeting ML20125A3242020-05-0505 May 2020 Pre-Submittal Meeting Slides for License Amendment Request - Main Control Room Chiller Completion Time Extension ML20049G1822020-02-18018 February 2020 February 20, 2020 - Pre-submittal Meeting Presentation - Transition to Westinghouse Fuel ML20009C3962020-01-0808 January 2020 Pre-Submittal Telecon for Expedited License Amendment Request to Revise Technical Specification 3.3.5, LOP DG Start Instrumentation ML19347B0722019-12-12012 December 2019 TVA and Xcel Energy Slides for Joint Presubmittal Meeting to License Amendment Requests to Adopt WCAP-17661, Revision 1 ML19282A0082019-10-0909 October 2019 TVA Slides for Pre-Submittal Meeting for License Amendment Request to Correct Unbalanced Voltage Relay Instrumentation Values ML19255H5522019-09-12012 September 2019 August 27, 2019, Summary of Public Meeting - Tennessee Valley Safety Conscious Work Environment Update at Watts Bar, Docket 50-390 and 50-391 ML19298A0042019-09-12012 September 2019 Presentation Slides for 9/12/19 Public Meeting ML19252A0532019-09-0909 September 2019 TVA Presentation Slides: Watts Bar Nuclear Plant Pre-Submittal Meeting for License Amendment Request Revised Offsite Electrical Power Sources ML19235A2882019-08-23023 August 2019 2019 WBN SCWE Public Meeting Slides 8-27-2019 (NRC Slides) ML19235A2712019-08-23023 August 2019 2019 TVA Watts Bar Nuclear Plant Public Meeting Slides 08-27-2019 (TVA Slides) ML19178A2462019-07-0101 July 2019 Presentation Material for July 1, 2019 Pre-submittal Meeting with TVA on Full Spectrum LOCA Methodology for Watts Bar, Units 1 and 2 ML19161A2412019-06-11011 June 2019 Pre-Application Meeting for Proposed License Amendment Request (LAR) Regarding Change to the WBN Unit 2 Technical Specifications (TS) 3.4.17, Steam Generator Tube Integrity and 5.7.2.12 Steam Generator Program ML19161A2392019-06-10010 June 2019 Plants Pre-Submittal Meeting for Proposed License Amendments Hydrological Analysis Updates June 10, 2019 ML19142A3602019-05-21021 May 2019 May 9, 2019 Summary of Public Meeting; Watts Bar Nuclear Plant ML19018A0072019-01-18018 January 2019 (WBN)Pre-Submittal Meeting for Proposed License Amendment Request Regarding a One-Time Change for the WBN Unit 2 Technical Specification (TS) 3.7.8, Essential Raw Cooling Water (ERCW) System. ML18291A5732018-10-18018 October 2018 Chilled Work Environment ML18291A5632018-10-18018 October 2018 Chilled Worked Environment Update ML18248A1052018-09-0505 September 2018 Presentation Slides - Watts Bar Nuclear Plant Units 1 and 2 Adoption of TSTF-425 Initiative 5b - Surveillance Frequency Control Program - September 6, 2018 ML18248A1022018-09-0505 September 2018 Presentation Slides - Watts Bar Nuclear Plant (WBN) Pre-Submittal Meeting for Proposed License Amendment Request Regarding Shutdown Board Cleaning - September 6, 2018 ML18248A1012018-09-0505 September 2018 Bar Nuclear Plant (WBN) Pre-Submittal Meeting for Proposed License Amendment Adoption of TSTF-500 ML18248A1072018-09-0505 September 2018 Presentation Slides - Watts Bar Nuclear Plant Units 1 and 2 Adoption of 10 CFR 50.69 - September 6, 2018 ML18164A3192018-06-18018 June 2018 Presentation Material for 6/19/18 Pre-submittal Meeting ML18024A7932018-01-25025 January 2018 Presentation Slides - Watts Bar Nuclear Plant Unit 2 Pre-Submittal Meeting for Proposed License Amendment Request Regarding the Use of PAD4TCD in the Large Break Loss of Coolant Accident Analysis 2023-09-27
[Table view] Category:Slides and Viewgraphs
MONTHYEARML23291A1562023-10-18018 October 2023 NRC Pre-Submittal Meeting Watts Bar & Sequoyah LAR, TVA Presentation Slides ML23264A0412023-09-27027 September 2023 NRC Pre-Submittal Meeting WBN Rebaseline LAR, TVA Presentation Slides ML23251A1212023-09-12012 September 2023 RHR Flow Rate Reduction During Mode 6 Operation at 23 Ft. Refueling Water Level Technical Specification Change NON-PROPRIETARY Slides ML23251A1252023-09-12012 September 2023 Pre-submittal Meeting for License Amendment Request, Modify the Watts Bar Nuclear Plant Unit 1 and Unit 2 Technical Specification Surveillance Requirement 3.9.5.1 ML23178A0832023-07-10010 July 2023 Pre-submittal Meeting Slides for License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML23128A2882023-05-0808 May 2023 TVA Nuclear Plants -2022 EOC Media Slides ML23052A0362023-02-22022 February 2023 February 22, 2023, Pre-Submittal Meeting for the License Amendment Request for Increased Tritium Production at Watts Bar (EPID L-2023-LRM-0010) - Meeting Slides ML23044A5182023-02-15015 February 2023 Pre-Submittal Meeting Slides for Expedited License Amendment Request Re Main Control Room Chiller Completion Time Extension ML23041A3562023-02-15015 February 2023 February 15, 2023 Pre-submittal Meeting for Expedited License Amendment Request Main Control Room (MCR) Chiller Completion Time Extension (EPID L-2022-LRM-0098) (Slides) ML23010A2542023-01-12012 January 2023 Pre-submittal Meeting for Expedited License Amendment Request Main Control Room (MCR) Chiller Completion Time Extension -- Meeting Slides ML22318A1042022-11-14014 November 2022 Pre-submittal Meeting for American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative WBN-2-ISI-01 Slide Presentation ML22157A4132022-06-0606 June 2022 Plants - Pre-Submittal Teleconference for Proposed Amendment Request Regarding the Change for the Sequoyah and Watts Bar Nuclear Plants Technical Specification 3.4.12 Meeting Slides ML22103A0852022-04-14014 April 2022 and Watts Bar Plant Pre-submittal Meeting for Inservice Testing (IST) Program Request for Alternative for the Motor Driven Auxiliary Feedwater Pump Testing Following Maintenance During an Outage Per ISTB-3310 ML22102A3032022-04-12012 April 2022 Pre-submittal Meeting for Request for Exemption from Requirements of 10 CFR 26.205(d)(4) and 10 CFR 26.205(d)(6) Slide Presentation ML22080A1662022-03-21021 March 2022 TVA Nuclear Plants -2021 EOC Media Loop Slides for Automatic Play ML22035A0002022-02-0404 February 2022 February 8, 2022, Pre-Submittal Meeting Slides Regarding Proposed Change to Modify the Allowable Value for Technical Specification Table 3.3.2-1, Function 6.e(1) ML22013A6432022-01-19019 January 2022 TVA Slides - Watts Bar Nuclear Plant (WBN) Schedule for the Development of a License Amendment Request (LAR) for Increased Tritium Production at WBN ML21343A0282021-12-14014 December 2021 TVA Slide Presentation Regarding Pre-Submittal Meeting for Proposed Revision to Capsule Withdrawal Schedule ML21281A2282021-10-13013 October 2021 Tennessee Valley Authority Fleet Pre-Submittal Meeting for License Amendment Request to Change Emergency Action Level Scheme Presentation - October 13, 2021 (EPID L-2021-LRM-0096) (Slides) ML21250A3652021-09-0808 September 2021 Meeting Slides - Watts Bar Nuclear Plant Unit 2, Presubmittal Teleconference for Proposed License Amendment to Revise the Updated Final Safety Analyses Report (UFSAR) to Use a Tube Support Plate Locking/Displacement Analysis ML21229A1992021-08-19019 August 2021 Mid-Cycle SG Outage Strategy (EPID L-2021-LRM-0067) (Slides) ML21217A2872021-08-19019 August 2021 TVA Slides - Pre-Submittal Meeting for Proposed License Amendment Request Re Application to Modify Technical Specification 3.7.8 Essential Raw Cooling Water (ERCW) System, to Support Permanent Shutdown Board ML21231A0972021-08-18018 August 2021 TVA Slides - Pre-Submittal Meeting for Proposed LAR Regarding Application to Modify Watts Bar Units 1 and 2 Technical Specification 3.7.8, Essential Raw Cooling Water (ERCW) System, to Support Permanent Shutdown Board Cleaning ML21096A1312021-04-0707 April 2021 Pre-submittal Meeting for Inservice Testing (IST) Program Request for One-Time Extension of Test Frequency of WBN Unit 1 Group 6 Relief Valves ML21096A1002021-04-0606 April 2021 Annual Assessments ML21041A1552021-02-11011 February 2021 Meeting Slides for February 11, 2021 Meeting with TVA ML21019A5692021-01-19019 January 2021 Pre-Submittal Teleconference for Proposed License Amendment Requests (Lars) for the WBN Unit 2 Replacement Steam Generator (RSG) Project ML20352A0362020-12-17017 December 2020 Pre-Submittal Teleconference for Proposed License Amendment to Revise the Updated Final Safety Analysis Report (UFSAR) to Use an Alternate Probability of Detection (POD) ML20329A3722020-11-24024 November 2020 Pre-Submittal Teleconference for Proposed License Amendment Request Regarding Technical Specification 5.9.9, Steam Generator Tube Inspection Report, to Use Popcd Methodology ML21050A1562020-10-21021 October 2020 Graizer - Presentation - Analysis of Tva'S Watts Bar Nuclear Power Plant Strong-Motion Records of the M 4.4 December 12, 2018 Decatur Tennessee Earthquake ML20239A8672020-08-27027 August 2020 Pre-Submittal Meeting Slides License Amendment Request for Technical Specification 5.7.2.19 ML20220A2022020-08-0707 August 2020 Pre-Submittal Meeting Slides - Proposed License Approach Regarding a Change for Watts Bar Nuclear Plant Units 1 & 2 Technical Specification 3.3.2 Table 1 Function 6.e Auxiliary Feedwater Auto-Start from Loss of Main Feedwater Pumps(Epid L-2 ML20209A0702020-07-27027 July 2020 Pre-submittal Meeting for Inservice Testing (IST) Program Request for Relief from Increased Frequency Testing of Residual Heat Removal (RHR) Pump 1B-B Meeting Slides ML20169A5222020-06-25025 June 2020 Pre-Submittal Meeting for License Amendment Request (LAR) Revised Steam Generator (SG) Inspection Intervals and TSTF-510 ML20175A0552020-06-23023 June 2020 TVA Slides for June 23, 2020, Emergency Plan Change Presubmittal Meeting ML20148M1452020-05-27027 May 2020 (Wbn)Proposed License Approach Regarding a Change for the WBN Units 1& 2 Technical Specification (TS) 3.3.2 Table 1 Function 6.e Auxiliary Feedwater Auto-Start from Loss of Main Feedwater Pumps ML20147A0132020-05-26026 May 2020 NRC Slides Final WBN-1 TS 3.3.3 LAR ML20134J0102020-05-14014 May 2020 Pre-Submittal Meeting for License Amendment Request Technical Specification 5.9.6 Add NRC-approved Neutron Fluence Calculational Methodology ML20125A3242020-05-0505 May 2020 Pre-Submittal Meeting Slides for License Amendment Request - Main Control Room Chiller Completion Time Extension ML20112F5302020-04-21021 April 2020 TVA Nuclear Plants -2019 EOC Media Loop Slides for Automatic Play (Final) ML20049G1822020-02-18018 February 2020 February 20, 2020 - Pre-submittal Meeting Presentation - Transition to Westinghouse Fuel ML20009C3962020-01-0808 January 2020 Pre-Submittal Telecon for Expedited License Amendment Request to Revise Technical Specification 3.3.5, LOP DG Start Instrumentation ML19282A0082019-10-0909 October 2019 TVA Slides for Pre-Submittal Meeting for License Amendment Request to Correct Unbalanced Voltage Relay Instrumentation Values ML19298A0042019-09-12012 September 2019 Presentation Slides for 9/12/19 Public Meeting ML19255H5522019-09-12012 September 2019 August 27, 2019, Summary of Public Meeting - Tennessee Valley Safety Conscious Work Environment Update at Watts Bar, Docket 50-390 and 50-391 ML19252A0532019-09-0909 September 2019 TVA Presentation Slides: Watts Bar Nuclear Plant Pre-Submittal Meeting for License Amendment Request Revised Offsite Electrical Power Sources ML19252A0522019-09-0909 September 2019 TVA Presentation Slides: Watts Bar Nuclear Plant (WBN) Application to Modify WBN Unit 1 and Unit 2 Technical Specification (TS) 3.6.15, Shield Building - September 11, 2019 ML19235A2712019-08-23023 August 2019 2019 TVA Watts Bar Nuclear Plant Public Meeting Slides 08-27-2019 (TVA Slides) ML19197A0932019-07-16016 July 2019 Presentation Slides - Watts Bar Nuclear Plant (WBN) Unit 2, Pre-Submittal Meeting for License Amendment Request Measurement Uncertainty Recapture (Mur) Power Update ML19178A2462019-07-0101 July 2019 Presentation Material for July 1, 2019 Pre-submittal Meeting with TVA on Full Spectrum LOCA Methodology for Watts Bar, Units 1 and 2 2023-09-27
[Table view] |
Text
Watts Bar Nuclear Plant (WBN)
Pre-Submittal Meeting for Proposed License Amendment Request Regarding a One-Time Change for the WBN Unit 2 Technical Specification (TS) 3.7.8 Essential Raw Cooling Water (ERCW) System January 16, 2019
Agenda
- Overview of the 6.9 kilovolt (kV) Shutdown Board (SDBD) 1A-A Maintenance
- Basis for Proposed One - Time Change
Opening Remarks
- WBN Unit 1 is currently scheduled to perform SDBD maintenance during the Spring 2020 outage
- This license amendment request (LAR) proposes a one-time extension of the WBN Unit 2 TS 3.7.8 Essential Raw Cooling Water (ERCW) System completion time from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to seven days to perform scheduled maintenance activities on 6.9kV SDBD 1A-A when WBN Unit 1 is defueled.
- Due to the commonality of the WBN 6.9kV SDBD loads, performing maintenance on a 6.9kV SDBD during a WBN Unit 1 refueling outage affects the ERCW system on the operating unit.
- With regard to the ERCW system currently, WBN TS require two ERCW pumps aligned to separate 6.9kV SDBDs to be operable per train, with two trains required for each unit.
Consequently, this requires all four 6.9 kV SDBDs to be operable to support the ERCW pump TS requirement.
l 3
System Overview
- The ERCW System is a common two-train system with each train having the capability to provide the required cooling water for both units under any credible plant condition.
- These ERCW System trains are independent and redundant.
- Each train of the ERCW system has four pumps total. As noted in the bases of WBN TS 3.7.8, for operating modes 1-4, two ERCW pumps aligned to separate 6.9kV SDBDs are required to be operable per train, with two trains required for each unit.
- The ERCW system has been analyzed for "worst case" heat loads under combinations of maximum river water temperature, design basis accident conditions, normal cooldown requirements, power train failures, for both units.
- The ERCW system has sufficient pump capacity for cooling water flows under all conditions and the system is arranged in such a way that even a complete header loss can be isolated in a manner that does not jeopardize plant safety.
l 4
System Overview l 5
System Overview ERCW Pump Motor Electrical Board Alignment I6
Overview of 6.9kV SDBD 1A-A Maintenance
- Maintenance activities performed during a 6.9kV SDBD board outage include:
- Breaker compartment inspections
- Indicating light resistor replacements
- Circuit breaker interface inspections and adjustments
- Primary/Secondary disconnects
- Breaker position and interface measurements and adjustments
- Bus inspections and tests
- As-found and as-left insulation resistance (megger) testing
Overview of 6.9 kV SDBD 1A-A Maintenance Shutdown Board Maintenance Timeline Activity Duration 1 Install Clearance 6 Hours 2 Ground Installation 4.5 Hours 3 Breaker Compartment Inspections 42 Hours 4 Circuit Breaker Interface Inspections 34 Hours and Adjustments 5 Bus Inspections and Tests 8 Hours 6 Ground Removal 4.5 Hours 7 Release Clearance 6 Hours Total 105 Hours
- 105 Hours is 4 Days 9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br />.
- Remaining duration of the one-time TS change allows for a contingency should the maintenance activities identify the need for an unexpected repair.
l 8
Overview of 6.9 kV SDBD 1A-A Maintenance
- In addition to this proposed LAR, other changes will be required to facilitate SDBD maintenance.
- On November 26,2018, Tennessee Valley Authority (TVA) submitted an LAR to the completion times with alternating current (AC) power sources and AC electrical distribution subsystems.
> NRC acceptance of this LAR 1/3/2019
- On November 29,2018, TVA submitted an LAR to adopt the Technical Specification Task Force (TSTF) Traveler TSTF-500.
- The proposed TS changes contained in these LARs are not dependent on each other and may be approved individually.
However, the approval of all proposed TS changes is necessary to provide the time required to perform 6.9kV SDBD 1A-A maintenance with WBN Unit 2 in operation.
l 9
Proposed One - Time Change for WBN Unit 2 TS 3.7.8 The proposed one-time change to the WBN Unit 2 TS 3.7.8 will:
- Add a new condition for modes 1-4 to increase the completion time for an inoperable ERCW Train from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days based on the following :
> When WBN Unit 1 is defueled.
> UHS temperature is 71°F.
> One ERCW System train is inoperable for planned maintenance of 6.9kV SD BD 1A-A.
l 10
3.7 PLANT SYSTEMS 3.7.8 Essential Raw Cooling W ater (ERCW ) System Proposed LCO 3.7.8 Two ERCW trains shall be OPERABLE.
APPLICABILITY: MODES 1, 2, 3, and 4.
One -Time ACTIONS Change for CONDITION REQUIRED ACTION COMPLETION TIME
NOTES--------------- A.1 ------------NOTES-----------
- 1. Only applicable when Unit 1 1. Enter applicable WBN Unit 2 2.
is defueled.
Only applicable when Conditions and Required Actions of LCO 3.8.1, "AC Ultimate Heat Sink (UHS) Sources - Operating,"
temperature is 71 ºF. for diesel generator TS 3.7.8 3. Only applicable during made inoperable by ERCW .
planned maintenance on 6.9 kV shutdown board 2. Enter applicable 1A-A. Conditions and
Required Actions of LCO 3.4.6, "RCS A. One ERCW train Loops - MODE 4," for inoperable.* residual heat removal loops made inoperable by ERCW .
Restore ERCW train to 7 days OPERABLE status.
AND A.2 Verify UHS temperature 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is 71 ºF.
AND Once every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter (continued)
- This Condition will apply during the Unit 1 spring 2020 refueling outage (U1R16) or until May 1, 2020, whichever occurs first. l 11
ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME Proposed BA. One ERCW train BA.1 ------------NOTES-----------
inoperable for reasons 1. Enter applicable other than Condition A. Conditions and One -Time Required Actions of LCO 3.8.1, "AC Sources- Operating,"
for diesel generator Change for made inoperable by ERCW.
- 2. Enter applicable WBN Unit 2 Conditions and Required Actions of LCO 3.4.6, "RCS TS 3.7.8 Loops-MODE 4," for residual heat removal loops made inoperable by ERCW.
Restore ERCW train to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OPERABLE status.
CB. Required Action A.1 and CB.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time not met. AND OR CB.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> Required Action and associated Completion Time of Condition AB not met.
l 12
Basis for Proposed One-Time Change
- TVA employs a graded approach to defense in depth (DID) and protected equipment strategies when equipment is removed from service
> NPG-SPP-07.0 Work Management
>> This program incorporates risk assessment methodologies and contingency processes to maximize personnel safety, plant safety, plant reliability, and worker productivity during plant modifications, maintenance, and testing.
> Includes both Online Work Management and Outage Management
>> NPG-SPP-07.1 On Line Work Management provides the guidance for the development and risk assessment for the daily schedule and supports the 13 week rolling schedule
>> NPG-SPP-07.2 Outage Management provides guidance for the development and risk assessment of the outage schedule
> NPG-SPP-07.3.4 Protected Equipment
>> Provides guidance for protecting plant equipment in order to minimize the potential for adverse operational events.
l 13
Basis for Proposed One-Time Change
- Engineering analyses have been performed with a single ERCW pump powered from the 6.9kV SDBD 2A-A (train A) in operation under the following bases
>> Design basis accident in WBN Unit 2
>> Loss of offsite power
>> WBN Unit 1 100 hour0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> limit prior to irradiated fuel movement (WBN TS 3.9.10)
>> WBN Unit 1 defueled
>> Unnecessary WBN Unit 1 ERCW cooling loads isolated.
>> 6.9kV SDBD 1A-A Out of Service
>> B ERCW train assumed failed
>> UHS temperature of 71°F
- This analyses conclude that a single ERCW pump powered from 6.9kV SDBD 2A-A can supply sufficient heat removal, while maintaining the outlet piping thermal stress temperature limits l 14
Technical Evaluation
- Hydraulic Proto-Flo model is used for the ERCW analyses
- Proto-Flo model was modified to reflect ERCW one pump configuration powered from 6.9kV SDBD 2A-A
- Reconfigured flow rates were compared to the analyzed flow rates for required equipment
> For components where flow rates are less than analyzed;
>> ERCW temperature versus ERCW flow curves were developed to determine the maximum allowable temperature for the one pump ERCW operation.
o PROTO-HX was used to determine the ERCW temperature required for available flow rate for heat exchangers and discharge piping temperature limits o Heat transfer analyses were used for the shutdown board room and electric board room chiller performance o Outlet piping temperatures were evaluated to confirm piping thermal stress limits were not exceeded
- The UHS temperature of 71°F ensures the required ERCW loads have sufficient cooling, while maintaining the outlet piping thermal stress temperature limits.
l 15
Technical Evaluation
- Conservatism in the analyses include
- ERCW pump performance curve used represents the in-service surveillance testing (IST) minimum performance criterion.
- Predicted flow rates for a single ERCW pump performance are reduced by 10% in the ERCW hydraulic analyses to account for measurement and analysis uncertainties
- 100 gallon per minute (gpm) system leakage loss is assumed in the analyses. This accounts for any unidentified system leakage which is in excess of typical system leakage under normal operating conditions.
- Commitments included in the LAR
- Hardware Changes
> To improve ERCW flow margin, emergency diesel generator 2A-A jacket water heat exchangers 2A1 and 2A2 will be replaced prior to implementation of the one-time TS change. The new heat exchangers are higher capacity units which require less ERCW cooling water flow.
- Administrative Controls
> Site operational procedure(s) will be developed / revised to align the ERCW system in accordance with the analyses prior to entry into the one-time WBN Unit 2 TS change.
l 16
Regulatory Precedent
- The proposed LAR to WBN Unit 2 TS 3.7.8 is consistent with the license amendment approved by Nuclear Regulatory Commission (NRC) for the Sequoyah Nuclear Plant (SQN), that also made a change to TS 3.7.8 for SQN Units 1 and 2.
- SQN LAR submitted on March 11, 2016 (ML16225A276)
- Request for Additional Information (RAI) responses dated May 31, 2016 (ML16153A071) and July 22, 2016 (ML16207A205),
- NRC Approval September 29, 2016 (ML16225A276)
- SQN LAR also added a new Condition A to TS 3.7.8 with a completion time of seven days and a limiting UHS temperature.
- WBN LAR TS 3.7.8 Condition A is only applicable when WBN unit 1 is defueled
- WBN LAR TS 3.7.8 Condition A is only applicable when one ERCW System train is inoperable for planned maintenance of 6.9kV SDBD 1A-A l 17
Schedule for Submittal
- 1/16/19 - Pre-submittal meeting with NRC
- 2/28/19 - Submit LAR to NRC
- Request NRC approval by 2/15/20 with a 30-day implementation date to support the WBN Unit 1 outage scheduled for Spring 2020 (U1R16).
- March 2019 - Telecon or meeting to discuss any NRC questions l 18
Closing Remarks
- Proposed one-time WBN Unit 2 TS change is needed to support scheduled maintenance activities of the 6.9kV SDBD 1A-A during the Unit1 R16 outage at WBN.
- Due to the commonality of the 6.9kV SDBDs, performing maintenance on 6.9kV SDBD 1A-A during a WBN Unit 1 refueling outage affects operability of the ERCW system for WBN Unit 2.
- The one-time change will extend the WBN Unit 2 TS 3.7.8 completion time from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days to support maintenance activities on 6.9kV SDBD 1A-A when WBN Unit 2 is in operation.
- This change is needed to support the WBN Unit 1R16 outage scheduled for Spring 2020.
l 19