MONTHYEARML24029A2362024-01-30030 January 2024 Preliminary Results of the Environmental Review, Subsequent License Renewal ML23338A1522023-12-0707 December 2023 Public Meeting Slides for North Anna and Surry Emergency Plan Augmentation Times License Amendment Request ML23255A0992023-09-15015 September 2023 Slides for September 15, 2023 Public Meeting on Poanhi Seismic Evaluations ML23254A0562023-09-13013 September 2023 Presentation Material for 9/13/23 Pre-Submittal Meeting License Amendment Request to Support Cycle Reloads Using Framatome Gaia Fuel ML23103A3482023-04-14014 April 2023 Annual Assessment Meeting Presentation for North Anna and Surry ML22277A8412022-10-18018 October 2022 Presentation Material for 10/18/22 Pre-Submittal Meeting Licensing Requests to Implement Framatome Gaia Fuel ML22243A0322022-09-0707 September 2022 Presentation Material for 9/7/22 Pre-Submittal Meeting Supplement to the Spent Fuel Pool Criticality Safety Analysis ML22236A0602022-08-29029 August 2022 Presentation Material for 8/29/22 Pre-Submittal Meeting Reactor Pressure Vessel Head Peening Follow-Up Exam Deferral ML22215A2872022-08-0909 August 2022 Presentation Material for 8/9/22 Pre-Submittal Meeting Containment Recirc Spray System Flow Test Alternative Request ML21221A0332022-06-17017 June 2022 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - NRC Slides ML22097A2262022-04-13013 April 2022 Presubmittal Presentation April 13, 2022 One-time TS Change of AOT for Unit 2 AFW Piping Replacement ML22082A1482022-03-23023 March 2022 Annual Assessment Meeting for Millstone Power Station - Webinar Presentation (NRC) ML22055B1132022-03-0202 March 2022 Technical Support Center (TSC) Relocation Proposed License Amendment Request - NRC Pre-Submittal Meeting, March 2, 2022 ML21174A3042021-06-23023 June 2021 SLRA RAI Response Public Meeting - 21-06-24 ML21221A1542021-05-27027 May 2021 Meeting Summary: Discussion of Dominion'S Response to Select Staff Requests for Additional Information on Subsequent License Renewal Application (EPID No. L-2020-SLR-0000) - Dominion Slides ML21134A1632021-05-20020 May 2021 Resolution of Tornado Wind Nonconformances Proposed License Amendment Request NRC Pre-Submittal Meeting - May 20, 2021 ML21145A2172021-05-13013 May 2021 Discussion on May 13, 2021 with Dominion on Select Staff RAIs on North Anna Subsequent License Renewal Application - Dominion Slides ML21132A2892021-05-13013 May 2021 SLRA RAI Response Public Meeting ML21127A1362021-05-13013 May 2021 May 13, 2021 NRC Pre-Submittal Meeting - Surry Power Station New Fuel Storage and Spent Fuel Pool Criticality Analysis Proposed License Amendment Request ML21076A3322021-03-18018 March 2021 3/18/21 - Annual Assessment Meeting for Millstone Power Station - Presentation Slides ML21034A5972021-02-10010 February 2021 External Presentation Am Atkinson_Nrc ISG-06 Meeting Dominion Digital IC Project 02102021 ML20307A1772020-11-0404 November 2020 NRC Presentation North Anna Power Station, Units 1 and 2 Subsequent License Renewal Review ML20288A3472020-10-14014 October 2020 (COVID-19) Emergency Preparedness Exemption Pre-Application Meeting ML20309A5912020-10-14014 October 2020 Pre-Submittal Meeting for License Amendment Requests to Implement Batch Framatome 15 X 15 AGORA-5A-I (Agora) Fuel at Surry Power Station Units 1 and 2 (SPS) - Slides ML20226A4112020-08-19019 August 2020 Presentation Material for 8/19/20 Pre-Submittal Meeting Biennial Emergency Preparedness Exercise Date Change Exemption Request ML20176A2762020-06-29029 June 2020 Presentation Material for 6/29/20 Pre-Submittal Meeting Proposed License Amendment Request for Measurement Uncertainty Recapture Power Uprate ML20143A0772020-05-26026 May 2020 Presentation Material for 5/26/20 Pre-Submittal Meeting Steam Generator Examination Frequency Alternative Request ML20111A0352020-04-20020 April 2020 Annual Assessment Meeting for Millstone Power Station - NRC Presentation Slides ML20099F2412020-04-0909 April 2020 Co., NRC Safety Pre& 8208;Application Meeting North Anna Power Station (NAPS) ML20099F2992020-04-0909 April 2020 NRC Slides for North Anna pre-app April 9 ML20098B6022020-04-0707 April 2020 Annual Assessment Meeting Presentation ML20098B7292020-04-0707 April 2020 Sur 2019 Annual Assessment Meeting Presentation ML19297D1872019-11-18018 November 2019 Pre-Application Meeting - Dominion Slides ML19311C5292019-11-0707 November 2019 Dsies Slides for Nov. 7, 2019 Public Meeting ML19143A4722019-06-0303 June 2019 Presentation Material for 6/03/19 Pre-Submittal Meeting Integrated Leak Rate Test Extension License Amendment Request ML19128A4072019-05-0909 May 2019 Presentation Material for 5/09/19 Pre-Submittal Meeting TS Coolant Activity Changes, License Amendment Request ML19063D9452019-03-0707 March 2019 Presentation Material for 3/07/19 Pre-Submittal Meeting License Amendment Request to Revise Technical Specification 3.8.1.1 ML19022A2432019-01-22022 January 2019 Presentation Material for 1/22/19 Pre-Submittal Meeting Fillet Weld Preheat Alternative Request ML19007A2162019-01-0808 January 2019 Subsequent License Renewal Environmental Scoping Meeting, Surry Power Station, Unit Nos. 1 and 2, January 8, 2018 ML18320A2502018-11-20020 November 2018 50.90 License Amendment Request - Dominion Fleet EAL Scheme Changes, November 20, 2018 Public Meeting ML18310A1812018-11-0808 November 2018 Presentation Material for 11/08/18 Pre-Submittal Meeting 10 CFR 50.69 Risk Informed Approach License Amendment Request ML18141A3072018-05-21021 May 2018 18 - SLR Status ML18108A2072018-04-10010 April 2018 04/10/2018 Public Teleconference Meeting Slides MPS3 C Charging Pump ML18032A5842018-02-0707 February 2018 SLR Pre-Application 02/07/2018 Meeting - Dominion Energy Slides ML17320A2012017-11-15015 November 2017 Modeling FLEX in Surry Power Station Internal Events and Flooding PRA ML17230A1282017-08-31031 August 2017 Connecticut, Inc. Presentation Slides for Pre-submittal Meeting on August 31, 2017 ML17200C9572017-07-18018 July 2017 Connecticut, Inc. Presentation Slides for Pre-submittal Meeting on July 18, 2017 ML17123A2092017-05-0303 May 2017 Summary of Meeting to Discuss Annual Assessment of the North Anna Power Station, Units 1 and 2 with the Public for the Period of January 1, 2016 Through December 31, 2016 ML16320A5232016-09-0707 September 2016 Pre-Submittal Meeting with Surry Power Station Regarding Carbon Fiber Reinforced Polymer Alternative Request ML16272A3462016-08-10010 August 2016 08/10/2016 - NEI Supplemental Material 2 (Estimate of BADGER System Uncertainty Using Millstone Unit 1 2013) 2024-01-30
[Table view] |
Text
50.90 License Amendment Request Fleet EAL Scheme Changes North Anna Surry Millstone 1 Nov. 20, 2018
Pre-Submittal Call License Amendment Request for NEI 99-01, Rev. 6 EAL Scheme Changes
- Millstone Power Station
- North Anna Power Station
- Surry Power Station November 20, 2018 2
Agenda
- Questions 3 Nov. 20, 2018
Purpose
- Communicate LAR plans for Millstone, North Anna & Surry Power Stations EAL scheme changes
- Outline proposed LAR format and content
- Review LAR schedule 4 Nov. 20, 2018
Current Licensing Basis Millstone Power Station
- MPS2 & MPS3 - NUMARC/NESP-007, Rev. 2 North Anna & Surry Power Stations
Reason for the Changes
- Implement EAL scheme commonality for the Fleet
- Take advantage of EAL scheme benefits in Rev. 6 6 Nov. 20, 2018
Proposed EAL Changes
- Scheme change for all three sites to adopt the NRC endorsed NEI 99-01, Rev. 6 EALs
- One fleet LAR submittal for all three sites
- Differences will be indicated and justified
- Deviations associated with EP FAQs 2015-013, 2015-014 & 2016-002 justified / incorporated
- Site specific deviation associated with ICs AU1 &
SG1 justified 7 Nov. 20, 2018
LAR Content One LAR for all three sites includes:
- EAL Comparison Matrix Documents (i.e.
differences & deviations)
- NEI 99-01, Rev. 6 EAL Technical Bases Documents - Marked-up & Clean Copies
- Calculation Summaries 8 Nov. 20, 2018
LAR Schedule
- One LAR scheduled to be submitted by the end of the fourth quarter 2018
- One year review requested
- 270 day implementation period proposed for each site 9 Nov. 20, 2108
?
10 Nov. 20, 2018