50.90 License Amendment Request Fleet EAL Scheme Changes North Anna Surry Millstone 1 Nov. 20, 2018

Pre-Submittal Call License Amendment Request for NEI 99-01, Rev. 6 EAL Scheme Changes

- Millstone Power Station

- North Anna Power Station

- Surry Power Station November 20, 2018 2

Agenda

  • Purpose
  • Current Licensing Basis
  • Reason for the Changes
  • Proposed EAL Changes
  • Conclusions
  • Questions 3 Nov. 20, 2018

Purpose

  • Communicate LAR plans for Millstone, North Anna & Surry Power Stations EAL scheme changes
  • Outline proposed LAR format and content
  • Review LAR schedule 4 Nov. 20, 2018

Current Licensing Basis Millstone Power Station

  • MPS2 & MPS3 - NUMARC/NESP-007, Rev. 2 North Anna & Surry Power Stations

Reason for the Changes

  • Implement EAL scheme commonality for the Fleet
  • Take advantage of EAL scheme benefits in Rev. 6 6 Nov. 20, 2018

Proposed EAL Changes

  • Scheme change for all three sites to adopt the NRC endorsed NEI 99-01, Rev. 6 EALs
  • One fleet LAR submittal for all three sites
  • Differences will be indicated and justified
  • Deviations associated with EP FAQs 2015-013, 2015-014 & 2016-002 justified / incorporated
  • Site specific deviation associated with ICs AU1 &

SG1 justified 7 Nov. 20, 2018

LAR Content One LAR for all three sites includes:

  • Cover Letter
  • EAL Comparison Matrix Documents (i.e.

differences & deviations)

  • NEI 99-01, Rev. 6 EAL Technical Bases Documents - Marked-up & Clean Copies
  • Calculation Summaries 8 Nov. 20, 2018

LAR Schedule

  • One LAR scheduled to be submitted by the end of the fourth quarter 2018
  • One year review requested
  • 270 day implementation period proposed for each site 9 Nov. 20, 2108

?