Annual Assessment Meeting for Millstone Power Station - NRC Presentation Slides
ML20111A035
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 04/20/2020
From:
Reactor Projects Branch 2
To:
Draxton M
References
Download: ML20111A035 (14)


Text

Millstone April 21, 2020 Annual Assessment Meeting Millstone Annual Assessment Meeting Reactor Oversight Process - 2019 Nuclear Regulatory Commission - Region I King of Prussia, PA April 21, 2020 2

Agenda

  • Opening Remarks - Dan Schroeder
  • 2019 Millstone ROP Assessment Summary - Dan Schroeder
  • Millstone Significant License Changes - Rich Guzman
  • COVID - 19 Response - Dan Schroeder
  • ROP Enhancement - Dan Schroeder
  • NEAC Member Question and Answer - Dan Schroeder
  • Public Question and Answer - Dan Schroeder 3 04/21/2020 ML20111A035

Millstone April 21, 2020 Annual Assessment Meeting How To Ask a Question

  • You can type in your question at any time using the WebEx app. Questions will be addressed during the Question-and-Answer session at the end, - or -
  • You can wait until the Question-and-Answer session at the end and ask your question by verbally asking it or typing in your question 4 04/21/2020 Opening Remarks Daniel Schroeder Branch Chief Division of Reactor Projects 5 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting Millstone 2019 Assessment Summary

  • Millstone Units 2 & 3 operated safely and in a manner that preserved the public health and safety and protected the environment
  • Millstone Units 2 & 3 remained in the Licensee Response column of the Action Matrix
  • 8,777 hours0.00899 days <br />0.216 hours <br />0.00128 weeks <br />2.956485e-4 months <br /> of inspection and related activities
  • 9 Green Non-Cited Violations (NCVs) 6 04/21/2020 Millstone 2019 Assessment Summary (Cont)
  • 2 Allegations in 2019
  • All Green Performance Indicators
  • Unit 3 Emergency AC Power MSPI -

Close to Threshold 7 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting Millstone Senior Resident Inspector Summary Justin Fuller Senior Resident Inspector 8 04/21/2020 Millstone Resident Staff Chris Highley Eben Allen Amanda Rancourt Resident Inspector Resident Inspector Program Assistant 9 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting Millstone 2019 Power History Unit 2

  • April 22, 2019 - Power Reduction
  • July 25, 2019 - Power Reduction
  • April 11, 2019 - Scheduled Refueling Outage

Millstone April 21, 2020 Annual Assessment Meeting Triennial Fire Protection Inspection Inspection Report 2019010 (ML19261A879)

  • Inadequate Alternative Shutdown Procedure Fire Protection Program for Operating Reactors 12 04/21/2020 Millstone Significant License Changes Richard Guzman NRC Project Manager Office of Nuclear Reactor Regulation 13 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting Millstone Significant License Changes

  • Millstone Unit 2 Primary/Secondary Coolant Activity Limits
  • Millstone Unit 2 AC Offsite Source (permanent and one-time allowed outage time changes)
  • Emergency Action Level (EAL) Changes 14 04/21/2020 MP2 Pressurizer Weld Issues Kerri Kavanagh David Rudland Jonathan Ortega-Chief, Quality Senior Technical Luciano Assurance and Vendor Advisor for Reactor Ops Engineer Inspection Branch Materials, NRR 15 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting MP2 Pressurizer Weld Issues

  • In Sept 2019 and Jan 2020, Framatome identified deviations in the post weld heat treatment of welds in certain large components
  • These deviations pertain to the control of temperature within the ranges specified in the ASME code
  • The Millstone pressurizer was mentioned in both Part 21 discussions 16 04/21/2020 MP2 Pressurizer Weld Issues
  • NRC staff reviewed Framatomes Part 21 evaluation for the first issue and determined there is no immediate safety concern for those basic components supplied to U.S. reactors
  • A meeting to discuss the second PWHT issue is scheduled for May 19, 2020
  • NRC staff will participate in a vendor inspection of Framatome Saint-Marcel site in September 2020 17 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting NRC Actions in Response to COVID-19

  • Monitoring plant activities through inspections and oversight.
  • Maintaining emergency response capabilities within Regional IRCs and HQ.
  • Risk-informing eyes-on inspections through residents and regional inspections.

18 04/21/2020 NRC Requirements Related to COVID-19

  • 2010 Regulatory Issue Summary (RIS)

- https://www.nrc.gov/docs/ML1005/ML100539611.pdf

  • Minimum Shift Staffing

- Operators

- Security

- Emergency Response Organization

Millstone April 21, 2020 Annual Assessment Meeting Millstone Response to COVID-19

  • Asked staff to follow CDC prevention guidelines
  • Implemented social distancing guidelines and encouraged telework for many employees
  • Asked employees to stay home if they have symptoms 20 04/21/2020 ROP Enhancement Overall goal - further improve the risk-informed and performance-based aspects of the ROP taking into account NRC Principles of Good Regulation 21 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting ROP Enhancement (Cont.)

Phase 1 completed June 2019 (SECY-19-0067/ML19070A036)

- Key impact on inspectors is modest reduction in baseline inspection samples 22 04/21/2020 ROP Enhancement (Cont.)

  • Decision made Feb 2020 to discontinue project and return to normal work management practices
  • Other nearer term work (formerly Phase 2) underway - expect to complete in 2020

- Focuses on ISFSI inspections, Cross-cutting issues Program and PI&R Inspection Program

- RP inspection procedures already completed

  • Longer term work such as reviewing certain aspects of the PI Program and improving SDP tools will continue as priorities permit

Millstone April 21, 2020 Annual Assessment Meeting How to contact the NRC (www.nrc.gov) 24 04/21/2020 Office of Public Affairs Diane Screnci Neil Sheehan Diane.Screnci@nrc.gov Neil.Sheehan@nrc.gov 610-337-5330 610-337-5331 25 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting NRC Social Media Channels

1. Mail in NRC 2. Scan QR Code on back feedback form that - OR - of form with smart device will be emailed to all attendees - OR -
3. Through any computer by going to the Public Meeting Schedule and pressing the Meeting Feedback link for this meeting, or pressing the

[more] link for this meeting and then pressing the Meeting Feedback link on the Meeting Details page.

27 04/21/2020

Millstone April 21, 2020 Annual Assessment Meeting Question & Answers with members of the Connecticut Nuclear Energy Advisory Council 28 04/21/2020