Millstone April 21, 2020 Annual Assessment Meeting Millstone Annual Assessment Meeting Reactor Oversight Process - 2019 Nuclear Regulatory Commission - Region I King of Prussia, PA April 21, 2020 2
Agenda
- Opening Remarks - Dan Schroeder
- 2019 Millstone ROP Assessment Summary - Dan Schroeder
- Millstone Senior Resident Inspector Summary - Justin Fuller
- Millstone Significant License Changes - Rich Guzman
- MSP2 Pressurizer Weld Issues - David Rudland & Jonathan Ortega-Luciano
- COVID - 19 Response - Dan Schroeder
- ROP Enhancement - Dan Schroeder
- NEAC Member Question and Answer - Dan Schroeder
- Public Question and Answer - Dan Schroeder 3 04/21/2020 ML20111A035
Millstone April 21, 2020 Annual Assessment Meeting How To Ask a Question
- You can type in your question at any time using the WebEx app. Questions will be addressed during the Question-and-Answer session at the end, - or -
- You can wait until the Question-and-Answer session at the end and ask your question by verbally asking it or typing in your question 4 04/21/2020 Opening Remarks Daniel Schroeder Branch Chief Division of Reactor Projects 5 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting Millstone 2019 Assessment Summary
- Millstone Units 2 & 3 operated safely and in a manner that preserved the public health and safety and protected the environment
- Millstone Units 2 & 3 remained in the Licensee Response column of the Action Matrix
- 8,777 hours0.00899 days <br />0.216 hours <br />0.00128 weeks <br />2.956485e-4 months <br /> of inspection and related activities
- 9 Green Non-Cited Violations (NCVs) 6 04/21/2020 Millstone 2019 Assessment Summary (Cont)
- 2 Allegations in 2019
- All Green Performance Indicators
Close to Threshold 7 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting Millstone Senior Resident Inspector Summary Justin Fuller Senior Resident Inspector 8 04/21/2020 Millstone Resident Staff Chris Highley Eben Allen Amanda Rancourt Resident Inspector Resident Inspector Program Assistant 9 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting Millstone 2019 Power History Unit 2
- April 22, 2019 - Power Reduction
- July 25, 2019 - Power Reduction
- December 27, 2019 - Manual Reactor Trip Unit 3
- April 11, 2019 - Scheduled Refueling Outage
- December 17, 2019 - Technical Specification Required Reactor Shutdown 10 04/21/2020 Emergency Diesel Generator (EDG) Issues (2019)
- Unit 3: Cooling water leak (ML19224B324)
- Unit 3: Run Failure (ML19312A324)
- Unit 2: Fuel Oil Calculation (ML20044C873)
- Mitigating Systems Performance Index (MSPI) Emergency AC Power 11 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting Triennial Fire Protection Inspection Inspection Report 2019010 (ML19261A879)
- Control of Transient Combustibles
- Inadequate Alternative Shutdown Procedure Fire Protection Program for Operating Reactors 12 04/21/2020 Millstone Significant License Changes Richard Guzman NRC Project Manager Office of Nuclear Reactor Regulation 13 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting Millstone Significant License Changes
- Millstone Unit 2 Primary/Secondary Coolant Activity Limits
- Millstone Unit 2 AC Offsite Source (permanent and one-time allowed outage time changes)
- Emergency Action Level (EAL) Changes 14 04/21/2020 MP2 Pressurizer Weld Issues Kerri Kavanagh David Rudland Jonathan Ortega-Chief, Quality Senior Technical Luciano Assurance and Vendor Advisor for Reactor Ops Engineer Inspection Branch Materials, NRR 15 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting MP2 Pressurizer Weld Issues
- In Sept 2019 and Jan 2020, Framatome identified deviations in the post weld heat treatment of welds in certain large components
- These deviations pertain to the control of temperature within the ranges specified in the ASME code
- The Millstone pressurizer was mentioned in both Part 21 discussions 16 04/21/2020 MP2 Pressurizer Weld Issues
- NRC staff reviewed Framatomes Part 21 evaluation for the first issue and determined there is no immediate safety concern for those basic components supplied to U.S. reactors
- A meeting to discuss the second PWHT issue is scheduled for May 19, 2020
- NRC staff will participate in a vendor inspection of Framatome Saint-Marcel site in September 2020 17 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting NRC Actions in Response to COVID-19
- Monitoring plant activities through inspections and oversight.
- Maintaining emergency response capabilities within Regional IRCs and HQ.
- Risk-informing eyes-on inspections through residents and regional inspections.
18 04/21/2020 NRC Requirements Related to COVID-19
- 2010 Regulatory Issue Summary (RIS)
- https://www.nrc.gov/docs/ML1005/ML100539611.pdf
- Minimum Shift Staffing
- Operators
- Security
- Emergency Response Organization
- NRC Coronavirus Website https://www.nrc.gov/reading-rm/doc-collections/faq/coronavirus.html 19 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting Millstone Response to COVID-19
- Asked staff to follow CDC prevention guidelines
- Implemented social distancing guidelines and encouraged telework for many employees
- Asked employees to stay home if they have symptoms 20 04/21/2020 ROP Enhancement Overall goal - further improve the risk-informed and performance-based aspects of the ROP taking into account NRC Principles of Good Regulation 21 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting ROP Enhancement (Cont.)
Phase 1 completed June 2019 (SECY-19-0067/ML19070A036)
- Key impact on inspectors is modest reduction in baseline inspection samples 22 04/21/2020 ROP Enhancement (Cont.)
- Decision made Feb 2020 to discontinue project and return to normal work management practices
- Other nearer term work (formerly Phase 2) underway - expect to complete in 2020
- Focuses on ISFSI inspections, Cross-cutting issues Program and PI&R Inspection Program
- RP inspection procedures already completed
- Longer term work such as reviewing certain aspects of the PI Program and improving SDP tools will continue as priorities permit
- Web page below being retired when a more general Current Activities web page is developed https://www.nrc.gov/reactors/operating/oversight/rop-enhancement.html 23 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting How to contact the NRC (www.nrc.gov) 24 04/21/2020 Office of Public Affairs Diane Screnci Neil Sheehan Diane.Screnci@nrc.gov Neil.Sheehan@nrc.gov 610-337-5330 610-337-5331 25 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting NRC Social Media Channels
- Twitter: https://twitter.com/nrcgov
- YouTube: http://www.youtube.com/user/NRCgov
- RSS: http://www.nrc.gov/public-involve/listserver.html#rss 26 04/21/2020 Annual Assessment Meeting Feedback
- 1. Mail in NRC 2. Scan QR Code on back feedback form that - OR - of form with smart device will be emailed to all attendees - OR -
- 3. Through any computer by going to the Public Meeting Schedule and pressing the Meeting Feedback link for this meeting, or pressing the
[more] link for this meeting and then pressing the Meeting Feedback link on the Meeting Details page.
27 04/21/2020
Millstone April 21, 2020 Annual Assessment Meeting Question & Answers with members of the Connecticut Nuclear Energy Advisory Council 28 04/21/2020