Annual Assessment Meeting for Millstone Power Station - Webinar Presentation (NRC)
ML22082A148
Person / Time
Site: Millstone  
Issue date: 03/23/2022
From:
Division of Operating Reactors
To:
Young M
References
Download: ML22082A148 (25)


Text

Millstone Annual Assessment Meeting Welcome!

This meeting will start shortly If calling in using the phone:

Dial-in Number: (301) 576-2978 Phone Conference ID: 934440395#

Millstone Annual Assessment Meeting Reactor Oversight Process - 2021 Nuclear Regulatory Commission - Region I King of Prussia, PA March 24, 2022

Agenda Opening Remarks - Matt Young 2021 Millstone ROP Assessment Summary - Justin Fuller COVID-19 Response Update - Justin Fuller Nuclear Energy Advisory Council (NEAC) Items of Interest

- 2021 Unplanned Power Changes (update) - Justin Fuller

- Local Intense Precipitation Finding-Justin Fuller

- Unit 2 Turbine Driven Aux Feedwater Check Valve - Justin Fuller

- Millstone Significant License Changes - Rich Guzman Discussion with members of the Connecticut NEAC - Matt Young/Justin Fuller Public Question and Answer - Matt Young/Justin Fuller 3

03/24/2022

How To Ask a Question

  • Questions will be addressed during the question-and-answer session following the presentation and discussion with NEAC o If youre on your computer, raise your hand to indicate you have a question, o If on the phone, please unmute your phone and ask your question, then mute yourself again. Thank you.

03/24/2022 4

Todays Presenters 5

03/24/2022 Matt Young Branch Chief Division of Reactor Projects Justin Fuller Senior Resident Inspector Richard Guzman NRC Project Manager Nuclear Reactor Regulation

Opening Remarks

  • Three full-time residents assigned to Millstone
  • Technical specialists conduct additional inspection activities
  • Inspectors have adapted to COVID-19 work environment 6

03/24/2022

Millstone Resident Inspectors Eben Allen Resident Inspector 7

03/24/2022 Earl Bousquet Resident Inspector Justin Fuller Sr. Resident Inspector

Millstone 2021 Assessment Summary

  • Millstone operated safely and in a manner that preserved the public health and safety and protected the environment
  • Millstone Units 2 & 3 remained in the Licensee Response Column of the Action Matrix
  • 8,700+ hours of inspection and related activities
  • Green Performance Indicators
  • 9 Green Non-Cited Violations (NCVs)

03/24/2022

Safety Conscious Work Environment (SCWE)

SCWE No SCWE concerns The last PI&R was December 2020 Next PI&R scheduled for September 2022 Allegations 4 allegations in 2021 Resident inspectors and regional staff are highly accessible and take all allegation matters seriously 9

03/24/2022

NRC Actions in Response to COVID-19

  • Monitored plant activities through inspections and oversight
  • Maintained emergency response capabilities within Regional Incident Response Centers and NRC Headquarters 10 03/24/2022

Inspection Impact Due to COVID-19 11 03/24/2022 INSPECTIONS DEFERRED/DELAYED BEYOND CY 2020 DUE TO COVID-19 Inspection Procedure # - Title Originally Scheduled Date Completed Date Date Required to be Completed By IP 71114 Exercise Evaluation June 2020 June 2021 12/31/2021 IP 71111.11B U2 Licensed Operator Requalification Program November 2020 December 2021 12/31/2021 COVID-19 related licensing actions:

  • Temporary and final exemption from the annual force-on-force exercise requalification requirements of security personnel
  • License Amendment for one-time deferral of the MPS3 steam generator (SG) tube inspections for MPS3 SGs A and C from fall 2020 to spring 2022

Connecticut Nuclear Energy Advisory Council Items of Interest 12 03/24/2022

NEAC Items of Interest

  • Local Intense Precipitation (LIP)

Finding

NEAC Item of Interest -

Millstone 2021 Unplanned Power Changes 14 03/24/2022 Date Unit Impact Cause Jan 1 3

Forced Outage Feed water heater Jun 10 3

Maintenance Outage 3A RCP Seal Aug 22 2

90%

Henri Aug 22 3

92%

Henri Oct 7 2

0%

Refueling Outage No Unplanned Power Changes in 2021

NEAC Item of Interest - Local Intense Precipitation Finding (LIP)

  • Possible LIP was predicted by National Weather Service
  • GREEN Non-Cited Violation 15 03/24/2022

NEAC Item of Interest - U2 Turbine Driven Aux. Feedwater Check Valve (1 of 2)

  • Event Notifications:

- 55565 (11/6/21)

- 55576 (11/14/21)

  • GREEN Non-Cited Violation of Quality Assurance Criteria 16, Corrective Action 16 03/24/2022

17 03/24/2022

18 03/24/2022 Richard Guzman NRC Senior Project Manager Office of Nuclear Reactor Regulation

NEAC Item of Interest -

Millstone Significant License Changes

  • Millstone Unit 2 Steam Generator Inspection Frequency Technical Specification Revision
  • Millstone Unit 3 Technical Specification Changes - based on Westinghouse Topical Reports

- Core Operating Limits Report for Large Break Loss of Coolant Accident analysis

- Peak Fuel Centerline Melt Temperature Safety Limits 19 03/24/2022

Office of Public Affairs Diane Screnci Diane.Screnci@nrc.gov 610-337-5330 03/24/2022 20 Neil Sheehan Neil.Sheehan@nrc.gov 610-337-5331

NRC Social Media Channels 21 03/24/2022 Facebook www.facebook.com/nrcgov/

Twitter twitter.com/nrcgov YouTube www.youtube.com/user/NRCgov Flickr www.flickr.com/photos/nrcgov/

LinkedIn www.linkedin.com/company/u-s--nuclear-regulatory-commission/

RSS www.nrc.gov/public-involve/listserver.html#rss

Annual Assessment Meeting Feedback Submit feedback: Through any computer by going to the Public Meeting Schedule and pressing the Meeting Feedback link for this meeting, or pressing the [more]

link for this meeting and then pressing the Meeting Feedback link on the Meeting Details page.

Meeting number: 20220247 03/24/2022 22

Discussion with members of the Connecticut Nuclear Energy Advisory Council 23 03/24/2022

Q&A with Members of the Public

  • If on the computer, raise your hand when ready to ask your question
  • If on the phone, please unmute your phone to ask your question, then mute yourself again. Thank you.

03/24/2022 24

25 03/24/2022 This ends the Meeting Thank You for Attending!