Response to a Request for Additional Information in Regards to Changes to the Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program
ML15156A360
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 05/22/2015
From: Gardner P
Northern States Power Co, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-MT-15-040
Download: ML15156A360 (2)


Text

ENCLOSURE CONTAINS SAFEGUARDS INFORMATION. WHEN SEPARATED FROM THE ENCLOSURE, THIS DOCUMENT IS NOT SAFEGUARDS INFORMATION XcelEnergy@ Monticello Nuclear Generating Plant 2807 W County Road 75 Monticello, MN 55362 May 22, 2015 L-MT-15-040 10 CFR 50.54(p)(2)

U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed Facility Operating License No. DPR-22 Response to a Request for Additional Information in Regards to Changes to the Monticello Nuclear Generating Plant Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program

References:

1) NSPM to NRC, "Changes to the Monticello Nuclear Generating Plant Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" (L-MT-15-001) dated February 4, 2015. (ADAMS Accession No. ML15037A050)
2) NRC e-mail to NSPM, "Monticello Nuclear Generating Plant - DRAFT Requests for Additional Information Regarding Revision 14 to Physical Security Plan," dated April 30, 2015.

Northern States Power Company - Minnesota (NSPM), a Minnesota corporation, doing business as Xcel Energy, submitted pursuant to 10 CFR 50.54(p)(2), Revision 14 of the Monticello Nuclear Generating Plant (MNGP) Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program (here after referred to as the Security Plan) on February 4, 2015 (Reference 1).

By email dated April 30, 2015 (Reference 2), staff in the Reactor Security Licensing Branch (RSLB) in the Office of Nuclear Security and Incident Response (NSIR) requested additional information (RAI) to complete the review. The response to these RAIs is provided in Enclosure 1. In accordance with 10 CFR 73.21, the information contained in the Enclosure 1 is classified as Safeguards Information and must be withheld from public disclosure. When separated from the Safeguards Information enclosure, this document is decontrolled provided the transmittal document does not otherwise warrant protection from unauthorized disclosure.

ENCLOSURE CONTAINS SAFEGUARDS INFORMATION. WHEN SEPARATED FROM THE ENCLOSURE, THIS DOCUMENT IS NOT SAFEGUARDS INFORMATION

ENCLOSURE CONTAINS SAFEGUARDS INFORMATION. WHEN SEPARATED FROM THE ENCLOSURE, THIS DOCUMENT IS NOT SAFEGUARDS INFORMATION Document Control Desk L-MT-1 5-040 Page 2 of 2 Summary of Commitments This letter proposes no new commitments and does not revise any existing commitments.

Should you have questions regarding this letter, please contact Mr. Dale Miller at (763) 295-1098.

Peter A. Gardner Site Vice President, Monticello Nuclear Generating Plant Northern States Power Company - Minnesota Enclosure cc: Administrator, Region III, USNRC Project Manager, Monticello, USNRC (without Enclosure)

Resident Inspector, Monticello, USNRC (without Enclosure)

ENCLOSURE CONTAINS SAFEGUARDS INFORMATION. WHEN SEPARATED FROM THE ENCLOSURE, THIS DOCUMENT IS NOT SAFEGUARDS INFORMATION