MONTHYEARIR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 and Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 05000483/LER-2024-001, Submittal of LER 2024-001-00 for Callaway Plant, Unit 1, Reactor Trip Due to Turbine Trip2024-04-0404 April 2024 Submittal of LER 2024-001-00 for Callaway Plant, Unit 1, Reactor Trip Due to Turbine Trip ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation IR 05000483/20230022024-02-21021 February 2024 Amended Integrated Inspection Report 05000483/2023002 ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 IR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds 2024-08-05
[Table view] Category:Licensee Response to Notice of Violation
MONTHYEARULNRC-06779, ULNRC-06779: Contesting of Green NCV 05000483/2022010-03, Failure to Perform Required Inservice Testing of Residual Heat Removal Heat Exchanger Pneumatically (Air) Operated Outlet and Bypass Valves2022-11-14014 November 2022 ULNRC-06779: Contesting of Green NCV 05000483/2022010-03, Failure to Perform Required Inservice Testing of Residual Heat Removal Heat Exchanger Pneumatically (Air) Operated Outlet and Bypass Valves ML22318A1892022-11-14014 November 2022 Enclosure 1 - Ameren Missouri'S Response to Green NCV 05000483/2022010-03 ULNRC-06493, Supplemental Response to Notice of Violation, Inspection Report No. 50-483/20160022019-04-11011 April 2019 Supplemental Response to Notice of Violation, Inspection Report No. 50-483/2016002 IR 05000483/20170072017-11-0101 November 2017 Reply to Notice of Violation 05000483/2017007-01 ULNRC-06394, Reply to Notice of Violation 05000483/2017007-012017-11-0101 November 2017 Reply to Notice of Violation 05000483/2017007-01 ULNRC-06378, Supplemental Response to Notice of Violation Inspection Report No. 50-483/20160022017-06-27027 June 2017 Supplemental Response to Notice of Violation Inspection Report No. 50-483/2016002 ULNRC-06365, Updated Response to Notice of Violation Inspection Report 50-483/20160022017-04-27027 April 2017 Updated Response to Notice of Violation Inspection Report 50-483/2016002 ULNRC-06326, Reply to a Notice of Violation Inspection Report 05000-483/20160022016-09-0909 September 2016 Reply to a Notice of Violation Inspection Report 05000-483/2016002 IR 05000483/20080032008-09-0404 September 2008 Reply to Notice of Violation: EA-08-190, Inspection Report No. 50-483/2008003 ULNRC-05528, Reply to Notice of Violation: EA-08-190, Inspection Report No. 50-483/20080032008-09-0404 September 2008 Reply to Notice of Violation: EA-08-190, Inspection Report No. 50-483/2008003 ML0608304122006-03-14014 March 2006 IR 05000483-05-005, Union Electric Co., Reply to Notice of Violation IR 05000483/20050052006-03-14014 March 2006 IR 05000483-05-005, Union Electric Co., Reply to Notice of Violation ML0535702612005-12-14014 December 2005 Reply to Inspection No 50-483/05-004 IR 05000483/20050042005-12-14014 December 2005 Callaway, Reply to Inspection No 50-483/05-004 ULNRC-04867, Reply to Notice of Violation Inspection Report No. 50-483/2003-0082003-07-21021 July 2003 Reply to Notice of Violation Inspection Report No. 50-483/2003-008 ULNRC-04848, Reply to Preliminary White Finding Regarding Inspection Report No. 50-483/2003-0082003-06-10010 June 2003 Reply to Preliminary White Finding Regarding Inspection Report No. 50-483/2003-008 ULNRC-04653, Reply to Notice of Violation for Inspection Report 50-483/2002-007, Enforcement Action EA-02-0462002-05-0808 May 2002 Reply to Notice of Violation for Inspection Report 50-483/2002-007, Enforcement Action EA-02-046 ML0202903752002-01-22022 January 2002 Response to Enforcement Action (EA-01-005) from Union Electric Co 2022-11-14
[Table view] |
Text
W Ameren MISSOURI November 1, 2017 ULNRC-06394 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Ladies and Gentlemen:
10 CFR 2.201 DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO. RENEWED FACILITY OPERATING LICENSE NPF-30 REPLY TO NOTICE OF VIOLATION 05000483/2017007-01 Callaway Plant This letter provides Ameren Missouri's response to the Notice of Violation identified for the Callaway Plant in NRC's letter dated October 6, 2017, "Callaway Plant -NRC Design Bases Assurance Inspection Report 05000483/2017007 and Notice of Violation," from Thomas R. Famholtz to Fadi Diya. The response to the violation is presented in the attachment to this letter. None of the material in the response is considered proprietar This letter does not contain new commitment Please contact me for any questions you may have or for any additional infonnation you may require in regard to this respons Attachment 1: Response to Violation
................... ****** .............................
..................... . ..........................
..........................
.... .. **************
......................................
........................ . ********************
..... ***********-*****************
- .......................................... . *************
......................
- ********************************************
Sincerely,-, J J ~-£ Ir ,____ __ P.O. Box 620 T. E. Hemnann Site Vice President Fulton, MO 65251 AmerenMissouri.com ULNRC-06394 November 1, 2017 Page 2 of3 cc: Mr. Kriss M. Kennedy Regional Administrator U.S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 820 I NRC Road Steedman, MO 65077 Mr. L. John Klos Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 08H4 Washington, DC 20555-0001
...........................................................................
.; ... ................................................................................................................................................ . *********************************************************************************************************-**************************-*****************-*************************************************************************
................................................................................................................................................................................................................................
................................................................................................................................................................................................................................
................................................................................................................................................................................................................................