MONTHYEAR0CAN091302, Assistance in Obtaining Information on Dams2013-09-30030 September 2013 Assistance in Obtaining Information on Dams Project stage: Request L-PI-14-024, Extension Request Regarding the Flooding Hazard Reevaluation Report Required by NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(0 Regarding Recommendation 2.1, Flooding, of the Near-Term Task For2014-03-10010 March 2014 Extension Request Regarding the Flooding Hazard Reevaluation Report Required by NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(0 Regarding Recommendation 2.1, Flooding, of the Near-Term Task Force Project stage: Request L-14-113, Extension Request Regarding the Flood Hazard Reevaluation Report Required by NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights.2014-03-11011 March 2014 Extension Request Regarding the Flood Hazard Reevaluation Report Required by NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights. Project stage: Request 0CAN031401, Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report Arkansas Nuclear One - Units 1 and 22014-03-12012 March 2014 Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report Arkansas Nuclear One - Units 1 and 2 Project stage: Request 0CAN041402, Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report2014-04-14014 April 2014 Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report Project stage: Request ML14168A0182014-05-16016 May 2014 Xcel Energy Responses to NRC Questions Regarding Flood Hazard Reevaluation Report Extension Requests Project stage: Other ML14153A0242014-05-16016 May 2014 Xcel Energy'S Presentation Slides Supporting a May 16, 2014, Public Meeting to Discuss the Flood Hazard Reevaluation Schedule for the Monticello and Prairie Island Nuclear Generating Plants Project stage: Meeting ML14153A0252014-06-20020 June 2014 Meeting Summary - Public Meeting on May 16, 2014, to Discuss Xcel Energy'S Flood Hazard Reevaluation Extension Request for the Monticello and Prairie Island Nuclear Generating Plants Project stage: Meeting ML14162A3712014-06-26026 June 2014 5/22/2014 Summary of Meeting with Entergy Operations, Inc. to Discuss Flooding Hazard Reevaluation Extension Request for Arkansas Nuclear One, Units 1 and 2; Near-Term Task Force Recommendation 2.1 Project stage: Meeting ML14171A5292014-07-17017 July 2014 Relaxation of Response Due Date Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of the Insights from the Fukushima Dai-Ichi Accident Project stage: Approval ML14171A1662014-07-29029 July 2014 Relaxation of Response Due Date Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of the Insights from the Fukushima Dai-Ichi Accident Project stage: Approval ML15155A6312015-06-0808 June 2015 Nuclear Regulatory Commission Plan for the Audit of Duke Energy Carolinas, Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1 Flooding for Catawba Nuclear Station, Units 1 and 2 Project stage: Other 2014-05-16
[Table View] |
|
---|
Category:Letter
MONTHYEARML24295A1202024-10-21021 October 2024 Relief Request ANO2-RR-24-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 71 IR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20244042024-08-29029 August 2024 Cybersecurity Inspection Report 05000313/2024404 and 05000368/2024404 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20243012024-04-16016 April 2024 NRC Examination Report 05000313/2024301 ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle 2024-09-09
[Table view] |
Text
0CAN031401March 12, 2014U.S. Nuclear Regulatory CommissionATTN: Document Control Desk11555 Rockville PikeRockville, MD 20852
SUBJECT:
Required Response 2 to March 12, 2012, Request for Information (RFI),Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation ReportArkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368License Nos. DPR-51 and NPF-6
REFERENCES:
- 1. NRC letter to Entergy,RFI Pursuant to Title 10 of the Code ofFederal Regulations 50.54(f) Regarding Recommendations 2.1,2.3, and 9.3 of the Near-Term Task Force (NTTF) Review ofInsights from the Fukushima Dai-ichi Accident
, datedMarch 12, 2012 (0CNA031208) (ML12053A340)2. Entergy letter to NRC,Entergy's Response to NRC RFI Pursuantto 10 CFR 50.54(f) Regarding the Flooding Aspects ofRecommendations 2.1 and 2.3 of the NTTF Review of Insightsfrom the Fukushima Dai-ichi Accident
, dated June 8, 2012 (0CAN061202)3. Entergy letter to NRC,Assistance in Obtaining Information on Dams, dated September 30, 2013 (0CAN091302)4. NRC letter to Entergy,Supplemental Information Related to RFIPursuant toTitle 10 of the Code of Federal Regulations 50.54(f)Regarding Flooding Hazard Reevaluations for Recommendation2.1 of the NTTF Review of Insights fron the Fukushima Dai-ichi Accident, dated March 1, 2013 (0CAN031302 ) (ML13044A561)
Dear Sir or Madam:
On March 12, 2012, the NRC issued Reference 1 requesting information pursuant toTitle 10 of the Code of Federal Regulations 50.54(f). Enclosure 2 of that letter containsspecific requested Information associated with NTTF Recommendation 2.1 for flooding.By Reference 2 Entergy Operations, Inc. (Entergy) committed to submit the flood hazardevaluation for Arkansas Nuclear One (ANO), Units 1 and 2 as a Category 2 site byMarch 12, 2014.Entergy Operations, Inc.
1448 S.R. 333Russellville, AR 72802Tel 479-858-3110Jeremy G. BrowningSite Vice PresidentArkansas Nuclear One 0CAN031401 Page 2 of 3In September 2013 (Reference 3), Entergy requested the assistance of the NRC toobtain information from three Districts of the United States Army Corps of Engineers(USACE) to support the flood hazard reevaluation at ANO. Pursuant to the guidance inReference 4, Entergy is revising its commitment for submittal of the flood hazardreevaluation report to six months after USACE data is received.Reason for the Delay:The NRC recently notified Entergy that the kickoff meeting with the USACE and theNRC is expected to be scheduled in the near future. Receipt of the USACE informationis not expected for several months subsequent to the meeting.
Proposed Schedule:Subsequent to receipt of the USACE information, six months are necessary to: Complete the Dam Failure calculation. Use Dam Failure calculation as input to complete the Combined Effects calculation. Perform anticipated stepwise model refinements (consistent with the hierarchicalhazard assessment approach) to the Probable Maximum Precipitation, ArkansasRiver Probable Maximum Flood (PMF) flow, and Arkansas River PMF elevation calculations. Perform iterations to the Dam Failure and Combined Effects calculations. Complete flood hazard reevaluation report for submittal.Basis for Acceptability: Preliminary results to date based on publicly available information including theUSACE districts and National Inventory of Dams indicate the flood hazard isexpected be bounded by the current design basis flood level. The NRC has previously determined in their March 2012, 50.54(f) letter that thecurrent regulatory approach and the resultant plant capabilities provide confidencethat an accident with consequences similar to the Fukushima accident is unlikely tooccur in the United States. The NRC letter concluded that continued plant operationand the continuation of licensing activities do not pose an imminent risk to publichealth and safety. The events being analyzed in the flooding hazard reevaluation are beyond theplant's design basis (and licensing basis). The reevaluation results do not constitutean operability concern. The reevaluated flooding hazard is a very low probability event. The timeframe ofthe submittal delay is short relative to the probability of occurrence of the flood eventbeing evaluated.
0CAN031401 Page 3 of 3This letter contains a revised regulatory commitment which is identified in theattachment. Should you have any questions concerning the content of this letter, pleasecontact Stephenie Pyle at 479.858.4704.I declare under penalty of perjury that the foregoing is true and correct. Executed onMarch 12, 2014.
Sincerely,Original signed by Jeremy G. Browning JGB/nbm
Attachment:
List of Regulatory Commitmentscc: Mr. Marc L. DapasRegional AdministratorU. S. Nuclear Regulatory Commission, Region IV1600 East Lamar BoulevardArlington, TX 76011-4511NRC Senior Resident Inspector Arkansas Nuclear OneP.O. Box 310London, AR 72847U. S. Nuclear Regulatory CommissionAttn: Mr. Alan WangMS O-88B1One White Flint North11555 Rockville PikeRockville, MD 20852U. S. Nuclear Regulatory CommissionAttn: Mr. Michael OrenakMS O-8G9AOne White Flint North11555 Rockville PikeRockville, MD 20852 Attachment to0CAN031401List of Regulatory Commitments Attachment to 0CAN031401 Page 1 of 1List of Regulatory CommitmentsThe following table identifies those actions committed to by Entergy Operations, Inc. in thisdocument. Any other statements in this submittal are provided for information purposes andare not considered to be regulatory commitments.COMMITMENT TYPE(Check One)
SCHEDULEDCOMPLETIONDATE(If Required)
ONE-TIMEACTIONCONTINUINGCOMPLIANCESubmit Flood Hazard Evaluation Reportto the NRC.
XSix months after receipt ofinformation from theUnited States ArmyCorps of Engineers