MONTHYEAR0CAN091302, Assistance in Obtaining Information on Dams2013-09-30030 September 2013 Assistance in Obtaining Information on Dams Project stage: Request L-PI-14-024, Extension Request Regarding the Flooding Hazard Reevaluation Report Required by NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(0 Regarding Recommendation 2.1, Flooding, of the Near-Term Task For2014-03-10010 March 2014 Extension Request Regarding the Flooding Hazard Reevaluation Report Required by NRC Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(0 Regarding Recommendation 2.1, Flooding, of the Near-Term Task Force Project stage: Request L-14-113, Extension Request Regarding the Flood Hazard Reevaluation Report Required by NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights.2014-03-11011 March 2014 Extension Request Regarding the Flood Hazard Reevaluation Report Required by NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights. Project stage: Request 0CAN031401, Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report Arkansas Nuclear One - Units 1 and 22014-03-12012 March 2014 Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report Arkansas Nuclear One - Units 1 and 2 Project stage: Request 0CAN041402, Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report2014-04-14014 April 2014 Required Response 2 to March 12, 2012, Request for Information (Rfi), Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report Project stage: Request ML14168A0182014-05-16016 May 2014 Xcel Energy Responses to NRC Questions Regarding Flood Hazard Reevaluation Report Extension Requests Project stage: Other ML14153A0242014-05-16016 May 2014 Xcel Energy'S Presentation Slides Supporting a May 16, 2014, Public Meeting to Discuss the Flood Hazard Reevaluation Schedule for the Monticello and Prairie Island Nuclear Generating Plants Project stage: Meeting ML14153A0252014-06-20020 June 2014 Meeting Summary - Public Meeting on May 16, 2014, to Discuss Xcel Energy'S Flood Hazard Reevaluation Extension Request for the Monticello and Prairie Island Nuclear Generating Plants Project stage: Meeting ML14162A3712014-06-26026 June 2014 5/22/2014 Summary of Meeting with Entergy Operations, Inc. to Discuss Flooding Hazard Reevaluation Extension Request for Arkansas Nuclear One, Units 1 and 2; Near-Term Task Force Recommendation 2.1 Project stage: Meeting ML14171A5292014-07-17017 July 2014 Relaxation of Response Due Date Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of the Insights from the Fukushima Dai-Ichi Accident Project stage: Approval ML14171A1662014-07-29029 July 2014 Relaxation of Response Due Date Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of the Insights from the Fukushima Dai-Ichi Accident Project stage: Approval ML15155A6312015-06-0808 June 2015 Nuclear Regulatory Commission Plan for the Audit of Duke Energy Carolinas, Llc'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1 Flooding for Catawba Nuclear Station, Units 1 and 2 Project stage: Other 2014-05-16
[Table View] |
|
---|
Category:Letter type:
MONTHYEAR0CAN102401, Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzle2024-10-16016 October 2024 Response to Request for Additional Information - Arkansas Nuclear One – Units 1 and 2, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 2CAN102401, Cycle 31 Core Operating Limits Report (COLR)2024-10-14014 October 2024 Cycle 31 Core Operating Limits Report (COLR) 1CAN082401, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R312024-08-13013 August 2024 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 1 Thirty-First Refueling Outage (1R31 2CAN072401, Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02)2024-07-19019 July 2024 Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) 0CAN072401, Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes2024-07-0808 July 2024 Annual 10 CFR 50.46 Report for Calendar Year 2023 Emergency Core Cooling System Evaluation Changes 1CAN072401, Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply2024-07-0202 July 2024 Request for Review and Approval of Changes to the Safety Analysis Report and to a Confirmatory Order Clarifying an Alternate Means of Compliance for Pressurizer Heaters Emergency Power Supply 0CAN062403, Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels2024-06-25025 June 2024 Groundwater Protection Initiative - Voluntary Special Report for Tritium Levels 0CAN062402, Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-06-0606 June 2024 Proposed Alternatives ANO1-ISI-24-01 and ANO2-ISI-24-01 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles 0CAN052401, – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 20232024-05-13013 May 2024 – Units 1 and 2, Submittal of Annual Radiological Environmental Operating Report for 2023 1CAN052401, Cycle 32 Core Operating Limits Report2024-05-0404 May 2024 Cycle 32 Core Operating Limits Report 2CAN042403, Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C2024-04-24024 April 2024 Response to the Request for Additional Information Regarding ANO-2 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended C 0CAN042402, Annual Occupational Radiation Exposure Report for 20232024-04-23023 April 2024 Annual Occupational Radiation Exposure Report for 2023 0CAN042401, Radioactive Effluent Release Report for the 2023 Calendar Year2024-04-15015 April 2024 Radioactive Effluent Release Report for the 2023 Calendar Year 2CAN042402, Special Report of Non-functional Main Steam Line Radiation Monitor2024-04-11011 April 2024 Special Report of Non-functional Main Steam Line Radiation Monitor 2CAN042401, Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications2024-04-0404 April 2024 Request to Revise Typographical Errors in Arkansas Nuclear One, Unit 2 Technical Specifications 2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol 2CAN012403, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42024-01-11011 January 2024 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN012401, Registration of Cask Use2024-01-10010 January 2024 Registration of Cask Use 1CAN122301, Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037)2023-12-14014 December 2023 Responses to Request for Additional Information for Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISl-037) 0CAN102303, Registration of Cask Use2023-10-24024 October 2023 Registration of Cask Use 0CAN102301, Evacuation Time Estimate (ETE) Study2023-10-0404 October 2023 Evacuation Time Estimate (ETE) Study 1CAN092301, Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-09-21021 September 2023 Supplemental Information - Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN092302, Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2023-09-14014 September 2023 Supplement to Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2CAN092301, Reply to a Notice of Violation2023-09-0808 September 2023 Reply to a Notice of Violation 0CAN092301, Emergency Plan Implementing Procedure Revision2023-09-0505 September 2023 Emergency Plan Implementing Procedure Revision 0CAN082301, Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 03412023-08-17017 August 2023 Units 1 and 2 - Changes to the Quality Assurance Program Approval Form for Radioactive Material Package No. 0341 2CAN082301, Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29)2023-08-10010 August 2023 Inservice Inspection Summary Report for the Arkansas Nuclear One, Unit 2, Twenty-Ninth Refueling Outage (2R29) 0CAN072301, Registration of Cask Use2023-07-18018 July 2023 Registration of Cask Use 1CAN062304, Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation2023-06-29029 June 2023 Supplement Related to License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation 0CAN062301, Status of Actions to Return to Compliance2023-06-26026 June 2023 Status of Actions to Return to Compliance 0CAN062302, Submittal of Revision 22 of the ANO Fire Hazards Analysis2023-06-20020 June 2023 Submittal of Revision 22 of the ANO Fire Hazards Analysis 1CAN062301, Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037)2023-06-0808 June 2023 Request for Alternative for Implementation of Extended Reactor Vessel Inservice Inspection Interval (ANO1-ISI-037) 0CAN052303, Annual 10 CFR 50.46 Report for Calendar Year 20222023-05-24024 May 2023 Annual 10 CFR 50.46 Report for Calendar Year 2022 0CAN052302, Emergency Plan Rev. 482023-05-11011 May 2023 Emergency Plan Rev. 48 0CAN052301, Units 1 and 2 - Annual Radiological Environmental Operating Report for 20222023-05-0909 May 2023 Units 1 and 2 - Annual Radiological Environmental Operating Report for 2022 2CAN052301, Cycle 30 Core Operating Limits Report (COLR)2023-05-0303 May 2023 Cycle 30 Core Operating Limits Report (COLR) 0CAN042302, Annual Occupational Radiation Exposure Report for 20222023-04-27027 April 2023 Annual Occupational Radiation Exposure Report for 2022 0CAN042301, Radioactive Effluent Release Report for 20222023-04-14014 April 2023 Radioactive Effluent Release Report for 2022 2CAN042301, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42023-04-0505 April 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 1CAN032301, License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure2023-03-30030 March 2023 License Amendment Request to Modify the Arkansas Nuclear One, Unit 1, Technical Specification 3.3.1, Reactor Protection System Instrumentation, Turbine Trip Function on Low Control Oil Pressure 2CAN032303, Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Responses to Request for Additional Information Concerning the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032304, Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 462023-03-29029 March 2023 Supplement to the Request for Alternative Regarding the Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 46 2CAN032305, 03 Post Examination Analysis2023-03-23023 March 2023 03 Post Examination Analysis 1CAN032302, Inspection Summary Report for the Thirtieth Refueling Outage (1R30)2023-03-20020 March 2023 Inspection Summary Report for the Thirtieth Refueling Outage (1R30) 1CAN012301, Responses to Request for Additional Information for Request for Relief ANO1-ISI-0352023-01-30030 January 2023 Responses to Request for Additional Information for Request for Relief ANO1-ISI-035 2CAN012303, U.S. Additional Protocol2023-01-23023 January 2023 U.S. Additional Protocol 1CAN122201, License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 42022-12-22022 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4 0CAN122202, Registration of Cask Use2022-12-21021 December 2022 Registration of Cask Use 0CAN122201, Reply to a Notice of Violation; EA-22-0992022-12-0808 December 2022 Reply to a Notice of Violation; EA-22-099 0CAN112201, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002)2022-11-10010 November 2022 Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (ANO-CISI-002) 2024-08-13
[Table view] |
Text
Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Tel 479-858-3110 Jeremy G. Browning Site Vice President Arkansas Nuclear One 0CAN031401 March 12, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Required Response 2 to March 12, 2012, Request for Information (RFI),
Enclosure 2, Recommendation 2.1, Flood Hazard Evaluation Report Arkansas Nuclear One - Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6
REFERENCES:
- 1. NRC letter to Entergy, RFI Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (0CNA031208) (ML12053A340)
- 2. Entergy letter to NRC, Entergys Response to NRC RFI Pursuant to 10 CFR 50.54(f) Regarding the Flooding Aspects of Recommendations 2.1 and 2.3 of the NTTF Review of Insights from the Fukushima Dai-ichi Accident, dated June 8, 2012 (0CAN061202)
- 3. Entergy letter to NRC, Assistance in Obtaining Information on Dams, dated September 30, 2013 (0CAN091302)
- 4. NRC letter to Entergy, Supplemental Information Related to RFI Pursuant toTitle 10 of the Code of Federal Regulations 50.54(f)
Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the NTTF Review of Insights fron the Fukushima Dai-ichi Accident, dated March 1, 2013 (0CAN031302 ) (ML13044A561)
Dear Sir or Madam:
On March 12, 2012, the NRC issued Reference 1 requesting information pursuant to Title 10 of the Code of Federal Regulations 50.54(f). Enclosure 2 of that letter contains specific requested Information associated with NTTF Recommendation 2.1 for flooding.
By Reference 2 Entergy Operations, Inc. (Entergy) committed to submit the flood hazard evaluation for Arkansas Nuclear One (ANO), Units 1 and 2 as a Category 2 site by March 12, 2014.
0CAN031401 Page 2 of 3 In September 2013 (Reference 3), Entergy requested the assistance of the NRC to obtain information from three Districts of the United States Army Corps of Engineers (USACE) to support the flood hazard reevaluation at ANO. Pursuant to the guidance in Reference 4, Entergy is revising its commitment for submittal of the flood hazard reevaluation report to six months after USACE data is received.
Reason for the Delay:
The NRC recently notified Entergy that the kickoff meeting with the USACE and the NRC is expected to be scheduled in the near future. Receipt of the USACE information is not expected for several months subsequent to the meeting.
Proposed Schedule:
Subsequent to receipt of the USACE information, six months are necessary to:
- Complete the Dam Failure calculation.
- Use Dam Failure calculation as input to complete the Combined Effects calculation.
- Perform anticipated stepwise model refinements (consistent with the hierarchical hazard assessment approach) to the Probable Maximum Precipitation, Arkansas River Probable Maximum Flood (PMF) flow, and Arkansas River PMF elevation calculations.
- Perform iterations to the Dam Failure and Combined Effects calculations.
- Complete flood hazard reevaluation report for submittal.
Basis for Acceptability:
- Preliminary results to date based on publicly available information including the USACE districts and National Inventory of Dams indicate the flood hazard is expected be bounded by the current design basis flood level.
- The NRC has previously determined in their March 2012, 50.54(f) letter that the current regulatory approach and the resultant plant capabilities provide confidence that an accident with consequences similar to the Fukushima accident is unlikely to occur in the United States. The NRC letter concluded that continued plant operation and the continuation of licensing activities do not pose an imminent risk to public health and safety.
- The events being analyzed in the flooding hazard reevaluation are beyond the plants design basis (and licensing basis). The reevaluation results do not constitute an operability concern.
- The reevaluated flooding hazard is a very low probability event. The timeframe of the submittal delay is short relative to the probability of occurrence of the flood event being evaluated.
0CAN031401 Page 3 of 3 This letter contains a revised regulatory commitment which is identified in the attachment. Should you have any questions concerning the content of this letter, please contact Stephenie Pyle at 479.858.4704.
I declare under penalty of perjury that the foregoing is true and correct. Executed on March 12, 2014.
Sincerely, Original signed by Jeremy G. Browning JGB/nbm
Attachment:
List of Regulatory Commitments cc: Mr. Marc L. Dapas Regional Administrator U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 U. S. Nuclear Regulatory Commission Attn: Mr. Alan Wang MS O-88B1 One White Flint North 11555 Rockville Pike Rockville, MD 20852 U. S. Nuclear Regulatory Commission Attn: Mr. Michael Orenak MS O-8G9A One White Flint North 11555 Rockville Pike Rockville, MD 20852
Attachment to 0CAN031401 List of Regulatory Commitments
Attachment to 0CAN031401 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy Operations, Inc. in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE SCHEDULED (Check One) COMPLETION COMMITMENT DATE ONE-TIME CONTINUING (If Required)
ACTION COMPLIANCE Submit Flood Hazard Evaluation Report X Six months after to the NRC. receipt of information from the United States Army Corps of Engineers