2017/08/22 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Revise TS Actions for One Steam Supply to Turbine Driven EFW Pump Inoperable (MG0009)
ML17234A629
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 08/22/2017
From: Wengert T J
Plant Licensing Branch IV
To: Stephanie Pyle
Entergy Nuclear Operations
References
MG0009
Download: ML17234A629 (3)


Text

1NRR-PMDAPEm Resource From:Wengert, Thomas Sent:Tuesday, August 22, 2017 2:13 PM To:PYLE, STEPHENIE L Cc:BICE, DAVID B (ANO); Pascarelli, Robert

Subject:

ANO Unit 1 - Acceptance of Requested Licens ing Action RE: LAR to Revise TS Actions for One Steam Supply to Turbine Dr iven EFW Pump Inoperable (MG0009)

By letter dated July 17, 2017 (Agencywide Document s Access and Management System (ADAMS) Accession No. ML17198F072), Entergy Operations, Inc. (the licensee) submitted a license amendment request for

Arkansas Nuclear One, Unit 1 (ANO-1). The amendment request would establish Conditions, Required Actions, and Completion Times in ANO-1 Technical Specification (TS) 3.7.5, "Emergency Feedwater (EFW) System," for the condition where one steam supply to the turbine driven EFW pump is inoperable concurrent with an inoperable motor driven EFW train. The application stated that the change is consistent with NRC-approved Technical Specification Task Force (TSTF) Traveler TSTF-412, Revision 3, "Provide Actions for One Steam Supply to Turbine Driven AFW/EFW Pump Inoperable."

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff's acceptance review of the amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to a llow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that it does provide technical information in

sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed license amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that the licensing request will take approximately 200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is July, 2018. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staff's initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

2 Tom Wengert Senior Project Manager - Arkansas Nuclear One, Units 1 and 2 U. S. Nuclear Regulatory Commission NRR/DORL/LPL4

(301) 415-4037

Hearing Identifier: NRR_PMDA Email Number: 3680 Mail Envelope Properties (Thomas.Wengert@nrc.gov20170822141300)

Subject:

ANO Unit 1 - Acceptance of Requested Licensing Action RE: LAR to Revise TS Actions for One Steam Supply to Turbine Driven EFW Pump Inoperable (MG0009) Sent Date: 8/22/2017 2:13:01 PM Received Date: 8/22/2017 2:13:00 PM From: Wengert, Thomas Created By: Thomas.Wengert@nrc.gov Recipients: "BICE, DAVID B (ANO)" <DBICE@entergy.com> Tracking Status: None "Pascarelli, Robert" <Robert.Pascarelli@nrc.gov> Tracking Status: None "PYLE, STEPHENIE L" <SPYLE@entergy.com>

Tracking Status: None Post Office: Files Size Date & Time MESSAGE 3848 8/22/2017 2:13:00 PM

Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: