ML15313A207

From kanterella
Revision as of 03:55, 6 June 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Ltr 11/06/15 Acknowledgement of Annual Response to Confirmatory Order EA-13-068
ML15313A207
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 11/06/2015
From: Orth S K
Plant Support Branch II
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
EA-13-068
Download: ML15313A207 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 6, 2015 EA-13-068 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

ACKNOWLEDGEMENT OF ANNUAL RESPONSE TO CONFIRMATORY ORDER EA-13-068

Dear Mr. Hanson:

This acknowledges the receipt of your letter dated October 28, 2015, which provided an update to the status of your actions to complete the requirements contained in Confirmatory Order EA-13-068, as required by Section V.C of the Confirmatory Order. The Confirmatory Order confirmed commitments made by Exelon Generation Company, LLC (EGC) to the U.S. Nuclear Regulatory Commission (NRC) in an Alternate Dispute Resolution session. On May 4, 2015, the Confirmatory Order was relaxed by the NRC to allow EGC until November 30, 2015, to meet the requirements of Condition V.A.1. The NRC also relaxed the completion dates of Conditions V.A.2 and V.A.3. We understand from your letter that you are completing the final reviews of the revision to the Behavioral Observation Program procedure, as required by Condition V.A.1. In your letter, you also confirmed that Conditions V.A.2 and V.A.3 would be completed by the dates provided in the relaxation. Once you have notified us that all actions have been completed, we will schedule and conduct a follow-up inspection. The purpose of the inspection will be to independently confirm completion of the actions and evaluate their effectiveness in resolving the issues specified in the Confirmatory Order. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

B. Hanson Please contact me at 630-829-9757 with any questions you may have regarding this letter. Sincerely, /RA/

Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc: Distribution via LISTSERV B. Hanson Please contact me at 630-829-9757 with any questions you may have regarding this letter. Sincerely, /RA/

Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc: Distribution via LISTSERV DISTRIBUTION: Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ROPassessment.Resource@nrc.gov ADAMS Accession Number ML15313A207 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME KLambert for RSkokowski:cs SOrth DATE 11/06/15 11/06/15 OFFICIAL RECORD COPY UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 6, 2015 EA-13-068 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

ACKNOWLEDGEMENT OF ANNUAL RESPONSE TO CONFIRMATORY ORDER EA-13-068

Dear Mr. Hanson:

This acknowledges the receipt of your letter dated October 28, 2015, which provided an update to the status of your actions to complete the requirements contained in Confirmatory Order EA-13-068, as required by Section V.C of the Confirmatory Order. The Confirmatory Order confirmed commitments made by Exelon Generation Company, LLC (EGC) to the U.S. Nuclear Regulatory Commission (NRC) in an Alternate Dispute Resolution session. On May 4, 2015, the Confirmatory Order was relaxed by the NRC to allow EGC until November 30, 2015, to meet the requirements of Condition V.A.1. The NRC also relaxed the completion dates of Conditions V.A.2 and V.A.3. We understand from your letter that you are completing the final reviews of the revision to the Behavioral Observation Program procedure, as required by Condition V.A.1. In your letter, you also confirmed that Conditions V.A.2 and V.A.3 would be completed by the dates provided in the relaxation. Once you have notified us that all actions have been completed, we will schedule and conduct a follow-up inspection. The purpose of the inspection will be to independently confirm completion of the actions and evaluate their effectiveness in resolving the issues specified in the Confirmatory Order. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter, and your response (if any) will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

B. Hanson Please contact me at 630-829-9757 with any questions you may have regarding this letter. Sincerely, /RA/

Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc: Distribution via LISTSERV B. Hanson Please contact me at 630-829-9757 with any questions you may have regarding this letter. Sincerely, /RA/

Steven K. Orth, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc: Distribution via LISTSERV DISTRIBUTION: Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ROPassessment.Resource@nrc.gov ADAMS Accession Number ML15313A207 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME KLambert for RSkokowski:cs SOrth DATE 11/06/15 11/06/15 OFFICIAL RECORD COPY