Letter Sequence Other |
---|
|
|
MONTHYEARML15337A4132015-12-0303 December 2015 License Amendment Request to Revise Surveillance Requirement 3.8.1.6 Involving EDG Fuel Oil Transfer Project stage: Request ML16005A5522016-01-0505 January 2016 Acceptance Review - Peach Bottom Units 2 and 3 - Emergency Diesel Generator Fuel Oil Transfer Surveillance Requirements (CACs MF7143 and MF7144) Project stage: Acceptance Review ML16134A4742016-05-12012 May 2016 Draft Request for Additional Information Project stage: Draft RAI ML16162A1012016-06-0909 June 2016 Response to Request for Additional Information Regarding Proposed License Amendment Concerning Emergency Diesel Generator Fuel Oil Transfer Surveillance Requirements Project stage: Response to RAI ML16209A2042016-07-27027 July 2016 Draft Request for Additional Information Project stage: Draft RAI ML16216A0762016-08-0202 August 2016 Response to Draft Request for Additional Information Regarding the Proposed License Amendment Request Concerning Emergency Diesel Generator Fuel Oil Transfer Surveillance Requirements Project stage: Draft Request ML16314A0212016-11-0808 November 2016 Request to Extend the Implementation Period for the Proposed License Amendment Concerning Emergency Diesel Generator Fuel Oil Transfer Surveillance Requirements for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML16292A1882016-11-16016 November 2016 Issuance of Amendments Diesel Generator Fuel Oil Transfer Surveillance Requirements Project stage: Approval 2016-11-08
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000277/20244012024-10-17017 October 2024 Security Baseline Inspection Report 05000277/2024401 and 05000278/2024401 (Cover Letter Only) RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24284A2842024-10-10010 October 2024 (Wcgs), Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) ML24281A1012024-10-0707 October 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24221A2582024-09-0606 September 2024 Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 05000277/LER-2024-003, Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum2024-09-0505 September 2024 Automatic Reactor Scram Following Main Turbine Trip Due to Degraded Condenser Vacuum IR 05000277/20240022024-09-0404 September 2024 Reissued Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000277/20240052024-08-29029 August 2024 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2024005 and 05000278/2024005) IR 05000277/20240102024-08-23023 August 2024 Fire Protection Team Inspection Report 05000277/2024010 and 05000278/2024010 ML24235A0342024-08-23023 August 2024 U.S. Nuclear Regulatory Commission’S Analysis of Constellation Energy Generation’S Decommissioning Funding Status Report ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24227A5492024-08-14014 August 2024 Integrated Inspection Report 05000277/2024002 and 05000278/2024002 IR 05000482/20240052024-08-14014 August 2024 Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2024005) ML24225A1692024-08-12012 August 2024 10 CFR 50.46 Annual Report ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24214A3232024-08-0101 August 2024 Response to Request for Additional Information - Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24206A1252024-07-24024 July 2024 Revision of Three Procedures and Two Forms That Implement the Radiological Emergency Response Plan (RERP) ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24178A3672024-06-26026 June 2024 Correction to 2023 Annual Radioactive Effluent Release Report – Report 47 ML24178A4142024-06-26026 June 2024 Revision of One Procedure and One Form That Implement the Radiological Emergency Response Plan (RERP) ML24177A1512024-06-24024 June 2024 Post Accident Monitoring Instrumentation Report ML24166A1172024-06-20020 June 2024 Regulatory Audit Summary Regarding Proposed Alternative Schedule to Complete Decommissioning Beyond 60 Years RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000277/20243012024-06-13013 June 2024 Initial Operator Licensing Examination Report 05000277/2024301 and 05000278/2024301 RS-24-058, Regarding Subsequent License Renewal Environmental Review2024-06-0505 June 2024 Regarding Subsequent License Renewal Environmental Review ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24150A2722024-05-29029 May 2024 Annual Radiological Environmental Operating Report 81, January 1, 2023 Through December 31, 2023 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000277/20240012024-05-13013 May 2024 Integrated Inspection Report 05000277/2024001 and 05000278/2024001 ML24134A1792024-05-13013 May 2024 Supplemental Information in Support of Request for Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations IR 05000277/20245012024-05-0808 May 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000277/2024501 and 05000278/2024501 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24121A1832024-04-30030 April 2024 Pre-Submittal Meeting Presentation Material Peach Bottom ECCS Compensated Level System Replacement Project ML24118A0032024-04-27027 April 2024 2023 Annual Radioactive Effluent Release Report - Report 47 ML24120A2762024-04-23023 April 2024 Independent Spent Fuel Storage Installation (ISFSI) Facility - Annual Radioactive Effluent Release Report 66 January 1, 2023 Through December 31, 2023 CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24107A2462024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24102A0472024-04-11011 April 2024 Operator Licensing Examination Approval 05000277/LER-2024-002, Uncoordinated DC Circuits Cause Unanalyzed Condition2024-04-0808 April 2024 Uncoordinated DC Circuits Cause Unanalyzed Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. 05000277/LER-2024-001, Submittal of LER 2024-001-00 for Peach Bottom Atomic Power Station (PBAPS) Unit 2, Automatic Reactor Scram Due to an Invalid Generator Lockout2024-03-21021 March 2024 Submittal of LER 2024-001-00 for Peach Bottom Atomic Power Station (PBAPS) Unit 2, Automatic Reactor Scram Due to an Invalid Generator Lockout IR 05000277/20244022024-03-12012 March 2024 Cybersecurity Inspection Report 05000277/2024402 and 05000278/2024402 (Cover Letter Only) 2024-09-06
[Table view] |
Text
Exelon Generation 200 Exelon Way Kennett Square. PA 19348 www.exeloncorp.com 10 CFR 50.90 November 8, 2016 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRG Docket Nos. 50-277 and 50-278
Subject:
Request to Extend the Implementation Period for the Proposed License Amendment concerning Emergency Diesel Generator Fuel Oil Transfer Surveillance Requirements for Peach Bottom Atomic Power Station, Units 2 and 3
References:
1) Letter from J. Barstow (Exelon Generation Company, LLC) to the U.S. Nuclear Regulatory Commission, "License Amendment Request to Revise Surveillance Requirement 3.8.1.6 Involving EOG Fuel Oil Transfer (ML15337A413)," dated December3, 2015. 2) E-mail correspondence from R. Ennis (U.S. Nuclear Regulatory Commission) to S. J. Hanson (Exelon Generation Company, LLC), "Peach Bottom Atomic Power Station-:-Request for Additional Information Regarding Proposed License Amendment Request to Revise Surveillance Requirement 3.8.1.6 Involving EOG Fuel Oil Transfer (ML16134A474)," dated April 20, 2016. 3) Letter from J. Barstow (Exelon Generation Company, LLC) to the U.S. Nuclear Regulatory Commission, "Peach Bottom Atomic Power Station -Response to Request for Additional Information Regarding the Proposed License Amendment Request to Revise Surveillance Requirement 3.8.1.6 Involving EOG Fuel Oil Transfer (ML16162A101)," dated June 9, 2016. 4) E-mail correspondence from R. Ennis (U.S. Nuclear Regulatory Commission) to S. J. Hanson (Exelon Generation Company, LLC), "Peach Bottom Atomic Power Station -Request for Additional Information Regarding the Proposed License Amendment Request to Revise Surveillance Requirement 3.8.1.6 Involving EOG Fuel Oil Transfer (ML16209A204}," dated July 27, 2016.
U.S. Nuclear Regulatory Commission Request to Extent Implementation Period PBAPS SR 3.8.1.6 -EOG Fuel Oil Transfer November 8, 2016 Page 2 5) Letter from J. Barstow (Exelon Generation Company, LLC) to the U.S. Nuclear Regulatory Commission, "Peach Bottom Atomic Power Station -Response to Draft Request for Additional Information Regarding the Proposed License Amendment Request concerning Emergency Diesel Generator Fuel Oil Transfer Surveillance Requirements for Peach Bottom Atomic Power Station, Units 2 and 3(ML16216A076)," dated August 2, 2016. By application dated December 3, 2015, as supplemented by letters dated June 9, 2016 and August 2, 2016 Exelon Generation Company, LLC (EGC) submitted a license amendment request (LAR) for Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3 (Reference 1 ). The proposed amendment would revise the technical specification (TS) surveillance requirements (SRs) associated with the emergency diesel generator (EOG) fuel oil transfer system. Specifically, the amendment would allow for the crediting of manual actions, in lieu of automatic actions, without having to declare the EDGs inoperable. The U.S. NRC requested additional information (References 2 and 4). References 3 and 5 provided EGC's response. In the Reference 1 letter, EGC requested approval of the proposed amendment by December 3, 2016, and that once approved, the amendment shall be implemented within 60 days. EGC is requesting an extension of the implementation date from 60 days to 120 days for both PBAPS Units 2 and 3. This will provide adequate time, following the current Unit 2 refueling outage, for orderly implementation of the amendments, procedure revisions and the incorporation of engineering analysis into the time sensitive action (TSA) program. There are no regulatory commitments in this letter. If you have any questions concerning this request, please contact Stephanie J. Hanson at 610-765-5143. I declare under penalty of perjury that the foregoing is true and correct. Executed on the 8th day of November 2016. Respectfully, James Barstow Director, Licensing and Regulatory Affairs Exelon Generation Company, LLC U.S. Nuclear Regulatory Commission Request to Extent Implementation Period PBAPS SR 3.8.1.6 -EOG Fuel Oil Transfer November 8, 2016 Page 3 cc: USNRC Region I, Regional Administrator USNRC Senior Resident Inspector, PBAPS USNRC Project Manager, PBAPS R. R. Janati, Pennsylvania Bureau of Radiation Protection S. T. Gray, State of Maryland