Salem, Units 1 and 2: Triennial Fire Protection Inspection Report 05000272/2018007 and 05000311/2018007
ML18099A086
Person / Time
Site: Salem  PSEG icon.png
Issue date: 04/09/2018
From: Dentel G T
Engineering Region 1 Branch 2
To: Sena P P
Public Service Enterprise Group
References
IR 2018007
Download: ML18099A086 (19)


Text

April 9, 2018

Mr. Peter P. Sena, III President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P.O. Box 236 Hancocks Bridge, NJ 08038

SUBJECT: SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 AND 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000272/2018007 AND 05000311/2018007

Dear Mr. Sena:

On March 2, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Salem Nuclear Generating Stations (Salem), Units 1 and 2. The NRC inspectors discussed the results of this inspection with Mr. Paul Davison, Vice President of Nuclear Engineering, and other members of your staff. The results of this inspection are documented in the enclosed report. NRC inspectors documented one finding of very low safety significance (Green) in this report. This finding involved a violation of NRC requirements. Additionally, NRC inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Salem. In addition, if you disagree with the cross-cutting aspect assignment of the finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I, and the NRC Resident Inspector at Salem. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR ), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Sincerely,/RA/ Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-272 and 50-311 License Nos. DPR-70 and DPR-75

Enclosure:

Inspection Report 05000272/2018007 and 05000311/2018007 cc w/encl: Distribution via ListServ