Westinghouse Response to Schedule Update for the License Renewal Review
ML20202A678
Person / Time
Site: Westinghouse
Issue date: 07/20/2020
From: Malek E
Westinghouse
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
LTR-RAC-20-63
Download: ML20202A678 (2)


Text

WESTINGHOUSE NON-PROPRIETARY CLASS 3

@ Westinghouse Westinghouse Electric Company LLC Columbia Fuel Site 5801 BluffRoad Hopkins, South Carolina 29061-9121 USA Chief Fuel Facility Licensing Branch Division of Fuel Direct tel: 803-647-2046 Management Office of Nuclear Material Safety and Safeguards e-mail: malekem@westinghouse.com U. S. Nuclear Regulatory Commission Document Control Desk Your ref:

11555 Rockville Pike Our ref: LTR-RAC-20-63 Rockville, Maryland 20852-2738 July 20, 2020

SUBJECT:

WESTINGHOUSE RESPONSE TO SCHEDULE UPDATE FOR THE LICENSE RENEWAL REVIEW In accordance with the NRC request dated June 30, 2020, Westinghouse Electric Company LLC

("Westinghouse") is providing dates for the Phase II Remedial Investigation Work Plan activities, under the Consent Agreement with the South Carolina Department of Health and Environmental Control

("SCDHEC"), including when the Plan will be submitted to SCDHEC and when the results will be available. Note the structure of the investigation under the Consent Agreement mirrors the Environmental Protection Agency (EPA) Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process. The results of Phase II investigation will determine the next actions to be completed under the Consent Agreement.

Attachment 1 provides a tentative schedule for the Phase II Remedial Investigation Work Plan activities.

The process provides SCDHEC with multiple opportunities to review, comment on, and ultimately approve each step of the process. The SCDHEC milestone completion dates are presumed based on Westinghouse's understanding of SCDHEC's review process and not firm dates provided by the Department. Also, completion of environmental investigation activities is dependent on the weather and therefore, the schedule is subject to change.

If you have any questions, please contact me at (803) 647-2046.

  1. ~~

Elise Malek Licensing Manager Westinghouse Columbia Fuel Fabrication Facility Docket 70-1151 License SNM-1107 cc:

Mr. Thomas Vukovinsky Ms. Marilyn Diaz Ms. Jessie Quintero Mr. Andrea Kock Mr. John Tappert Mr. Ken Taylor

© 2020 Westinghouse Electric Company LLC All Rights Reserved

WESTINGHOUSE NON-PROPRIETARY CLASS 3 Page 2 of2 Our ref: LTR-RAC-20-63 July 20, 2020 ATTACHMENT 1 The following schedule provides tentative due dates for key milestones in the Phase II Remedial Investigation activities between Westinghouse and SCDHEC. If activities are completed, faster than outlined below, it is expected that the schedule moves up accordingly.

Tentative Phase II Remedial Investigation Schedule Milestone Comoletion Date Westinghouse submits Remedial Investigation Phase II Work Plan 09/14/2020 SCDHEC reviews and provides comments on the Work Plan 11/2020 Westinghouse resolves comments and submits Final Work Plan 12/2020 SCDHEC annroves Phase II Final Work Plan 01/2021 Westinghouse executes Work Plan and submits Phase II Interim Report 09/2021 SCDHEC reviews and provides comments on the Phase II Interim Report 11 /2021 Westinghouse resolves comments and submits Final Phase II Interim Report 12/2021 SCDHEC approves Final Phase II Remedial Investigation Interim Report 01 /2022