MONTHYEARML20202A6782020-07-20020 July 2020 Westinghouse Response to Schedule Update for the License Renewal Review Project stage: Other ML20259A1792020-07-30030 July 2020 Final Interim Remedial Investigation Data Summary Report Westinghouse Columbia Fuel Fabrication Facility Project stage: Request ML20294A0562020-07-30030 July 2020 Westinghouse Columbia Fuel Fabrication Facility Hf Spiking Station 1 Assessment Report Project stage: Request ML20259A2212020-07-30030 July 2020 Fuel Fabrication Facility Technetium (Tc-99) Source Investigation Report Project stage: Request ML20275A2512020-11-0303 November 2020 Letter to Westinghouse with RAIs Regarding Environmental Review for Proposed Renewal of Cfff License Project stage: RAI ML20353A2802020-12-18018 December 2020 Enclosure 4 - Response to Request for Additional Information - Phase II Remedial Investigation Work Plan Project stage: Response to RAI ML21026A0622021-01-28028 January 2021 Letter: Revised EIS Schedule to WEC-January 2021 Project stage: Other ML21102A0692021-04-0606 April 2021 Westinghouse Columbia Fuel Fabrication Facility License Renewal Environmental Commitments Project stage: Other ML21138A9262021-05-28028 May 2021 Westinghouse EIS Schedule Letter Project stage: Other ML21263A2172021-09-20020 September 2021 Submittal of Westinghouse Revised SNM-1107 License Renewal Application Project stage: Other ML21263A2182021-09-20020 September 2021 SNM-1107 License Renewal Application Project stage: Other ML22033A0712022-02-18018 February 2022 Westinghouse License Renewal RAIs (Environmental) Memo (Public) Project stage: RAI ML22052A0122022-02-21021 February 2022 Response to NRC Request for Additional Information Associated with the SNM-1107 License Renewal Environmental Impact Statement Project stage: Response to RAI ML22080A2822022-03-21021 March 2022 Westinghouse, Response to NRC Request for Additional Information Associated with the SNM-1107 License Renewal Environmental Impact Statement Project stage: Response to RAI ML22094A0972022-04-19019 April 2022 Westinghouse Schedule Extension Letter Project stage: Other ML22157A3482022-09-12012 September 2022 Westinghouse License Renewal Project stage: Request ML22157A3492022-09-12012 September 2022 Westinghouse Electric Company, LLC - Renewal of Materials License SNM-1107 (Enterprise Project Identifier: L-2017-RNW-0016) Project stage: Other 2021-05-28
[Table View] |
|
---|
Category:Letter
MONTHYEARML24023A6952024-01-26026 January 2024 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 07001151/2023004 ML24017A2252024-01-22022 January 2024 Westinghouse Electric Company, LLC, Conveyance of Revised Standby Trust Agreement to Support the Decommissioning Funding Plan (Enterprise Project Identifier L-2023-DFA-0009) ML23349A2722023-12-14014 December 2023 Westinghouse, Submittal of Monthly Progress Reports Under Consent Agreement 19-02-HW with the South Carolina Department of Health and Environmental Control ML23338A3372023-12-0404 December 2023 Submittal of Amendment 4 to Standby Trust Agreement (STA) for License Nu. SNM-1107, Replacement of Trust Fund with Additional Surety Bonds, and Certification of Financial Assurance for SNM-1107 ML23311A0032023-11-0606 November 2023 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 70-1151/2023-402 (Cover Letter) ML23296A0362023-10-24024 October 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023003 ML23240A5082023-08-28028 August 2023 Westinghouse Electric Company LLC - NRC Semi-Annual Discharge Report (January- June 2023) ML23230B2022023-08-18018 August 2023 Westinghouse, Supplemental Information for Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23216A0712023-08-0404 August 2023 Westinghouse Columbia Fuel Fabrication Facility Physical Security Core Inspection Report 07001151/202340 ML23202A1472023-07-24024 July 2023 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2023002 ML23150A2362023-07-0303 July 2023 Letter to Westinghouse Regarding Effluent Testing Issue ML23184A1512023-06-29029 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report Revision ML23171B1502023-06-20020 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report ML23160A2612023-06-0909 June 2023 Westinghouse, Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23139A1942023-06-0505 June 2023 Westinghouse Electric Company LLC - Approval of Environmental Sampling and Monitoring Program ML23138A3762023-05-18018 May 2023 Westinghouse Submittal of Columbia Fuel Fabrication Facility Site Emergency Plan, Revision 23 ML23096A2812023-05-15015 May 2023 Letter - Transfer of Control Approval 2023 ML23094A1582023-05-0505 May 2023 Westinghouse Electric Company, LLC - Revision to Temporarily Store Hematite Ash Above License Limits and Removal of Uranium Flywheel ML23115A2382023-04-26026 April 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023001 ML23114A3592023-04-24024 April 2023 Westinghouse Submittal of Environmental Sampling and Monitoring Program for NRC Review and Approval ML23114A3612023-03-23023 March 2023 Enclosures 2 & 3 - SCDHEC Approval Letter of Westinghouse Ri Report, Dated March 23, 2023 and Environmental Sampling and Monitoring Program Section of SNM-1107 License Application ML23058A4482023-02-27027 February 2023 Request for Threshold Determination for Interim Transaction Included in December 20, 2022 Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals ML23058A2722023-02-27027 February 2023 Westinghouse, NRC Semiannual Discharge Report July - December 2022 ML23053A0712023-02-17017 February 2023 Westinghouse Electric Company LLC, Supplement to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23053A0752023-02-17017 February 2023 Westinghouse Electric Co. - Supplement 2 to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23047A4562023-02-16016 February 2023 Westinghouse, Response to Request for Additional Information - Request for Temporary License Amendment for Storage of Hematite Ash ML23030B8552023-01-30030 January 2023 Westinghouse 10CFR70.72 Facility Change Report ML23024A2312023-01-30030 January 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151//2022004 ML23013A2122023-01-27027 January 2023 Acceptance Letter for Westinghouse License Transfer - Cac/Epid L-2022-LLM-0004 ML23026A3642023-01-26026 January 2023 Westinghouse, January 2023 Updated Integrated Safety Analysis Summary ML22354A0732023-01-19019 January 2023 Response to Westinghouse Revised Funding Instrument in Support of the Decommissioning Funding Plan ML22363A0152022-12-29029 December 2022 Westinghouse Electric Co - 60-Day Report Regarding the November 1, 2022, Incident Reported Under 10 CFR 70 Appendix a 24-Hr Report, Columbia Fuel Fabrication Facility (License No. SNM-1107, Docket No. 70-1151) ML22354A2912022-12-20020 December 2022 Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML22347A1162022-12-13013 December 2022 Westinghouse 2021-2022 Annual Groundwater Monitoring Report ML22336A1742022-12-0202 December 2022 Westinghouse Request for Temporary License Amendment for Storage of Hematite Ash ML22316A0052022-11-10010 November 2022 Westinghouse Electric Company LLC, Submittal of Amendment to Trust Agreement for License Number SNM-1107, Surety Bond Rider for SNM-1107, and Certification of Financial Assurance for SNM-1107 (Proprietary/Non-Proprietary) ML22298A0432022-10-28028 October 2022 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2022003 ML22294A1792022-10-21021 October 2022 Westinghouse, Request to Amend License SNM-1107 and Submittal of SNM-1107 License Application Page Changes ML22259A1802022-09-27027 September 2022 Letter -WEC 2022 DFP Approval MD ML22157A3492022-09-12012 September 2022 Westinghouse Electric Company, LLC - Renewal of Materials License SNM-1107 (Enterprise Project Identifier: L-2017-RNW-0016) ML22249A2252022-09-0606 September 2022 EPA Comments_Columbia Fuels Feis 2022 ML22228A1812022-08-16016 August 2022 Westinghouse, NRC Semi-Annual Discharge Report January - June 2022 ML22217A0422022-08-0505 August 2022 Response Ltr. to Mmitchum, Chief, Pine Hill Indian Tribe, the First People of Fort Jackson Re., Correspondence Related to the Proposed License Renewal for the WEC Cfff in Richland, Sc ML22214A1492022-08-0202 August 2022 Letter to Ms. Michelle Mitchum, Pine Hill Indian Tribe; Re. Westinghouse Cfff ML22215A1952022-08-0202 August 2022 Letter to USNRC and Schpo 8-2-22 from Pine Hill Indian Tribe Re Columbia Fuel Fabrication Facility ML22182A4352022-07-29029 July 2022 Letter to Applicant - Notice of Availability of the Final Environmental Impact Statement for Westinghouse Columbia Fuel Fabrication Facility 2024-01-26
[Table view] |
Text
WESTINGHOUSE NON-PROPRIETARY CLASS 3
@ Westinghouse Westinghouse Electric Company LLC Columbia Fuel Site 5801 BluffRoad Hopkins, South Carolina 29061-9121 USA Chief Fuel Facility Licensing Branch Division of Fuel Direct tel: 803-647-2046 Management Office of Nuclear Material Safety and Safeguards e-mail: malekem@westinghouse.com U. S. Nuclear Regulatory Commission Document Control Desk Your ref:
11555 Rockville Pike Our ref: LTR-RAC-20-63 Rockville, Maryland 20852-2738 July 20, 2020
SUBJECT:
WESTINGHOUSE RESPONSE TO SCHEDULE UPDATE FOR THE LICENSE RENEWAL REVIEW In accordance with the NRC request dated June 30, 2020, Westinghouse Electric Company LLC
("Westinghouse") is providing dates for the Phase II Remedial Investigation Work Plan activities, under the Consent Agreement with the South Carolina Department of Health and Environmental Control
("SCDHEC"), including when the Plan will be submitted to SCDHEC and when the results will be available. Note the structure of the investigation under the Consent Agreement mirrors the Environmental Protection Agency (EPA) Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) process. The results of Phase II investigation will determine the next actions to be completed under the Consent Agreement.
Attachment 1 provides a tentative schedule for the Phase II Remedial Investigation Work Plan activities.
The process provides SCDHEC with multiple opportunities to review, comment on, and ultimately approve each step of the process. The SCDHEC milestone completion dates are presumed based on Westinghouse's understanding of SCDHEC's review process and not firm dates provided by the Department. Also, completion of environmental investigation activities is dependent on the weather and therefore, the schedule is subject to change.
If you have any questions, please contact me at (803) 647-2046.
- ~~
Elise Malek Licensing Manager Westinghouse Columbia Fuel Fabrication Facility Docket 70-1151 License SNM-1107 cc:
Mr. Thomas Vukovinsky Ms. Marilyn Diaz Ms. Jessie Quintero Mr. Andrea Kock Mr. John Tappert Mr. Ken Taylor
© 2020 Westinghouse Electric Company LLC All Rights Reserved
WESTINGHOUSE NON-PROPRIETARY CLASS 3 Page 2 of2 Our ref: LTR-RAC-20-63 July 20, 2020 ATTACHMENT 1 The following schedule provides tentative due dates for key milestones in the Phase II Remedial Investigation activities between Westinghouse and SCDHEC. If activities are completed, faster than outlined below, it is expected that the schedule moves up accordingly.
Tentative Phase II Remedial Investigation Schedule Milestone Comoletion Date Westinghouse submits Remedial Investigation Phase II Work Plan 09/14/2020 SCDHEC reviews and provides comments on the Work Plan 11/2020 Westinghouse resolves comments and submits Final Work Plan 12/2020 SCDHEC annroves Phase II Final Work Plan 01/2021 Westinghouse executes Work Plan and submits Phase II Interim Report 09/2021 SCDHEC reviews and provides comments on the Phase II Interim Report 11 /2021 Westinghouse resolves comments and submits Final Phase II Interim Report 12/2021 SCDHEC approves Final Phase II Remedial Investigation Interim Report 01 /2022