MONTHYEARNRC-2023-0138, Written Statement from the City of Oak Ridge Tennessee for Kairos Power, Hermes 2, Uncontested Hearing Docket2024-09-20020 September 2024 Written Statement from the City of Oak Ridge Tennessee for Kairos Power, Hermes 2, Uncontested Hearing Docket ML24247A1602024-09-0303 September 2024 Kairos - Hermes 2 Docs - Final Environmental Assessment and Finding of No Significant Impact for Kairos Hermes 2 Test Reactors in Oak Ridge, Tennessee ML24246A0142024-08-28028 August 2024 NRR E-mail Capture - Regarding DG-5071 Target Set Identification and Development for Nuclear Power Reactors Access ML24206A0862024-07-24024 July 2024 Construction of Kairos Power, LLC, Hermes 2 Non-Power Test Reactor, Ettp - Project SHPO0004436 ML24206A0842024-07-24024 July 2024 NPS Draft EA Response - Hermes 2 ML24193A2442024-07-11011 July 2024 Transmittal Email for the Summary Report for the Regulatory Audit of the Hermes 2 Preliminary Safety Analysis Report ML24180A1392024-06-28028 June 2024 Kairos - Hermes 2 Docs - Advanced Safety Evaluation for Hermes 2 ML24166A2222024-06-14014 June 2024 Kairos - Hermes 2 Docs - FW FW (External) Re Fw Kairos Power Test Reactor NRC ML24138A2072024-05-17017 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 13 of Hermes 2 SE to ACRS ML24138A1562024-05-17017 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 5 of Hermes 2 SE to ACRS ML24137A2662024-05-15015 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 9 of Hermes 2 SE to ACRS ML24135A2602024-05-14014 May 2024 Transmittal Email for Request for Confirmation of Information 3 for Hermes 2 Preliminary Safety Analysis Report ML24136A0682024-05-10010 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapters (2 & 3) of Hermes 2 SE to ACRS ML24116A1622024-04-25025 April 2024 Kairos - Hermes 2 Docs - Draft Environmental Assessment and Finding of No Significant Impact for Kairos Hermes 2 Test Reactors in Oak Ridge, Tennessee ML24114A2802024-04-23023 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE to ACRS ML24114A2822024-04-23023 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24113A2722024-04-22022 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24105A0002024-04-14014 April 2024 Kairos - Hermes 2 Docs - Environmental Audit Summary Report for Hermes 2 ML24103A1762024-04-12012 April 2024 Transmittal Email from NRC to Kairos Power LLC, Request for Confirmation of Information for the Hermes 2 Preliminary Safety Analysis Report ML24095A2922024-04-0404 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24080A4502024-03-20020 March 2024 Kairos - Hermes 2 Docs - FW Kairos Power Test Reactor NRC ML24074A3712024-03-14014 March 2024 Kairos - Hermes 2 Docs - Preliminary Chapters of Hermes 2 SE ML24072A3162024-03-12012 March 2024 Kairos - Hermes 2 Docs - FW Transmittal of Responses to NRC Requests for Confirmatory Information for the Review of the Hermes 2 Environmental Report (Courtesy Copy) ML24059A3892024-02-28028 February 2024 Kairos - Hermes 2 Docs - Feb 28 2024 Ipac Updated Species List_ Tennessee Ecological Services Field Office (1).pdf ML24057A3872024-02-26026 February 2024 Hermes 2 General Audit Questions 5.2-13, 5.2-14, and 5.2-15 ML24057A4222024-02-26026 February 2024 Kairos - Hermes 2 Docs - RCI Confirmation Message ML24051A2412024-02-20020 February 2024 Kairos - Hermes 2 Docs - Quick Question ML24051A2352024-02-20020 February 2024 Kairos - Hermes 2 Docs - FW HC-1 Status ML24046A1732024-02-15015 February 2024 Hermes 2 General Audit Question 9.3-1 ML24043A2172024-02-12012 February 2024 Hermes 2 General Audit Questions 5.2-10, 5.2-11, and 5.2-12 ML24206A0872024-02-0707 February 2024 Prshpo Section 106 Initiation Response - Hermes 2 ML24033A1812024-02-0202 February 2024 Hermes 2 General Audit Questions 5.2-6, 5.2-7, 5.2-8, and 5.2-9 ML24030A9732024-01-30030 January 2024 Kairos - Hermes 2 Docs - RCI Preview for Hermes 2 Environmental Audit ML24024A2262024-01-24024 January 2024 Hermes 2 General Audit Question 13.1-11 ML24002B1392024-01-0202 January 2024 Hermes 2 General Audit Questions 2.5-2, 2.5-3, 4.3-2, 4.3-3, 4.5-1, 5.1-1, 5.1-2, 5.1-3, 5.2-2, 5.2-3, 5.2-4, 5.2-5, 6.3-1, 9.1-1, 9.1-2, 9.6-1, 13.1-7 Through 10, TR-1, TR-2, TR-3 ML23346A0162023-12-11011 December 2023 Hermes 2 General Audit Questions 3.5-1, 4.3-1, 5.2-1, 7.4-1, 9.8-1, 11.1-1, 13.1-1 Through 13.1-6, 13.2-1, 14.1-1, and 14.1-2 ML23338A2352023-12-0404 December 2023 Hermes 2 General Audit Questions 7.1-2, 7.1-3, 7.1-4, 7.1-5, and 7.2-3 ML23332A0012023-11-28028 November 2023 Public Summary of November 7 Tribal Consultation Response Letter to the NRC ML23317A3682023-11-0606 November 2023 Hermes CP Doc - (External_Sender) Construction of Kairos Power, LLC, Hermes Non-Power Test Reactor, Ettp - Project SHPO0001832 ML23305A0502023-11-0101 November 2023 NRR E-mail Capture - Response to Kairos Request for Non-Public Documents Related to Security ML23307A0552023-11-0101 November 2023 Hermes CP Doc - (External_Sender) Construction of Kairos Power, LLC, Hermes Non-Power Test Reactor, Ettp - Project SHPO0001832 ML23276B3992023-10-0303 October 2023 Email to Kairos Providing the Hermes 2 General Audit Plan ML23274A0062023-10-0101 October 2023 Hermes CP Doc - Public Summary of Sep 14 Meeting with Consulting Tribe NRC-2021-0193, Written Statement from the City of Oak Ridge Tennessee for the October 19, 2023 Evidentiary Hearing for the Kairos Power, LLC, Hermes Test Reactor Construction Permit Application2023-09-22022 September 2023 Written Statement from the City of Oak Ridge Tennessee for the October 19, 2023 Evidentiary Hearing for the Kairos Power, LLC, Hermes Test Reactor Construction Permit Application ML23268A3602023-09-12012 September 2023 Request to Speak Letter from the City of Oak Ridge, Tennessee at the October 19, 2023 Evidentiary Hearing for the Kairos Power, LLC, Hermes Test Reactor Construction Permit Application ML23226A1722023-08-10010 August 2023 NRR E-mail Capture - Hermes Construction Permit Application Mandatory Hearing Resource Estimate ML23185A0042023-07-0404 July 2023 Hermes CP Doc - Submittal of Supplemental Information from Kairos Power_Redacted (8).pdf ML23180A2982023-06-29029 June 2023 Hermes CP Doc - Public Summary of 6-27-23 Email from Consulting Tribe ML23180A2992023-06-29029 June 2023 Hermes CP Doc - FW Email Summary of the April 20 Kairos Submittal ML23177A1972023-06-26026 June 2023 Hermes CP Doc - Public Summary of 6-12-23 Letter from Consulting Tribe 2024-09-03
[Table view] |
Text
From: Edward Helvenston Sent: Friday, January 13, 2023 4:26 PM To: Drew Peebles; Darrell Gardner; Martin Bryan Cc: Benjamin Beasley; Samuel Cuadrado de Jesus; Matthew Hiser; Amitava Ghosh; Jason White
Subject:
General Audit questions for Hermes PSAR Chapter 2 Hello Darrell, Drew, Marty, Please see below for a list of questions the NRC staff has prepared for Kairos related to the Hermes PSAR, specifically, Chapter 2 (Site Characteristics). The NRC staff would like to discuss these within the scope of the General Audit (see audit plan dated 2/10/2022, ADAMS Accession No. ML22039A336), and I am providing these in advance to facilitate discussion during an audit meeting. Once Kairos is ready to discuss, please let us know and we can set up a meeting. We will add this e-mail with questions to public ADAMS. If any questions, please let Ben, Sam, Matt, or I know.
- Thanks, Ed 2.2-6 PSAR Section 2.2.3 references NRC Regulatory Guide (RG) 1.91, Revision 1, Evaluations of Explosions Postulated to Occur on Transportation Routes Near Nuclear Power Plants, dated 1978. However, the staff notes that RG 1.91 was updated as Revision 2, Evaluations of Explosions Postulated to Occur at Nearby Facilities and on Transportation Routes Near Nuclear Power Plants (note different title) in 2013. (RG 1.91 was updated again as Revision 3 in November 2021.) Based on how RG 1.91 methodologies are discussed in the PSAR, it is not clear to the staff whether Kairos intended to reference Revision 1, or a later version.
2.2-7 PSAR Section 2.2.3 references NRC RG 1.78, Evaluating the Habitability of a Nuclear Power Plant Control Room During a Postulated Hazardous Chemical Release. However, the PSAR does not provide a version and it is not clear to the staff which version of this RG Kairos intended to reference.
2.2-8 PSAR Section 2.2.3 references NRC RG 4.7, General Site Suitability Criteria for Nuclear Power Stations. However, the PSAR does not provide a version and it is not clear to the staff which version of this RG Kairos intended to reference.
2.2-9 PSAR Section 2.2, Reference 18, is SHINE Medical Technologies, LLC, SHINE Medical Isotope Production Facility Preliminary Safety Analysis Report. June 2019. However, the staff notes that the final (NRC-approved) revision of the SHINE PSAR is dated October 2015 (ADAMS Accession No. ML15258A431). Please clarify which revision of the SHINE safety analysis report Kairos intended to reference.
2.3-1 PSAR Section 2.3.1.10 states that Based on the data provided in American Society of Civil Engineers (ASCE) Standard No. 7-10 [], Figure 10.4-2, the specification for calculating the ice load on a structural element is: the 500-year mean recurrence interval of uniform ice thickness due to freezing rain for Roane County is 1 inch with a concurrent 3-second wind gust of 30 mph. However, based on its review of ASCE Standard No. 7-10, the staff notes that the standard does not appear to include a Figure 10.4-2. It is not clear to the staff if Kairos intended instead to reference Figure 10-2 of the ASCE standard, and refer to a 50-
year mean recurrence interval.
Ed Helvenston, U.S. NRC Non-Power Production and Utilization Facility Licensing Branch (UNPL)
Division of Advanced Reactors and Non-Power Production and Utilization Facilities (DANU)
Office of Nuclear Reactor Regulation (NRR)
O-6B22 (301) 415-4067
Hearing Identifier: NRR_DRMA Email Number: 1917 Mail Envelope Properties (BY5PR09MB595674E57BE3AE7DFE2ADAF1E0C29)
Subject:
General Audit questions for Hermes PSAR Chapter 2 Sent Date: 1/13/2023 4:26:04 PM Received Date: 1/13/2023 4:26:00 PM From: Edward Helvenston Created By: Edward.Helvenston@nrc.gov Recipients:
"Benjamin Beasley" <Benjamin.Beasley@nrc.gov>
Tracking Status: None "Samuel Cuadrado de Jesus" <Samuel.CuadradoDeJesus@nrc.gov>
Tracking Status: None "Matthew Hiser" <Matthew.Hiser@nrc.gov>
Tracking Status: None "Amitava Ghosh" <Amitava.Ghosh@nrc.gov>
Tracking Status: None "Jason White" <Jason.White@nrc.gov>
Tracking Status: None "Drew Peebles" <peebles@kairospower.com>
Tracking Status: None "Darrell Gardner" <gardner@kairospower.com>
Tracking Status: None "Martin Bryan" <bryan@kairospower.com>
Tracking Status: None Post Office: BY5PR09MB5956.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3175 1/13/2023 4:26:00 PM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: