MONTHYEARNRC-2023-0138, Written Statement from the City of Oak Ridge Tennessee for Kairos Power, Hermes 2, Uncontested Hearing Docket2024-09-20020 September 2024 Written Statement from the City of Oak Ridge Tennessee for Kairos Power, Hermes 2, Uncontested Hearing Docket ML24247A1602024-09-0303 September 2024 Kairos - Hermes 2 Docs - Final Environmental Assessment and Finding of No Significant Impact for Kairos Hermes 2 Test Reactors in Oak Ridge, Tennessee ML24246A0142024-08-28028 August 2024 NRR E-mail Capture - Regarding DG-5071 Target Set Identification and Development for Nuclear Power Reactors Access ML24206A0862024-07-24024 July 2024 Construction of Kairos Power, LLC, Hermes 2 Non-Power Test Reactor, Ettp - Project SHPO0004436 ML24206A0842024-07-24024 July 2024 NPS Draft EA Response - Hermes 2 ML24193A2442024-07-11011 July 2024 Transmittal Email for the Summary Report for the Regulatory Audit of the Hermes 2 Preliminary Safety Analysis Report ML24180A1392024-06-28028 June 2024 Kairos - Hermes 2 Docs - Advanced Safety Evaluation for Hermes 2 ML24166A2222024-06-14014 June 2024 Kairos - Hermes 2 Docs - FW FW (External) Re Fw Kairos Power Test Reactor NRC ML24138A2072024-05-17017 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 13 of Hermes 2 SE to ACRS ML24138A1562024-05-17017 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 5 of Hermes 2 SE to ACRS ML24137A2662024-05-15015 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapter 9 of Hermes 2 SE to ACRS ML24135A2602024-05-14014 May 2024 Transmittal Email for Request for Confirmation of Information 3 for Hermes 2 Preliminary Safety Analysis Report ML24136A0682024-05-10010 May 2024 Kairos - Hermes 2 Docs - Preliminary Chapters (2 & 3) of Hermes 2 SE to ACRS ML24116A1622024-04-25025 April 2024 Kairos - Hermes 2 Docs - Draft Environmental Assessment and Finding of No Significant Impact for Kairos Hermes 2 Test Reactors in Oak Ridge, Tennessee ML24114A2802024-04-23023 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE to ACRS ML24114A2822024-04-23023 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24113A2722024-04-22022 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24105A0002024-04-14014 April 2024 Kairos - Hermes 2 Docs - Environmental Audit Summary Report for Hermes 2 ML24103A1762024-04-12012 April 2024 Transmittal Email from NRC to Kairos Power LLC, Request for Confirmation of Information for the Hermes 2 Preliminary Safety Analysis Report ML24095A2922024-04-0404 April 2024 Kairos - Hermes 2 Docs - Preliminary Chapter of Hermes 2 SE ML24080A4502024-03-20020 March 2024 Kairos - Hermes 2 Docs - FW Kairos Power Test Reactor NRC ML24074A3712024-03-14014 March 2024 Kairos - Hermes 2 Docs - Preliminary Chapters of Hermes 2 SE ML24072A3162024-03-12012 March 2024 Kairos - Hermes 2 Docs - FW Transmittal of Responses to NRC Requests for Confirmatory Information for the Review of the Hermes 2 Environmental Report (Courtesy Copy) ML24059A3892024-02-28028 February 2024 Kairos - Hermes 2 Docs - Feb 28 2024 Ipac Updated Species List_ Tennessee Ecological Services Field Office (1).pdf ML24057A3872024-02-26026 February 2024 Hermes 2 General Audit Questions 5.2-13, 5.2-14, and 5.2-15 ML24057A4222024-02-26026 February 2024 Kairos - Hermes 2 Docs - RCI Confirmation Message ML24051A2412024-02-20020 February 2024 Kairos - Hermes 2 Docs - Quick Question ML24051A2352024-02-20020 February 2024 Kairos - Hermes 2 Docs - FW HC-1 Status ML24046A1732024-02-15015 February 2024 Hermes 2 General Audit Question 9.3-1 ML24043A2172024-02-12012 February 2024 Hermes 2 General Audit Questions 5.2-10, 5.2-11, and 5.2-12 ML24206A0872024-02-0707 February 2024 Prshpo Section 106 Initiation Response - Hermes 2 ML24033A1812024-02-0202 February 2024 Hermes 2 General Audit Questions 5.2-6, 5.2-7, 5.2-8, and 5.2-9 ML24030A9732024-01-30030 January 2024 Kairos - Hermes 2 Docs - RCI Preview for Hermes 2 Environmental Audit ML24024A2262024-01-24024 January 2024 Hermes 2 General Audit Question 13.1-11 ML24002B1392024-01-0202 January 2024 Hermes 2 General Audit Questions 2.5-2, 2.5-3, 4.3-2, 4.3-3, 4.5-1, 5.1-1, 5.1-2, 5.1-3, 5.2-2, 5.2-3, 5.2-4, 5.2-5, 6.3-1, 9.1-1, 9.1-2, 9.6-1, 13.1-7 Through 10, TR-1, TR-2, TR-3 ML23346A0162023-12-11011 December 2023 Hermes 2 General Audit Questions 3.5-1, 4.3-1, 5.2-1, 7.4-1, 9.8-1, 11.1-1, 13.1-1 Through 13.1-6, 13.2-1, 14.1-1, and 14.1-2 ML23338A2352023-12-0404 December 2023 Hermes 2 General Audit Questions 7.1-2, 7.1-3, 7.1-4, 7.1-5, and 7.2-3 ML23332A0012023-11-28028 November 2023 Public Summary of November 7 Tribal Consultation Response Letter to the NRC ML23317A3682023-11-0606 November 2023 Hermes CP Doc - (External_Sender) Construction of Kairos Power, LLC, Hermes Non-Power Test Reactor, Ettp - Project SHPO0001832 ML23305A0502023-11-0101 November 2023 NRR E-mail Capture - Response to Kairos Request for Non-Public Documents Related to Security ML23307A0552023-11-0101 November 2023 Hermes CP Doc - (External_Sender) Construction of Kairos Power, LLC, Hermes Non-Power Test Reactor, Ettp - Project SHPO0001832 ML23276B3992023-10-0303 October 2023 Email to Kairos Providing the Hermes 2 General Audit Plan ML23274A0062023-10-0101 October 2023 Hermes CP Doc - Public Summary of Sep 14 Meeting with Consulting Tribe NRC-2021-0193, Written Statement from the City of Oak Ridge Tennessee for the October 19, 2023 Evidentiary Hearing for the Kairos Power, LLC, Hermes Test Reactor Construction Permit Application2023-09-22022 September 2023 Written Statement from the City of Oak Ridge Tennessee for the October 19, 2023 Evidentiary Hearing for the Kairos Power, LLC, Hermes Test Reactor Construction Permit Application ML23268A3602023-09-12012 September 2023 Request to Speak Letter from the City of Oak Ridge, Tennessee at the October 19, 2023 Evidentiary Hearing for the Kairos Power, LLC, Hermes Test Reactor Construction Permit Application ML23226A1722023-08-10010 August 2023 NRR E-mail Capture - Hermes Construction Permit Application Mandatory Hearing Resource Estimate ML23185A0042023-07-0404 July 2023 Hermes CP Doc - Submittal of Supplemental Information from Kairos Power_Redacted (8).pdf ML23180A2982023-06-29029 June 2023 Hermes CP Doc - Public Summary of 6-27-23 Email from Consulting Tribe ML23180A2992023-06-29029 June 2023 Hermes CP Doc - FW Email Summary of the April 20 Kairos Submittal ML23177A1972023-06-26026 June 2023 Hermes CP Doc - Public Summary of 6-12-23 Letter from Consulting Tribe 2024-09-03
[Table view] |
Text
From: Giacinto, Joseph Sent: Tuesday, January 25, 2022 8:01 AM To: Dozier, Tami; Doub, Peyton
Subject:
RE: Summary of Phone Conversation with Patrick Berge Attachments: Kairos NRC application for ETTP - COR water supply and treatment capacities Tami and Peyton, Below is a summary of my January 21, 2022 phone conversation with Patrick Berge, Interim Director & Utility Manager, City of Oakridge Public Works. The notes below reference the attached email.
Joe Phone conversation started at approximately 11:45 am, 1/21/2022. During the call, I noted that I was following up on a 1/19/2022 email related to questions of waste water treatment and municipal supply capacities. I provided background on the Kairos application for NRC and the process of the staffs review of the environmental report (ER) provided to NRC by Kairos as part of the application. In particular, I noted that my review of water resources required a review a wastewater treatment and water supply issues as documented in the ER.
Patrick indicated that the Kairos facility would be treated like any other ETTP tenant with available connections to WTTP plant and municipal water supply services. There is an upper limit to WW discharge service, but it high something like 20,000 gpd (he was unsure of this number), but as he recalled that the Kairos facility wouldnt be using a significant amount of water. The City would have no trouble servicing the water even in wet weather when water becomes especially diluted with rainwater, it presents no problems. There would be no trouble servicing the WW. Since an effort began to limit unnecessary WW entering the system, the treatment volumes have steadily decreased potentially doubling the treatment capacity. Many of the old lines of WWII era age and collecting unnecessary rainwater/seepage. One effort in the K-25 area to plug and cap many of the inflow points to these types of lines have resulted in quite a bit of progress in limiting the unnecessary inflow to the WWTP. Rainwater was/is the primary volume of WWTP inflows.
The current municipal water supply plant is typically producing approximately 7/8 mgd with a capacity closer to 16 mgd and could likely produce 20 mgd maximum. New plant (which is currently funded with the City to shortly seek construction bids), will have ability to produce above 20 mgd maximum with a targeted construction starting date sometime during 2024.
Asked about the ability to the City to service large reserves required for the Kairos fire suppression system as described in the ER, Patrick noted that arrangements could be made to accommodate large reserves like that of the Kairos suppression system. I noted that I need further information on the Kairos system to determine the configuration of the fire suppression system (e.g., holding tank volumes, reserve tanks, frequency of refilling, etc.)
I noted that the fuel fabrication facility is mentioned in the ER and is planned for the site area at some point in the future; however, I was unsure of the WWTP and/or supply demands of that proposed facility at this point. I noted that the City should feel free to contact NRC if any questions or comments arise and Patrick welcomed further inquiries through his office from NRC as needed. Call ended at approximately 12:05 pm.
Hearing Identifier: KairosPower_CPDocs_NonPublic Email Number: 3 Mail Envelope Properties (SA0PR09MB6570208DC92A317BA78EA4F8E05F9)
Subject:
RE: Summary of Phone Conversation with Patrick Berge Sent Date: 1/25/2022 8:01:12 AM Received Date: 1/25/2022 8:01:13 AM From: Giacinto, Joseph Created By: Joseph.Giacinto@nrc.gov Recipients:
"Dozier, Tami" <Tamsen.Dozier@nrc.gov>
Tracking Status: None "Doub, Peyton" <Peyton.Doub@nrc.gov>
Tracking Status: None Post Office: SA0PR09MB6570.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3070 1/25/2022 8:01:13 AM Kairos NRC application for ETTP - COR water supply and treatment capacities 16295 Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: