MONTHYEARML20202A6782020-07-20020 July 2020 Westinghouse Response to Schedule Update for the License Renewal Review Project stage: Other ML20259A1792020-07-30030 July 2020 Final Interim Remedial Investigation Data Summary Report Westinghouse Columbia Fuel Fabrication Facility Project stage: Request ML20294A0562020-07-30030 July 2020 Westinghouse Columbia Fuel Fabrication Facility Hf Spiking Station 1 Assessment Report Project stage: Request ML20259A2212020-07-30030 July 2020 Fuel Fabrication Facility Technetium (Tc-99) Source Investigation Report Project stage: Request ML20275A2512020-11-0303 November 2020 Letter to Westinghouse with RAIs Regarding Environmental Review for Proposed Renewal of Cfff License Project stage: RAI ML20353A2802020-12-18018 December 2020 Enclosure 4 - Response to Request for Additional Information - Phase II Remedial Investigation Work Plan Project stage: Response to RAI ML21026A0622021-01-28028 January 2021 Letter: Revised EIS Schedule to WEC-January 2021 Project stage: Other ML21102A0692021-04-0606 April 2021 Westinghouse Columbia Fuel Fabrication Facility License Renewal Environmental Commitments Project stage: Other ML21138A9262021-05-28028 May 2021 Westinghouse EIS Schedule Letter Project stage: Other ML21263A2172021-09-20020 September 2021 Submittal of Westinghouse Revised SNM-1107 License Renewal Application Project stage: Other ML21263A2182021-09-20020 September 2021 SNM-1107 License Renewal Application Project stage: Other ML22033A0712022-02-18018 February 2022 Westinghouse License Renewal RAIs (Environmental) Memo (Public) Project stage: RAI ML22052A0122022-02-21021 February 2022 Response to NRC Request for Additional Information Associated with the SNM-1107 License Renewal Environmental Impact Statement Project stage: Response to RAI ML22080A2822022-03-21021 March 2022 Westinghouse, Response to NRC Request for Additional Information Associated with the SNM-1107 License Renewal Environmental Impact Statement Project stage: Response to RAI ML22094A0972022-04-19019 April 2022 Westinghouse Schedule Extension Letter Project stage: Other ML22157A3482022-09-12012 September 2022 Westinghouse License Renewal Project stage: Request ML22157A3492022-09-12012 September 2022 Westinghouse Electric Company, LLC - Renewal of Materials License SNM-1107 (Enterprise Project Identifier: L-2017-RNW-0016) Project stage: Other 2021-05-28
[Table View] |
|
---|
Category:Letter
MONTHYEARML24023A6952024-01-26026 January 2024 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 07001151/2023004 ML24017A2252024-01-22022 January 2024 Westinghouse Electric Company, LLC, Conveyance of Revised Standby Trust Agreement to Support the Decommissioning Funding Plan (Enterprise Project Identifier L-2023-DFA-0009) ML23349A2722023-12-14014 December 2023 Westinghouse, Submittal of Monthly Progress Reports Under Consent Agreement 19-02-HW with the South Carolina Department of Health and Environmental Control ML23338A3372023-12-0404 December 2023 Submittal of Amendment 4 to Standby Trust Agreement (STA) for License Nu. SNM-1107, Replacement of Trust Fund with Additional Surety Bonds, and Certification of Financial Assurance for SNM-1107 ML23311A0032023-11-0606 November 2023 Westinghouse Columbia Fuel Fabrication Facility, U.S. Nuclear Regulatory Commission Inspection Report Number 70-1151/2023-402 (Cover Letter) ML23296A0362023-10-24024 October 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023003 ML23240A5082023-08-28028 August 2023 Westinghouse Electric Company LLC - NRC Semi-Annual Discharge Report (January- June 2023) ML23230B2022023-08-18018 August 2023 Westinghouse, Supplemental Information for Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23216A0712023-08-0404 August 2023 Westinghouse Columbia Fuel Fabrication Facility Physical Security Core Inspection Report 07001151/202340 ML23202A1472023-07-24024 July 2023 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2023002 ML23150A2362023-07-0303 July 2023 Letter to Westinghouse Regarding Effluent Testing Issue ML23184A1512023-06-29029 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report Revision ML23171B1502023-06-20020 June 2023 Westinghouse Columbia Fuel 2023 Special Nuclear Material Inventory Summary Report ML23160A2612023-06-0909 June 2023 Westinghouse, Request for Modification to Temporary License Conditions for Sampling, Analysis and Disposition of Hematite Ash Material ML23139A1942023-06-0505 June 2023 Westinghouse Electric Company LLC - Approval of Environmental Sampling and Monitoring Program ML23138A3762023-05-18018 May 2023 Westinghouse Submittal of Columbia Fuel Fabrication Facility Site Emergency Plan, Revision 23 ML23096A2812023-05-15015 May 2023 Letter - Transfer of Control Approval 2023 ML23094A1582023-05-0505 May 2023 Westinghouse Electric Company, LLC - Revision to Temporarily Store Hematite Ash Above License Limits and Removal of Uranium Flywheel ML23115A2382023-04-26026 April 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151/2023001 ML23114A3592023-04-24024 April 2023 Westinghouse Submittal of Environmental Sampling and Monitoring Program for NRC Review and Approval ML23114A3612023-03-23023 March 2023 Enclosures 2 & 3 - SCDHEC Approval Letter of Westinghouse Ri Report, Dated March 23, 2023 and Environmental Sampling and Monitoring Program Section of SNM-1107 License Application ML23058A4482023-02-27027 February 2023 Request for Threshold Determination for Interim Transaction Included in December 20, 2022 Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals ML23058A2722023-02-27027 February 2023 Westinghouse, NRC Semiannual Discharge Report July - December 2022 ML23053A0712023-02-17017 February 2023 Westinghouse Electric Company LLC, Supplement to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23053A0752023-02-17017 February 2023 Westinghouse Electric Co. - Supplement 2 to Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML23047A4562023-02-16016 February 2023 Westinghouse, Response to Request for Additional Information - Request for Temporary License Amendment for Storage of Hematite Ash ML23030B8552023-01-30030 January 2023 Westinghouse 10CFR70.72 Facility Change Report ML23024A2312023-01-30030 January 2023 Westinghouse Columbia Fuel Fabrication Facility - Integrated Inspection Report 07001151//2022004 ML23013A2122023-01-27027 January 2023 Acceptance Letter for Westinghouse License Transfer - Cac/Epid L-2022-LLM-0004 ML23026A3642023-01-26026 January 2023 Westinghouse, January 2023 Updated Integrated Safety Analysis Summary ML22354A0732023-01-19019 January 2023 Response to Westinghouse Revised Funding Instrument in Support of the Decommissioning Funding Plan ML22363A0152022-12-29029 December 2022 Westinghouse Electric Co - 60-Day Report Regarding the November 1, 2022, Incident Reported Under 10 CFR 70 Appendix a 24-Hr Report, Columbia Fuel Fabrication Facility (License No. SNM-1107, Docket No. 70-1151) ML22354A2912022-12-20020 December 2022 Application for Consent to Indirect Change of Control with Respect to a Materials License, Export Licenses, and Notification Regarding Other Approvals and Request for Threshold Determination ML22347A1162022-12-13013 December 2022 Westinghouse 2021-2022 Annual Groundwater Monitoring Report ML22336A1742022-12-0202 December 2022 Westinghouse Request for Temporary License Amendment for Storage of Hematite Ash ML22316A0052022-11-10010 November 2022 Westinghouse Electric Company LLC, Submittal of Amendment to Trust Agreement for License Number SNM-1107, Surety Bond Rider for SNM-1107, and Certification of Financial Assurance for SNM-1107 (Proprietary/Non-Proprietary) ML22298A0432022-10-28028 October 2022 Westinghouse Columbia Fuel Fabrication Facility Integrated Inspection Report 07001151/2022003 ML22294A1792022-10-21021 October 2022 Westinghouse, Request to Amend License SNM-1107 and Submittal of SNM-1107 License Application Page Changes ML22259A1802022-09-27027 September 2022 Letter -WEC 2022 DFP Approval MD ML22157A3492022-09-12012 September 2022 Westinghouse Electric Company, LLC - Renewal of Materials License SNM-1107 (Enterprise Project Identifier: L-2017-RNW-0016) ML22249A2252022-09-0606 September 2022 EPA Comments_Columbia Fuels Feis 2022 ML22228A1812022-08-16016 August 2022 Westinghouse, NRC Semi-Annual Discharge Report January - June 2022 ML22217A0422022-08-0505 August 2022 Response Ltr. to Mmitchum, Chief, Pine Hill Indian Tribe, the First People of Fort Jackson Re., Correspondence Related to the Proposed License Renewal for the WEC Cfff in Richland, Sc ML22214A1492022-08-0202 August 2022 Letter to Ms. Michelle Mitchum, Pine Hill Indian Tribe; Re. Westinghouse Cfff ML22215A1952022-08-0202 August 2022 Letter to USNRC and Schpo 8-2-22 from Pine Hill Indian Tribe Re Columbia Fuel Fabrication Facility ML22182A4352022-07-29029 July 2022 Letter to Applicant - Notice of Availability of the Final Environmental Impact Statement for Westinghouse Columbia Fuel Fabrication Facility 2024-01-26
[Table view] Category:Schedule and Calendars
MONTHYEARML22187A1882022-07-0606 July 2022 Fuel Fabrication Facility - Inspection Schedule for Calendar Year 2023 ML22094A0972022-04-19019 April 2022 Westinghouse Schedule Extension Letter ML21306A3642021-11-29029 November 2021 Westinghouse License Renewal Schedule Change Letter ML21138A9262021-05-28028 May 2021 Westinghouse EIS Schedule Letter ML21026A0622021-01-28028 January 2021 Letter: Revised EIS Schedule to WEC-January 2021 ML20189A2552020-07-0202 July 2020 2021 Westinghouse Inspection Schedule Letter ML18176A2052018-06-25025 June 2018 2019 West Inspection Schedule (Non-Safeguards) 2022-07-06
[Table view] |
Text
April 19, 2022 Patrick Donnelly Licensing Manager Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, SC 29061-9121 USA
SUBJECT:
WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM-1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)
Dear Patrick Donnelly:
The U.S. Nuclear Regulatory Commission (NRC) staff has revised the schedule for its review of Westinghouse Electric Company, LLCs (WECs) license renewal application for its Columbia Fuel Fabrication Facility in Hopkins, South Carolina. As noted in our February 18, 2022 letter (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22033A071) conveying requests for additional information (RAI), the NRC, upon receiving complete RAI responses, has revised its licensing review schedule. Westinghouse provided the RAI responses in three submittals dated February 21, March 15 and March 21, 2022, respectively. The attached revised schedule reflects the RAIs issued in February 2022 and the State Historic Preservation Offices (SHPO) review and final approval of the cultural resources survey report conducted by WEC.
The NRC staff plans to publish the final environmental impact statement in July 2022, pending approval of the final cultural resources survey report from the SHPO and a determination that the historic properties evaluated in the report are not eligible for listing on the National Register of Historic Places. In August 2022, the staff plans to issue the safety evaluation report and the record of decision. These projected dates are with the understanding that WEC will provide follow-up clarification on one remaining item by May 2, 2022, and with the assumption that the SHPO review and final approval of the Cultural Resources Survey Report will happen by May 16, 2022.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this communication will be available electronically for public inspection in the NRC Public Document Room (PDR), or from the NRCs ADAMS. The PDR is open by appointment only. You may submit your request to the PDR via e-mail at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST),
Monday through Friday, except Federal holidays. ADAMS is accessible from the NRC Web site at: http://www.nrc.gov/reading-rm/adams.html
P. Donnelly 2 If you have any questions regarding the license renewal review, please contact me at 301-415-2328 or via e-mail at Jennifer.Tobin@nrc.gov.
Sincerely, Jenny Tobin, Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 70-1151 License No.: SNM-1107
Enclosure:
Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule cc: K. Taylor, South Carolina DHEC westinghouse_ff@listmgr.nrc.gov
P. Donnelly 3
SUBJECT:
WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM-1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)
DATE: April 19, 2022 DISTRIBUTION:
Public DFM r/f JTappert, NMSS TVukovinsky, RII LWilkins, OCA JTrefethen, NMSS CRegan, NMSS TInverso, NMSS SImboden, NMSS SHelton, NMSS EMichel, RII DMcIntyre, OPA PJehle, OGC ADAMS Accession Number: ML22094A097 NMSS/REFS/ NMSS/DFM/ NMSS/REFS/ NMSS/DFM/ NMSS/DFM/
OFFICE ERMB/PM FFLB/LA ERMB/BC FFLB/PM FFLB/BC JPark acting NAME SImboden ELee JTobin JZimmerman for JQuintero DATE 4/18/22 4/19/22 4/18/22 4/18/22 4/19/2022 OFFICIAL RECORD COPY
Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule Docket 70-1151 License SNM -1107 Milestone Previous Date Revised Date Notice of Intent to prepare an July 31, 2020(A) July 31, 2020(A) environmental impact statement (EIS) and begin the scoping process published in the Federal Register (85 FR 46193)
End of 30-day scoping comment period August 31, 2020(A) August 31, 2020(A)
Issuance of NRCs Requests for Additional November 3, 2020(A) November 3, 2020 (A)
Information (RAIs)
Westinghouse Electric Companys December 18, 2020 December 18, 2020(A)
(WECs) Responses to NRCs RAIs (A)
Publication of draft EIS 1 for a 45-day July 2021(A) July 2021(A) comment period Issuance of NRCs RAIs February 18, 2022(A)
WECs Responses to NRCs RAIs February 21, 2022 March 15, 2022 March 21, 2022(A)
Publication of the final EIS April 2022 (T) July 2022(T)
Record of Decision 2 and Licensing June 2022(T) August 2022(T)
Decision (T) - Target (A) - Actual 1 The draft EIS anticipated publication date assumed a 30-day RAI response time.
2 The NRC, per 10 CFR 51.100(a)(ii), must wait 30 days after publication of the U.S. Environmental Protection Agencys Federal Register Notice announcing the issuance of the final EIS.