Westinghouse Schedule Extension Letter
ML22094A097
Person / Time
Site: Westinghouse
Issue date: 04/19/2022
From: Jennifer Tobin
NRC/NMSS/DFM/FFLB
To: Donnelly P
Westinghouse Columbia Fuel Fabrication
J TOBIN NRC/NMSS/DFM/FFLB 3014152328
References
EPID L-2017-RNW-0016
Download: ML22094A097 (4)


Text

April 19, 2022 Patrick Donnelly Licensing Manager Westinghouse Columbia Fuel Fabrication 5801 Bluff Road Hopkins, SC 29061-9121 USA

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM-1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)

Dear Patrick Donnelly:

The U.S. Nuclear Regulatory Commission (NRC) staff has revised the schedule for its review of Westinghouse Electric Company, LLCs (WECs) license renewal application for its Columbia Fuel Fabrication Facility in Hopkins, South Carolina. As noted in our February 18, 2022 letter (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22033A071) conveying requests for additional information (RAI), the NRC, upon receiving complete RAI responses, has revised its licensing review schedule. Westinghouse provided the RAI responses in three submittals dated February 21, March 15 and March 21, 2022, respectively. The attached revised schedule reflects the RAIs issued in February 2022 and the State Historic Preservation Offices (SHPO) review and final approval of the cultural resources survey report conducted by WEC.

The NRC staff plans to publish the final environmental impact statement in July 2022, pending approval of the final cultural resources survey report from the SHPO and a determination that the historic properties evaluated in the report are not eligible for listing on the National Register of Historic Places. In August 2022, the staff plans to issue the safety evaluation report and the record of decision. These projected dates are with the understanding that WEC will provide follow-up clarification on one remaining item by May 2, 2022, and with the assumption that the SHPO review and final approval of the Cultural Resources Survey Report will happen by May 16, 2022.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this communication will be available electronically for public inspection in the NRC Public Document Room (PDR), or from the NRCs ADAMS. The PDR is open by appointment only. You may submit your request to the PDR via e-mail at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST),

Monday through Friday, except Federal holidays. ADAMS is accessible from the NRC Web site at: http://www.nrc.gov/reading-rm/adams.html

P. Donnelly 2 If you have any questions regarding the license renewal review, please contact me at 301-415-2328 or via e-mail at Jennifer.Tobin@nrc.gov.

Sincerely, Jenny Tobin, Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 70-1151 License No.: SNM-1107

Enclosure:

Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule cc: K. Taylor, South Carolina DHEC westinghouse_ff@listmgr.nrc.gov

P. Donnelly 3

SUBJECT:

WESTINGHOUSE ELECTRIC COMPANY, LLC - REVISED SCHEDULE FOR RENEWAL REVIEW OF MATERIALS LICENSE SNM-1107 (ENTERPRISE PROJECT IDENTIFIER L-2017-RNW-0016)

DATE: April 19, 2022 DISTRIBUTION:

Public DFM r/f JTappert, NMSS TVukovinsky, RII LWilkins, OCA JTrefethen, NMSS CRegan, NMSS TInverso, NMSS SImboden, NMSS SHelton, NMSS EMichel, RII DMcIntyre, OPA PJehle, OGC ADAMS Accession Number: ML22094A097 NMSS/REFS/ NMSS/DFM/ NMSS/REFS/ NMSS/DFM/ NMSS/DFM/

OFFICE ERMB/PM FFLB/LA ERMB/BC FFLB/PM FFLB/BC JPark acting NAME SImboden ELee JTobin JZimmerman for JQuintero DATE 4/18/22 4/19/22 4/18/22 4/18/22 4/19/2022 OFFICIAL RECORD COPY

Westinghouse Electric Company, LLC Columbia Fuel Fabrication Facility Revised License Renewal Schedule Docket 70-1151 License SNM -1107 Milestone Previous Date Revised Date Notice of Intent to prepare an July 31, 2020(A) July 31, 2020(A) environmental impact statement (EIS) and begin the scoping process published in the Federal Register (85 FR 46193)

End of 30-day scoping comment period August 31, 2020(A) August 31, 2020(A)

Issuance of NRCs Requests for Additional November 3, 2020(A) November 3, 2020 (A)

Information (RAIs)

Westinghouse Electric Companys December 18, 2020 December 18, 2020(A)

(WECs) Responses to NRCs RAIs (A)

Publication of draft EIS 1 for a 45-day July 2021(A) July 2021(A) comment period Issuance of NRCs RAIs February 18, 2022(A)

WECs Responses to NRCs RAIs February 21, 2022 March 15, 2022 March 21, 2022(A)

Publication of the final EIS April 2022 (T) July 2022(T)

Record of Decision 2 and Licensing June 2022(T) August 2022(T)

Decision (T) - Target (A) - Actual 1 The draft EIS anticipated publication date assumed a 30-day RAI response time.

2 The NRC, per 10 CFR 51.100(a)(ii), must wait 30 days after publication of the U.S. Environmental Protection Agencys Federal Register Notice announcing the issuance of the final EIS.

Enclosure