MONTHYEARML24177A1412024-06-11011 June 2024 NRR E-mail Capture - Audit Plan Related to Review of the Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, LAR to Revise Technical Specification Table 3.3.2-1 Function 5 ML24152A1542024-05-31031 May 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-03 ML24128A1802024-05-0707 May 2024 NRR E-mail Capture - Acceptance Review for Sequoyah License Amendment Request to Modify TS 3.8.1 and TS 3.8.2 (L-2024-LLA-0047) ML24123A0882024-05-0202 May 2024 NRR E-mail Capture - Correction Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24122B4872024-04-30030 April 2024 NRR E-mail Capture - Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24144A2322024-04-20020 April 2024 Tennessee Multi-Sector Permit (Tmsp), 2024 Annual Discharge Monitoring Report for Outfalls SW-3, SW-3, and SW-9 ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24074A4252024-03-14014 March 2024 NRR E-mail Capture - Sequoyah Hydrologic Analysis License Amendment Request - Notification of Change to Estimated Completion and Hours ML24059A4052024-02-28028 February 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-02 ML24053A0302024-02-21021 February 2024 NRR E-mail Capture - Request for Steam Generator (SG) Tube Inspection Call for Sequoyah, Unit 1 ML24047A2792024-02-15015 February 2024 RAI Related to the Exemption Request for 10 CFR 37.11 ML24045A1002024-02-13013 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Sequoyah Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML24036A0132024-01-23023 January 2024 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar Nuclear Plants, License Amendment Request to Revise TS Table 3.3.2-1, Function 5, Turbine Trip and Feedwater Isolation ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23165A2862023-06-14014 June 2023 Tennessee Multi-Sector Permit (Tmsp), 2023 Annual Discharge Monitoring Report for Outfalls SW-1, SW-16, SW-17, SW-18, SW-19, and SW-21 ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23062A5952023-02-27027 February 2023 Staff follow-up Questions to Tva'S 12/19/2022 Response of the Staff'S Rsi Regarding 08/04/2022 SQN Exemption Request ML23058A1312023-02-27027 February 2023 FW: TVA Intentions on EA-22-129 ML23052A0792023-02-21021 February 2023 NRR E-mail Capture - Acceptance Review for Browns Ferry and Sequoyah License Amendment Request to Adopt TSTF-541 ML23046A3552023-02-15015 February 2023 Annual Water Withdrawal Report 2022 ML23019A3442023-01-19019 January 2023 Tennessee Multi-Sector Permit (Tmsp), 2022 Annual Discharge Monitoring Report for Outfalls SW-1, SW-16, and SW-19 ML23013A0362023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML23013A0382023-01-12012 January 2023 NRR E-mail Capture - (External_Sender) State Consultation for Alabama - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML23026A0282023-01-12012 January 2023 001 Radiation Safety Baseline Inspection Information Request ML22348A0972022-12-14014 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-529, Revision 4 (L-2022-LLA-0088) ML22348A0442022-12-13013 December 2022 NRR E-mail Capture - State Consultation - Browns Ferry, Units 1, 2 and 3; Sequoyah, Units 1 and 2; and Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-554-A, Revision 1 (L-2022-LLA-0100) ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22348A0432022-11-28028 November 2022 NRR E-mail Capture - State Consultation - Sequoyah Nuclear Plant, Units 1 and 2, License Amendment Request to Modify the Approved 10 CFR 50.69 Categorization Process (L-2022-LLA-0033) ML22227A0712022-08-15015 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 (EPID L-2022-LLA-0103) - Corrected ML22227A0262022-08-12012 August 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar License Amendment Request to Revise TS 3.4.12 ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22215A2752022-08-0303 August 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-554 ML22214A1582022-08-0202 August 2022 NRR E-mail Capture - Request for Additional Information for Sequoyah Units 1 and 2 License Amendment Request for Fire and Seismic PRA Modification to 10 CFR 50.69 (L-2022-LLA-0033) ML22196A0732022-07-15015 July 2022 NRR E-mail Capture - (External_Sender) State Notification for Sequoyah Units 1 and 2 Amendment Issuance - TSTF-505 RICT (L-2021-LLA-0145) ML22194A8762022-07-13013 July 2022 NRR E-mail Capture - Acceptance Review Results for TVA Fleet License Amendment Request to Adopt TSTF-529 ML22173A0332022-06-17017 June 2022 NRR E-mail Capture - (External_Sender) State Notification for Sequoyah Units 1 and 2 Amendment Issuance - Reactor Trip System Instrumentation (L-2021-LLA-0200) ML22166A4292022-06-0606 June 2022 NRR E-mail Capture - LAR to Adopt TSTF-577 ML22151A0102022-05-27027 May 2022 NRR E-mail Capture - Revised Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3322022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Related to Sequoyah Nuclear Plant'S LAR to Adopt TSTF-505 ML22151A0092022-05-26026 May 2022 NRR E-mail Capture - Request for Additional Information Re Sequoyah Nuclear Plant Alternative Request RV-02 ML22146A3342022-05-25025 May 2022 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Relief Requests (EPID L-2022-LLR-0045 - 0047) ML22137A2692022-05-17017 May 2022 Notice of Termination, TNR192066, Gravel Lot Restoration Project ML22136A0182022-05-16016 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, Alternative Request RP-11 and Watts Bar Nuclear Plant, Units 1 and 2, Alternative Request IST-RR-9 ML22132A1762022-05-12012 May 2022 Tennessee Multi-Sector Permit (Tmsp), 2021 Annual Discharge Monitoring Report for Outfalls SW-2, SW-3, SW-4, SW-6, SW-8, SW-9, and SW-13 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to Tva'S Request to Revised the TVA Plants' Radiological Emergency Plans ML22123A1812022-05-0303 May 2022 NRR E-mail Capture - Acceptance Review Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-577 ML22095A0182022-04-0404 April 2022 NRR E-mail Capture - Sequoyah Nuclear Plant - Acceptance of Request for Alternative - Pressure Isolation Valve Leakage ISTC-3630 (L-2022-LLR-0034) 2024-06-11
[Table view] |
Text
From: Wentzel, Michael Sent: Thursday, April 8, 2021 7:57 AM To: Orf, Tracy J Cc: Taylor, Andrew Charles; Wrona, David
Subject:
Sequoyah Nuclear Plant, Units 1 and 2 - Acceptance of CRDM Canopy Weld Alternative Request (EPID L-2021-LLR-0019)
Dear Mr. Orf,
By letter dated March 26, 2021 (Agencywide Documents Access and Management System Accession No. ML21085A764), the Tennessee Valley Authority (the licensee) submitted a relief request for Sequoyah Nuclear Plant, Units 1 and 2. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The NRC staff performs acceptance reviews of applications to determine if the scope and depth of technical information is sufficient for the staff to complete its technical reviews. The acceptance reviews also intend to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Pursuant to Sections 50.55a(z)(1) and 50.55a(z)(2) of Title 10 of the Code of Federal Regulations (10 CFR), the applicant shall demonstrate that the proposed alternatives would provide an acceptable level of quality and safety, or that compliance with the specified requirements of Section 50.55a would result in hardship or unusual difficulty without a compensating increase in the level of quality or safety.
The NRC staff has concluded that the licensees submittal provides technical information in sufficient detail to enable the staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which the NRC staff identifies issues that affect its ability to complete the detailed technical review despite completion of an adequate acceptance review. If the NRC staff needs additional information, it will notify the licensee by separate correspondence.
The staff has estimated that it will take approximately 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br /> to complete this licensing request and that it will complete its review within one year of acceptance of the application (i.e., by April 2022).
These estimates are based on the NRC staffs initial review of the application and could change because of several factors, such as requests for additional information, unanticipated addition of application scope, review by NRC advisory committees, or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance of or in parallel with industry program initiatives or pilot applications. If complexities or challenges during the review cause significant changes to the estimated hours or completion date, the assigned project manager will communicate the new estimates and reasons for the changes to the licensee during routine interactions.
If you have any questions, please contact me at (301) 415-6459 or michael.wentzel@nrc.gov.
Sincerely, Michael J. Wentzel, Project Manager Plant Licensing Branch II-2
Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Hearing Identifier: NRR_DRMA Email Number: 1112 Mail Envelope Properties (BLAPR09MB7267D86CD209D5A5F1030A0FE7749)
Subject:
Sequoyah Nuclear Plant, Units 1 and 2 - Acceptance of CRDM Canopy Weld Alternative Request (EPID L-2021-LLR-0019)
Sent Date: 4/8/2021 7:56:56 AM Received Date: 4/8/2021 7:56:56 AM From: Wentzel, Michael Created By: Michael.Wentzel@nrc.gov Recipients:
"Taylor, Andrew Charles" <actaylor@tva.gov>
Tracking Status: None "Wrona, David" <David.Wrona@nrc.gov>
Tracking Status: None "Orf, Tracy J" <tjorf@tva.gov>
Tracking Status: None Post Office: BLAPR09MB7267.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3157 4/8/2021 7:56:56 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: