Summary of 970826 Telcon W/Westinghouse Re AP600 Emergency Response Guidelines.Summary of Actions from Telcon Listed. List of Telcon Participants Encl
ML20210Q764
Person / Time
Site: 05200003
Issue date: 08/28/1997
From: Huffman W
NRC (Affiliation Not Assigned)
To:
NRC (Affiliation Not Assigned)
References
NUDOCS 9709020142
Download: ML20210Q764 (4)


Text

_ _ - -- - - - - - - -

arg t UNITED STATES gf ' )

s (- ,j- NUCLEAR REGULATORY COMMISSION

% g WASHINGTON, D.C. 3068H001

'% # August 28, 1997 APPLICANT: Westinghouse Electric Corporation PROJECT: AP600

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE TO DISCUSS WESTINGHOUSE RESPONSES TO AP600 EMERGENCY RESPONSE GUIDELINE COMMENTS On August 26, 1997, the Nuclear Regulatory Comission (NRC) staff, an NRC contractor, and Westinghouse (see Attachment) conducted a telephone conference-(telecon) concerning the AP600 Emergency Response Guidelines (ERGS). NRC

- coments on the ERGS were provided to Westinghouse via NRC letters dated February 6, March 13, and April 9,1997. Westinghouse subsequently revised the ERGS and the Adverse System Interactions (ASI) evaluation report to address the NRC coments. The purpose of the telecon was to discuss how the NRC coments were addressed in the revised ERGS.

The following is a sumary of actions from the telecon:

Westinghouse agreed to formally document its responses to the three NRC ERG coment letters.

Westinghouse will revise the introduction to the ERG background document to discuss the need for the E0P writers to identify the continuous action steps. Westinghouse will provide some examples of ERG steps which are subject to continuous action.

Westinghouse will revise the introduction to the ERG background document to explain what is meant by the statement " Evaluate Long Term Plant h

Status" which appears in a number of ERGS. -This discussion will include g

the COL applicants development of an accident management plan and its relationship to the ERGS /EOPs. 3 Westinghouse will place a statement in the introduction to the ERG background document which directs the E0P writer to consider the insights identified in Chapter 3 of the ASI report, WCAP-14477.

Westinghouse will include a discussion in its response to coment #1 of the NRC February 6,1997, letter which will address that adverse interactions from the pressurizer spray and reactor head vent were reviewed but that no interactions were found.

Westinghouse will revise ERG procedures-AES-0.1 and AES-0.2 as comented in its response to coment #7 of the February 6,1997, NRC letter.

Westinghouse will revise its response to coment #8 of the NRC Febru-ary 6, 1997, letter by noting that the ERG background document discusses the role of automatic trip of the pressurizer heaters.

I2 iN llIlllllkll), l, l oy.f77 9709020142 970828 8 PDR ADOCK 05200003 A PDR

=; .

=

= August 28, 1997 Westinghou'se'will revise information in the background document for AES-1.2, ste) 15, to be-consistent ^with the ASI evaluation report concerning t te isolation of-accumulators to )revent nitrogen injection cinto the RCS. Westinghouse will also make tiis.rev.ision in other ERG step backgrounds-where appropriate.

]

Westinghouse will clarify its res)onse to comment #18 of NRC letter dated April 9. 1997, to explain t1at there is no backup for the accumu-i lators and none needed when they are isolated in step 25 of AE-3.

Westinghouse will issue an errata on the ASI evaluation report, WCAP-14477, Section 3.2, Subsection 2.2.1, which clarifies that ERGS permit restart of the RCPs after reset on an SI signal - and do not allow the operator to block the CMT actuation, original signed by:

William C. Huffman, Project Manager Standardization Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket-No.-52-003-

Attachment:

- As stated cc-w/att: .See next page DISTRIBUTION w/ attachment: .

Docket File PDST R/F TKenyon PUBLIC- BHuffman- JSebrosky DJackson-DISTRIBUTION w/o attachment:

.Scollins/FMiraglia, 0-12 G18 BSheron, 0-12 G18 JRoe DMatthews TQuay WDean,'0-5 E23 ACRS (11) JMoore, 0-15 B18 ACubbage, 0-8 E23 JBongarra, 0-9 H15 Alevin, 0-8 E23 TCollins, 0-8 E23 DOCUMENT NAME: -A:TLCON-1. ERG =

x. .w. . ..,y .e m. we m m. wm c . c , ui .n nu.nei e . copy wem eu.comi.nu.ncw.w. r . No copy 0FFICE PM:PDST:DRPM l D:PDST:DRPM -l -l l NAME WCHuffman:ut/ w - TRQuay T Q-DATE y/o y97 V 8/2.3/97 0FFICIAL RECORD COPY w

Westinghouse Electric Corporation Docket No.52-003 cc: Mr. Nicholas J. Liparulo, Manager Mr. Frank A. Ross Nuclear Safety and Regulatory Analysis U.S. Department of Energy, NE-42 Nuclear and Advanced Technology Division Office of LWR Safety and Technology Westinghouse Electric Corporation 19901 Germantown Road P.O. Box 355 Germantown, MD 20874 Pittsburgh, PA 15230 Mr. Russ Bell Mr. B. A. McIntyre Senior Project Manager, Programs Advanced Plant Safety & Licensing Nuclear Energy Institute Westinghouse Electric Corporation 1776 Eye Street, N.W.

Energy Systems Business Unit Suite 300 Box 355 Washington, DC 20006-3706 Pittsburgh, PA 15230 Ms. Lynn Connor Ms. Cindy L. Haag Doc-Search Associates Advanced Plant Safety & Licensing Post Office Box 34  !

Westinghouse Electric Corporation Cabin John, MD 20818 I Energy Systems Business Unit Box 355 Dr. Craig D. Sawyer, Manager Pittsburgh, PA 15230 Advanced Reactor Programs ,

GE Nuclear Energy Mr. M. D. Beaumont 175 Curtner Avenue, MC-754 Nuclear and Advanced Technology Division San Jose, CA 95125 Westinghouse Electric Corporation One Montrose Metro Mr. Robert H. Buchholz 11921 Rockville Pike GE Nuclear Energy Suite 350 175 Curtner Avenue, MC-781 Rockville, MD 20852 San Jose, CA 95125 Mr. Sterling Franks Barton Z. Cowan, Esq.

U.S. Department of Energy Eckert Seamans Cherin & Mellott NE-50 600 Grant Street 42nd Floor 19901 Germantown Road Pittsburgh, PA 15219 Germantown, MD 20874 Mr. Ed Rodwell, Manager Mr. S. M. Modro PWR Design Certification Nuclear Systems Analysis Technologies Electric Power Research Institute Lockheed Idaho Technologies Company 3412 Hillview Avenue Post Office Box 1625 Palo Alto, CA 94303 Idaho Falls, ID 83415 Mr. Charles Thompson, Nuclear Engineer AP600 Certification NE-50 19901 Germantown Road Germantown, MD 20874

WESTINGHOUSE /NRC AP600 EMERGENCY RESPONSE GUIDELINES TELECONFERENCE PARTICIPANTS AUGUST 26, 1997 l

E ORGANIZATION ROBIN NYDES -

WEFTINGHOUSE MIKE CORLETTI WESTINGH0dSE RICH PROK0POVICH WESTINGHOUSE AMY CUBBAGE NRC l BILL HUFFMAN NRC JIM HIGGINS BNL l

Attachment

. . . .. . . .