ML20217L143

From kanterella
Revision as of 20:58, 11 August 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Crop Resources Aug 2020
ML20217L143
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/04/2020
From: James Gaslevic
NRC/NRR/VPOB
To:
James Gaslevic Ex. 2776
References
Download: ML20217L143 (5)


Text

CONSTRUCTION REACTOR OVERSIGHT PROCESS RESOURCES The U.S. Nuclear Regulatory Commission (NRC) staff originally estimated that direct inspection will require 35,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> per unit over the course of a 5-year nuclear power plant construction project. As of August 3, 2020, revised estimates are approximately 40,600 hours0.00694 days <br />0.167 hours <br />9.920635e-4 weeks <br />2.283e-4 months <br /> for Vogtle Unit 3 and 29,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Vogtle Unit 4. These revised estimates include:

  • 19,400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> for inspections related to ITAAC for Vogtle Unit 3, and 13,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for Vogtle Unit 4;
  • 11,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for construction and operational program inspections for Vogtle Unit 3, and 6,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Vogtle Unit 4;
  • 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events;
  • and 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for technical support of construction inspections.

Table 1 and figure 1 show the total number of direct inspection hours expended through July 2020, for Vogtle, Units 3 and 4.

Table 1: Actual Total Construction Inspection Program Resource Expenditures Unit ITAAC Inspection Program Reactive/Allegation- Technical Total Hours/Percentage Inspections Related Inspections Support*

of Planned Inspections Vogtle, 16,520 / 85% 7,788 544 2,453 27,305 Unit 3 Vogtle, 9,040 / 70% 4,793 342 1,650 15,825 Unit 4

  • To date, NRC Headquarters technical staff inspection support has not been linked to a specific docket and has not been fee billable. Therefore, it is not possible to distinguish the technical support hours expended by the Office of Nuclear Reactor Regulation on each unit. In Table 1, the total hours expended on technical support have been split between the units.

August 3, 2020 35000 30000 25000 20000 15000 10000 5000 0

2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 3, Cumulative Data Vogtle, Unit 4, Cumulative Data Figure 1 Total cumulative direct inspection hours for Vogtle, Unit 3 and 4 20000 18000 16000 14000 12000 10000 8000 6000 4000 2000 0

2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Vogtle, Unit 3, ITAAC direct inspections Proj Hours Vogtle, Unit 4, ITAAC direct inspections Figure 2 Cumulative ITAAC-related direct inspection hours for Vogtle, Units 3 and 4 Figure 2 summarizes the direct inspection hours expended for inspections related to ITAAC since the start of construction at Vogtle Units 3 and 4. The staff estimates that there will be approximately 19,400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> of direct inspection related to ITAAC for Unit 3 and 13,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> of direct inspection related to ITAAC for Unit 4.

14000 12000 10000 8000 6000 4000 2000 0

2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 4, Program direct inspection Vogtle, Unit 4, QA direct inspection Vogtle, Unit 3, Program direct inspection Vogtle, Unit 3, QA direct inspection Figure 3 Cumulative quality assurance and program inspection for Vogtle, Units 3 and 4 Figure 3 summarizes the NRC staff resources in hours expended for programmatic inspection since the start of construction at Vogtle, Units 3 and 4. Based on Vogtles schedule, total cumulative program inspections are estimated at 11,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Vogtle Unit 3, and 6,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Unit 4.

3500 3000 2500 2000 1500 1000 500 0

2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 3, Reactive and Allegations Vogtle, Unit 3, HQ Technical Support Vogtle, Unit 4, Reactive and Allegations Vogtle, Unit 4, HQ Technical Support Figure 4 Cumulative reactive and technical support hours for Vogtle, Units 3 and 4 Figure 4 summarizes the direct inspection hours expended for reactive and allegation inspections and hours spent providing technical support for inspections since the start of construction at Vogtle, Units 3 and 4. The staff has not identified a need to revise the estimate of 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events, or the 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> estimated for technical support for construction inspections.