MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 ML23223A0022023-08-14014 August 2023 (Vegp), Unit 3, Integrated Inspection Report 05200025/2023002 IR 05000424/20230112023-08-11011 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000424/2023011 and 05000425/2023011 ML23215A0822023-08-0404 August 2023 (Vego), Unit 3 Initial Test Program and Operational Programs Integrated 05200025/2023011 Inspection Report IR 05000424/20234012023-07-31031 July 2023 Security Baseline Inspection Report 05000424/2023401 and 05000425/2023401 (Cover Letter) ML23212B0612023-07-31031 July 2023 Security Baseline Inspection Report 05200025/2023401 ML23216A0962023-07-26026 July 2023 Document Request for Vogtle 1 & 2 RP Inspection, Report No. 05000424/2023003 and 05000425/2023003 IR 05000424/20230022023-07-24024 July 2023 Integrated Inspection Report 05000424/2023002 and 05000425/2023002 ML23198A3802023-07-19019 July 2023 NRC Integrated Inspection Report 05200026/2023002 ML23199A0892023-07-18018 July 2023 (Vegp), Unit 4 Initial Test Program and Operational Programs Integrated Inspection Report 05200026/2023007 IR 05000424/20233012023-06-30030 June 2023 NRC Operator License Examination Report 05000424/2023301 and 05000425/2023301 ML23128A2932023-05-11011 May 2023 NRC Integrated Inspection Report 05200026/2023001 ML23129A0222023-05-10010 May 2023 (Vegp), Unit 3 - Integrated Report 05200025/2023001 ML23128A3492023-05-0909 May 2023 (Vegp), Unit 4 Initial Test Program and Operational Programs Integrated Inspection Report 05200026/2023006 ML23121A3202023-05-0404 May 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200025/2023010 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 IR 05000424/20230012023-04-26026 April 2023 Integrated Inspection Report 05000424/2023001 and 05000425/2023001 IR 05000424/20230902023-03-30030 March 2023 NRC Inspection Report 05000424/2023090 and 05000425/2023090, and Investigation Report 2-2022-006; and Apparent Violation ML23083B3702023-03-24024 March 2023 Security Baseline Inspection Report 05200026/2023401 IR 05000424/20220062023-03-0101 March 2023 Annual Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2, NRC Inspection Reports 05000424/2022006 and 05000425/2022006 ML23044A3902023-02-14014 February 2023 Integrated Inspection Report05200025 2022007 ML23040A3612023-02-0909 February 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026/2022008 ML23040A0422023-02-0909 February 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200025/2022008 ML23033A3972023-02-0707 February 2023 NRC Integrated Inspection Report 05200026/2022007 IR 05000424/20220042023-01-23023 January 2023 Integrated Inspection Report 05000424/2022004 and 05000425/2022004 ML22356A2932022-12-23023 December 2022 Information Request for the Cyber Security Baseline Security Inspection, Notification to Perform Inspection IR 05000424/20220102022-12-0202 December 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000424/2022010 and 05000425/2022010 ML22327A0532022-11-30030 November 2022 Security Baseline Inspection Report 05200026/2022401 Cover Letter IR 05000424/20224032022-11-28028 November 2022 Security Baseline Inspection Report 05000424/2022403 and 05000425/2022403 (Cover Letter) ML22314A0702022-11-14014 November 2022 NRC Integrated Inspected Reports 05200025/2022005, 05200026/2022005 ML22318A1602022-11-14014 November 2022 Integrated Inspection Report 05200025/2022010 ML22304A1812022-11-0808 November 2022 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200025/2022011 ML22311A0062022-11-0808 November 2022 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026/2022006 IR 05000424/20220032022-10-27027 October 2022 Integrated Inspection Report 05000424/2022003 and 05000425/2022003 IR 05000424/20220052022-08-24024 August 2022 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2022005 and 05000425/2022005 ML22230C6702022-08-22022 August 2022 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200025/2022006 ND-22-0655, ITAAC Closure Notification on Completion of ITAAC 2.5.01.03a (Index Number 511)2022-08-12012 August 2022 ITAAC Closure Notification on Completion of ITAAC 2.5.01.03a (Index Number 511) IR 05000424/20220022022-08-11011 August 2022 Integrated Inspection Report 05000424/2022002 and 05000425/2022002 ML22220A1342022-08-0909 August 2022 Review of the Refueling Outage 1R23 (Fall 2021) Steam Generator Tube Inspection Report IR 05000424/20224012022-08-0404 August 2022 Cyber Security Inspection Report 05000424/2022401 and 05000425/2022401 2024-02-05
[Table view] |
Text
CONSTRUCTION REACTOR OVERSIGHT PROCESS RESOURCES The U.S. Nuclear Regulatory Commission (NRC) staff originally estimated that direct inspection will require 35,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> per unit over the course of a 5-year nuclear power plant construction project. As of August 3, 2020, revised estimates are approximately 40,600 hours0.00694 days <br />0.167 hours <br />9.920635e-4 weeks <br />2.283e-4 months <br /> for Vogtle Unit 3 and 29,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Vogtle Unit 4. These revised estimates include:
- 19,400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> for inspections related to ITAAC for Vogtle Unit 3, and 13,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for Vogtle Unit 4;
- 11,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for construction and operational program inspections for Vogtle Unit 3, and 6,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Vogtle Unit 4;
- 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events;
- and 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for technical support of construction inspections.
Table 1 and figure 1 show the total number of direct inspection hours expended through July 2020, for Vogtle, Units 3 and 4.
Table 1: Actual Total Construction Inspection Program Resource Expenditures Unit ITAAC Inspection Program Reactive/Allegation- Technical Total Hours/Percentage Inspections Related Inspections Support*
of Planned Inspections Vogtle, 16,520 / 85% 7,788 544 2,453 27,305 Unit 3 Vogtle, 9,040 / 70% 4,793 342 1,650 15,825 Unit 4
- To date, NRC Headquarters technical staff inspection support has not been linked to a specific docket and has not been fee billable. Therefore, it is not possible to distinguish the technical support hours expended by the Office of Nuclear Reactor Regulation on each unit. In Table 1, the total hours expended on technical support have been split between the units.
August 3, 2020 35000 30000 25000 20000 15000 10000 5000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 3, Cumulative Data Vogtle, Unit 4, Cumulative Data Figure 1 Total cumulative direct inspection hours for Vogtle, Unit 3 and 4 20000 18000 16000 14000 12000 10000 8000 6000 4000 2000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Vogtle, Unit 3, ITAAC direct inspections Proj Hours Vogtle, Unit 4, ITAAC direct inspections Figure 2 Cumulative ITAAC-related direct inspection hours for Vogtle, Units 3 and 4 Figure 2 summarizes the direct inspection hours expended for inspections related to ITAAC since the start of construction at Vogtle Units 3 and 4. The staff estimates that there will be approximately 19,400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> of direct inspection related to ITAAC for Unit 3 and 13,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> of direct inspection related to ITAAC for Unit 4.
14000 12000 10000 8000 6000 4000 2000 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 4, Program direct inspection Vogtle, Unit 4, QA direct inspection Vogtle, Unit 3, Program direct inspection Vogtle, Unit 3, QA direct inspection Figure 3 Cumulative quality assurance and program inspection for Vogtle, Units 3 and 4 Figure 3 summarizes the NRC staff resources in hours expended for programmatic inspection since the start of construction at Vogtle, Units 3 and 4. Based on Vogtles schedule, total cumulative program inspections are estimated at 11,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Vogtle Unit 3, and 6,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for Unit 4.
3500 3000 2500 2000 1500 1000 500 0
2012 2013 2014 2015 2016 2017 2018 2019 2020 2020 Proj Hours Vogtle, Unit 3, Reactive and Allegations Vogtle, Unit 3, HQ Technical Support Vogtle, Unit 4, Reactive and Allegations Vogtle, Unit 4, HQ Technical Support Figure 4 Cumulative reactive and technical support hours for Vogtle, Units 3 and 4 Figure 4 summarizes the direct inspection hours expended for reactive and allegation inspections and hours spent providing technical support for inspections since the start of construction at Vogtle, Units 3 and 4. The staff has not identified a need to revise the estimate of 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for reactive inspections above the baseline program in response to licensee performance issues, allegations, and nonperformance issues or events, or the 5,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> estimated for technical support for construction inspections.