ML20092E038

From kanterella
Revision as of 20:37, 4 May 2020 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Proposed Tech Spec 3/4.7.8,clarifying Intent of Vacuum Relief Flow During TS Required Testing of Auxiliary Bldg Gas Treatment Sys
ML20092E038
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 09/08/1995
From:
TENNESSEE VALLEY AUTHORITY
To:
Shared Package
ML20092E037 List:
References
NUDOCS 9509150012
Download: ML20092E038 (4)


Text

. ._ .- . -. . _. - --

~

ENCLOSURE TECHNICAL SPECIFICATION (TS) BASES CHANGE i

SEQUOYAH NUCLEAR PLANT (SON) UNITS 1 AND 2 DOCKET NOS. 50-327 AND 50-328 i

LIST OF AFFECTED PAGES Unit 1 8 3/4 7-5

, Unit 2 3

B 3/4 7-2 i

B 3/4 7-5 i

i l

' 1 1

4 l

l 1

. l l

9509150012 950908 PDR ADOCK 05000327

_ P__. .. -. _ _ . _ . __ _ PDR . . _

,= ,'

PLANT SYSTEMS E SES 3/4.7.8 AUXILIAU BUILDING GAS TREATMENT SYSTEM The OPERABILITY of the auxiliary building gas treatment system ensures that radioactive materials leaking from the ECCS equipment following a LOCA are filtered prior to reaching the environment. The operation of this system and the resultant effect on offsite dosage calculations was assumed in the accident analyses. ANSI N510-1975 will be used as a procedural guide for surveillance

. testing. Cumulative operation of the system with the heaters on for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> over a 31 day period is sufficient to reduce the buildup of moisture on the adsorbers and HEPA filters.

The minimum vacuum relief flow requirement in TS Surveillance Requirement BR-6 4.7.8.d.3 is for test purposes only. It is intended to demonstrate an acceptable level of ABGTS performance margin by simulating an ABSCE boundary breach. The inability to meet the specified minimum test condition under other ,

circumstances does not challenge the operability of the ABGTS. J l

3/4.7.9 SrJBBERS

Snubbers are designed to prevent unrestrained pipe or component motion i under dynamic loads as might occur during an earthquake or severe transient, while allowing normal thermal motion during startup and shutdown. The con-sequence of an inoperable snubber is an increase in the probability of structural damage to piping or components as a result of a seismic or other y event initiating dynamic loads. It is therefore required that all snubbers -

required to protect the primary coolant system or any other safety system or O component be operable during reactor operation.

Because the snubber protection is required only during relatively low probability events, a period of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is allowed to replace or restore the .'

inoperable snubber (s) to operable status and perform an engineering evaluation on the supported' component or declare the supported system' inoperable and R16 follow the appropriate limiting condition for operation statement for that l system. The engineering evaluation is performed to determine whether the mode I of failure of the snubber has adversely affected any safety-related component or system.

Safety-related snubbers are visually inspected for overall integrity and operability. The inspection will include verification of proper orientation, l adequate fluid level if applicable, and attachment of the snubber to its l

anchorage. The removal of insulation or the verification of torque values for threaded fasteners is not required for visual inspections.

The inspection frequency is based upon maintaining a constant level of snubber protection. Thus, the required inspection interval varies inversely with the observed snubber failures. The number of inoperable snubbers found q during a required inspection determines the time interval for the next required i inspection. Inspections performed before that interval has elapsed may be used I as a new reference point to determine the next inspection. However, the i results of such early inspections performed before the original required time interval has elapsed (nominal time less 25 percent) may not be used to lengthen the required inspection interval. Any inspection whose results require a shorter inspection interval will override the previous schedule.

August 11, 1995 SEQUOYAH - UNIT 1 B 3/4 7-5 Amendment No. 12

m ~r -l l

. l x

l PLANT S STEMS a BASES R187 Q = Nominal NSSS power rating of the plant (including reactor coolant pump heat), Mwt K = Conversion factor, 947.82 (Btu /sec)

Mwt w, = Minimum total steam flow rate capability of the operable MSSVs on any one steam generator at the highest MSSV opening pressure including tolerance and accumulation, as appropriate, in lb/sec.

For example, if the maximum number of inoperable MSSVs on any one steam generator is one, then w, should be a summation of the capability of the operable MSSVs at the highest capacity MSSV operating pressure, excluding the highest capacity MSSV. If the maximum number of inoperable MSSVs per steam generator is three then w, should be a summation of the capacity of the operable MSFVs at the highest cperable MSSV cperating pressure, e::cluding the three highest capacity MSSVs.

hg = heat of vaporization for steam at the highest MSSV opening pressure including tolerance and accumulation, as appropriate, Btu /lbm N = Number of loops in plant l

The valves calculated from this algorithm must then be adjusted lower to account for instrument and channel uncertainties.

3/4.7.1.2 AUXILIARY FEEDWATER SYSTEM lh The OPERABILITY of the auxiliary feedwater system ensures that the Reactor Coolant System can be cooled down to less than 350*F from normal operating conditions in the event of a total loss of off-site power.

The steam driven auxiliary feedwater pump is capable of delivering 880 gpm (total feedwater flow) and each of the electric driven auxiliary feedwater pumps are capable of delivering 440 gpm (total feedwater flow) to the entrance of the steam generators at steam generator pressures of 1100 psia. At 1100 psia the open steam generator safety valve (s) are capable of relieving at least 11% of nominal steam flow. A total feedwater flow of 440 gpm at ,

pressures of 1100 psia is sufficient to ensure that adequate feedwater flow is j available to remove decay heat and reduce the Reactor Coolant System temperature to less than 350'F where the Residual Heat Removal System may be placed into operation. The surveillance test values enstre that cach pump will provide at least 440 gpm plus pump recirculation flow against a steam generator pressure of 1100 psia.

Each motor-driven auxiliary feedwater pump (one Train A and one Train B) BR-1 supplies flow paths to two steam generators. Each flow path contains an automatic air-operated level control valve (LCV) . The LCVs have the same train designation as the associated pump and are provided trained air. The turbine-driven auxiliary feedwater pump supplies flow paths to all four steam generators. Each of these flow paths contains an automatic opening BR-7 (non-modulating) air-operated LCV, two of O

SEQUOYAH - UNIT 2 B 3/4 7-2 Amendment No. 105, 187 May 25, 1995

L /

L l.

e '

PLANT SYSTEMS BASES 3/4.7.9 AUXILIARY BUILDING GAS TREMNET SYSTEM The' OPERABILITY of the auxiliary building gas treatment system ensures that radioactive materials leaking from the ECCS equipment following a LOCA are filtered prior to reaching the environment. The operation of this system and the resultant effect on offsite dosage calculations was assumed in the accident

. analyses- ' ANSI N510-1975 will be used as a procedural guide for surveillance testing. C:mlative operation of the system with the heaters on for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> over.a 31' day period is sufficient to reduce the buildup of moisture on the adsorbers'and HEPA filters.

The minimum vacuum relief flow requirement in TS Surveillance Requirement 4.7.8.d.3 is for test purpoans only. It is intended to demonstrate an BR-8 acceptable level of ABGTS perforn.ance margin by simulating an ABSCE boundary breach. -The inability to' meet'the specified minimum test cendition undar other circumstances does not challenge the operability of the ABGTS.

3/4.7.9 SNUBBERS Snubbers are designed to prevent unrestrained pipe or compon9nt motion under dynamic loads as might occur during an earthquake or severe transient, while j allowing normal thermal motion during startup and shutdown. The consequence of an inoperable snubber is an increase in the probability of structural damage to ,.

piping or components as a result of a seismic or other event initiating dynamic',7 l loads. It is therefore required that all snubbers required to protect the L

primary coolant system or any other safety system or component be operable l during reactor operation.

Because the snubber protection is required only during relatively low probability events, a period of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is allowed to replace or restore the inoperable snubber (s) to operable status and perform an engineering evaluation on the supported component or declare the supported system inoperable and follow the appropriate limiting condition for operation statement for that system. The engineering evaluation is perfomed to determine whether the mode of failure of the snubber has adversely affected any safety-related component or system.

R2 l

Safety-related snubbers are visually inspected for overall integrity and operability. The inspection will include verification of proper orientation, adequate fluid level if applicable, and attachment of the snubber to its anchorage. The removal of insulation or the verification of torque values for threaded fasteners is not required for visual inspections, j i

I

! The inspection frequency is based upon maintaining a constant level of snubber l protection. Thus, the required inspection interval varies inversely with the 1 observed snubber failures. The number of inoperable snubbers found during a required inspection determines the time interval for the next required inspection. Inspections performed before that interval has elapsed may be used

.as a new reference point to determine the next inspection. However, the results of such early inspections performed before the original required time interval has elapsed (nominal time less 25 percent) may not be used to lengthen the required inspection interval. Any inspection whose results require a shorter inspection interval will-override the previous schedule.

O August 11, 1995 SEQUOYAH UNIT 2 B 3/4 7; 5 ,

Amendment 2 m