TAC:MB4632, Revise Containment Requirements During Handling Irradiated Fuel and Core Alterations (Open) |
|
|
Technical Specification Pages for Amendment No. 195, Technical Specification Change Selective Implementation of Alternative Radiological SourceML022980530 |
Person / Time |
---|
Site: |
Robinson |
---|
Issue date: |
10/04/2002 |
---|
From: |
NRC/NRR/DLPM/LPD2 |
---|
To: |
|
---|
References |
---|
TAC MB4632 |
Download: ML022980530 (11) |
|
|
---|
Category:Technical Specification
MONTHYEARRA-23-0028, Application to Revise Technical Specifications to Adopt TSTF-234-A, Revision 1, Add Action for More than One (D)Rpi Inoperable2024-05-23023 May 2024 Application to Revise Technical Specifications to Adopt TSTF-234-A, Revision 1, Add Action for More than One (D)Rpi Inoperable RA-23-0121, License Amendment Request to Adopt TSTF-258-A, Revision 4, Regarding Changes to Technical Specification Section 5.7, High Radiation Area2023-10-0505 October 2023 License Amendment Request to Adopt TSTF-258-A, Revision 4, Regarding Changes to Technical Specification Section 5.7, High Radiation Area ML23145A1602023-05-25025 May 2023 Submittal of Updated Final Safety Analysis Report (Revision No. 30), Independent Spent Fuel Storage Installation Safety Analysis Report (Revision No. 28), Technical Specifications Bases Revisions, Quality RA-22-0091, Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2023-02-16016 February 2023 Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RA-22-0118, License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies2023-02-0101 February 2023 License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies RA-22-0153, License Amendment Request to Add Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.2 and Update the List of Analytical Methods Used in the Determination of Core.2022-09-21021 September 2022 License Amendment Request to Add Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.2 and Update the List of Analytical Methods Used in the Determination of Core. RA-21-0183, Remove 4.160 Kilovolt Bus 2 from Surveillance Requirement 3.8.1.16 (Automatic Transfer Capability from Unit Auxiliary Transformer to Startup Transformer)2022-04-28028 April 2022 Remove 4.160 Kilovolt Bus 2 from Surveillance Requirement 3.8.1.16 (Automatic Transfer Capability from Unit Auxiliary Transformer to Startup Transformer) RA-20-0107, Duke Energy Progress, LLC, and Duke Energy Carolinas, LLC, Application to Revise Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2022-01-18018 January 2022 Duke Energy Progress, LLC, and Duke Energy Carolinas, LLC, Application to Revise Technical Specifications to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position RA-22-0017, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-01-0606 January 2022 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections RA-21-0057, Independent Spent Fuel Storage Installation, Submittal of Updated Final Safety Analysis Report (Revision No. 29), Independent Spent Fuel Storage Installation Safety Analysis Report (Revision No. 27), Technical .2021-05-27027 May 2021 Independent Spent Fuel Storage Installation, Submittal of Updated Final Safety Analysis Report (Revision No. 29), Independent Spent Fuel Storage Installation Safety Analysis Report (Revision No. 27), Technical . RA-19-0183, License Amendment Request to Add New Feedwater Bypass Valves to Technical Specification 3.7.32019-07-29029 July 2019 License Amendment Request to Add New Feedwater Bypass Valves to Technical Specification 3.7.3 RA-19-0006, License Amendment Application to Relocate Technical Specification Unit/Facility Staff Qualification ANSI N18.1-1971, ANSI/ANS-3.1-1978 and ANSI/ANS-3.1-1981 Requirements to the Duke Energy Corporation Quality Assurance Program Description2019-07-0808 July 2019 License Amendment Application to Relocate Technical Specification Unit/Facility Staff Qualification ANSI N18.1-1971, ANSI/ANS-3.1-1978 and ANSI/ANS-3.1-1981 Requirements to the Duke Energy Corporation Quality Assurance Program Description RNP-RA/18-0044, Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transform2018-07-11011 July 2018 Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RA-18-0001, Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - License Amendment Application to Remove Heaters from Ventilation System Technical Specifications2018-05-10010 May 2018 Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - License Amendment Application to Remove Heaters from Ventilation System Technical Specifications ML18130A8072018-05-10010 May 2018 Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - Submittal of License Amendment Application to Remove Heaters from Ventilation System Technical Specifications RA-18-000, Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - Submittal of License Amendment Application to Remove Heaters from Ventilation System Technical Specifications2018-05-10010 May 2018 Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - Submittal of License Amendment Application to Remove Heaters from Ventilation System Technical Specifications RA-17-0005, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing2017-11-0707 November 2017 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing RA-17-0022, Technical Specification Changes to Support Self-Performance of Core Reload Design and Safety Analyses2017-10-19019 October 2017 Technical Specification Changes to Support Self-Performance of Core Reload Design and Safety Analyses RA-17-0045, Supplement: Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules.2017-10-12012 October 2017 Supplement: Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules. RNP-RA/17-0041, Transmittal of Technical Specifications Bases Revisions2017-05-23023 May 2017 Transmittal of Technical Specifications Bases Revisions RNP-RA/17-0034, Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544)2017-05-0202 May 2017 Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544) RA-16-0019, Duke Energy Progress - Application to Revise Technical Specifications to Adopt TSTF-522, Revision 0, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month Using the Consolidated Line Item Improvement Proces2016-09-27027 September 2016 Duke Energy Progress - Application to Revise Technical Specifications to Adopt TSTF-522, Revision 0, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month Using the Consolidated Line Item Improvement Process RA-16-0007, Duke Energy Carolinas, LLC, Application to Revise TS to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability Using the Consolidated Line Item Improvement Process2016-06-23023 June 2016 Duke Energy Carolinas, LLC, Application to Revise TS to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability Using the Consolidated Line Item Improvement Process ML16116A0332016-04-24024 April 2016 Application for Technical Specification Change to Adopt Technical Specifications Task Force (TSTF)-339, Relocate TS Parameters to the COLR Consistent with WCAP-14483, Revision 2 RA-16-0005, Supplement to Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 52016-02-0101 February 2016 Supplement to Application to Revise Technical Specifications for Methodology Report DPC-NE-2005-P, Revision 5 RNP-RA/15-0083, Submits Request for Technical Specification Change to Reactor Coolant System Pressure and Temperature Limits2015-11-0202 November 2015 Submits Request for Technical Specification Change to Reactor Coolant System Pressure and Temperature Limits RNP-RA/15-0086, Transmittal of Technical Specifications Bases Revisions2015-10-0808 October 2015 Transmittal of Technical Specifications Bases Revisions RNP-RA/15-0077, Submittal of Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report, 14-Day Report for the Inoperability of Pressurizer Power Operated Relief Valves Position Indication2015-09-0101 September 2015 Submittal of Technical Specifications Section 5.6.6, Post Accident Monitoring Instrumentation Report, 14-Day Report for the Inoperability of Pressurizer Power Operated Relief Valves Position Indication ML14188B0152014-06-20020 June 2014 Request for Technical Specifications (TS) Change Regarding Correction to TS 5.5.9.b.2, Steam Generator (SG) Program Accident-Induced Leakage Performance Criterion RNP-RA/14-0042, Transmittal of Technical Specifications Bases Revisions2014-04-29029 April 2014 Transmittal of Technical Specifications Bases Revisions RNP-RA/13-0077, License Amendment Request for Technical Specification(Ts) Change to Use NRC-Approved TSTF-491, Revision 2, Removal of Main Steam and Main Feedwater Valve Isolation Times from Technical Specifications2013-09-30030 September 2013 License Amendment Request for Technical Specification(Ts) Change to Use NRC-Approved TSTF-491, Revision 2, Removal of Main Steam and Main Feedwater Valve Isolation Times from Technical Specifications RNP-RA/13-0038, Replacement of Technical Specification Pages to Correct Typographical Errors in Request for TS Changes Regarding TS 3.1.4 Rod Group Alignment Limits and TS 3.1.7 Rod Position Indication2013-04-24024 April 2013 Replacement of Technical Specification Pages to Correct Typographical Errors in Request for TS Changes Regarding TS 3.1.4 Rod Group Alignment Limits and TS 3.1.7 Rod Position Indication RNP-RA/12-0066, Transmittal of Technical Specifications Bases Revisions2012-09-17017 September 2012 Transmittal of Technical Specifications Bases Revisions RNP-RA/12-0033, Application for Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers Using the Consolidated Line Item Improvement Process2012-08-0606 August 2012 Application for Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers Using the Consolidated Line Item Improvement Process RNP-RA/11-0095, Request for Technical Specifications Change Regarding Missed Surveillance Using the Consolidated Line Item Improvement Process2012-02-10010 February 2012 Request for Technical Specifications Change Regarding Missed Surveillance Using the Consolidated Line Item Improvement Process RNP-RA/11-0002, Transmittal of Technical Specifications Bases Revisions2011-01-12012 January 2011 Transmittal of Technical Specifications Bases Revisions RNP-RA/10-0001, Request for Technical Specification Changes to Section 3.3.2, Engineered Safety Feature, Actuation System (ESFAS) Instrumentation, and Section 3.3.6, Containment Ventilation Isolation Instrumentation2010-03-0505 March 2010 Request for Technical Specification Changes to Section 3.3.2, Engineered Safety Feature, Actuation System (ESFAS) Instrumentation, and Section 3.3.6, Containment Ventilation Isolation Instrumentation ML0828301372008-10-0606 October 2008 License Amendment Request to Eliminate Work Hour Controls to Support Compliance with Revised 10 CFR 26 RNP-RA/08-0006, Request for Technical Specifications Changes Related to Control Room Habitability - Supplement2008-04-0101 April 2008 Request for Technical Specifications Changes Related to Control Room Habitability - Supplement RNP-RA/08-0016, Supplement to the Request for Administrative Changes to the Technical Specifications2008-02-0404 February 2008 Supplement to the Request for Administrative Changes to the Technical Specifications RNP-RA/07-0126, Request for Technical Specifications Change to Section 3.6.8 Isolation Valve Seal Water System2007-11-29029 November 2007 Request for Technical Specifications Change to Section 3.6.8 Isolation Valve Seal Water System RNP-RA/07-0073, Request for Administrative Changes to the Operating License and Technical Specifications2007-11-19019 November 2007 Request for Administrative Changes to the Operating License and Technical Specifications RNP-RA/07-0124, Request for Technical Specifications Change to Section 3.1.7 Rod Position Indication2007-11-15015 November 2007 Request for Technical Specifications Change to Section 3.1.7 Rod Position Indication RNP-RA/07-0108, Transmittal of Technical Specifications Bases Revisions2007-10-30030 October 2007 Transmittal of Technical Specifications Bases Revisions RNP-RA/07-0056, Request for Technical Specifications Changes Related to Control Room Habitability2007-07-17017 July 2007 Request for Technical Specifications Changes Related to Control Room Habitability RNP-RA/06-0095, Request for Technical Specifications Change to Section 3.3.3, Post Accident Monitoring2007-02-0202 February 2007 Request for Technical Specifications Change to Section 3.3.3, Post Accident Monitoring ML0702404832007-01-19019 January 2007 H. B. Robinson, Unit 2 - Resubmission of Request for Technical Specifications Change Regarding Steam Generator Alternate Repair Criteria ML0634104702006-11-29029 November 2006 Technical Specification Pages Re Core Operating Limit Report References, ML0628900812006-10-12012 October 2006 Submittal of H. B. Robinson, Unit 2 - Request for Technical Specifications Change Regarding Steam Generator Alternate Repair Criteria RNP-RA/06-0033, Transmittal of Technical Specifications Bases Revisions2006-04-0606 April 2006 Transmittal of Technical Specifications Bases Revisions 2024-05-23
[Table view] Category:Amendment
MONTHYEARRA-23-0028, Application to Revise Technical Specifications to Adopt TSTF-234-A, Revision 1, Add Action for More than One (D)Rpi Inoperable2024-05-23023 May 2024 Application to Revise Technical Specifications to Adopt TSTF-234-A, Revision 1, Add Action for More than One (D)Rpi Inoperable RA-22-0091, Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2023-02-16016 February 2023 Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RA-22-0153, License Amendment Request to Add Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.2 and Update the List of Analytical Methods Used in the Determination of Core.2022-09-21021 September 2022 License Amendment Request to Add Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.2 and Update the List of Analytical Methods Used in the Determination of Core. RA-21-0183, Remove 4.160 Kilovolt Bus 2 from Surveillance Requirement 3.8.1.16 (Automatic Transfer Capability from Unit Auxiliary Transformer to Startup Transformer)2022-04-28028 April 2022 Remove 4.160 Kilovolt Bus 2 from Surveillance Requirement 3.8.1.16 (Automatic Transfer Capability from Unit Auxiliary Transformer to Startup Transformer) RA-19-0183, License Amendment Request to Add New Feedwater Bypass Valves to Technical Specification 3.7.32019-07-29029 July 2019 License Amendment Request to Add New Feedwater Bypass Valves to Technical Specification 3.7.3 RA-19-0006, License Amendment Application to Relocate Technical Specification Unit/Facility Staff Qualification ANSI N18.1-1971, ANSI/ANS-3.1-1978 and ANSI/ANS-3.1-1981 Requirements to the Duke Energy Corporation Quality Assurance Program Description2019-07-0808 July 2019 License Amendment Application to Relocate Technical Specification Unit/Facility Staff Qualification ANSI N18.1-1971, ANSI/ANS-3.1-1978 and ANSI/ANS-3.1-1981 Requirements to the Duke Energy Corporation Quality Assurance Program Description RNP-RA/18-0044, Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transform2018-07-11011 July 2018 Supplement to License Amendment Request Proposing to Add a Qualified Offsite Circuit to Technical Specification 3.8.1, AC Sources - Operating and the Use of Load Tap Changers in the Automatic Mode of Operation on the Startup Transformers RA-18-0001, Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - License Amendment Application to Remove Heaters from Ventilation System Technical Specifications2018-05-10010 May 2018 Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - License Amendment Application to Remove Heaters from Ventilation System Technical Specifications ML18130A8072018-05-10010 May 2018 Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - Submittal of License Amendment Application to Remove Heaters from Ventilation System Technical Specifications RA-18-000, Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - Submittal of License Amendment Application to Remove Heaters from Ventilation System Technical Specifications2018-05-10010 May 2018 Duke Energy Progress, LLC and Duke Energy Carolinas, LLC - Submittal of License Amendment Application to Remove Heaters from Ventilation System Technical Specifications RA-17-0005, Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing2017-11-0707 November 2017 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing RA-17-0022, Technical Specification Changes to Support Self-Performance of Core Reload Design and Safety Analyses2017-10-19019 October 2017 Technical Specification Changes to Support Self-Performance of Core Reload Design and Safety Analyses RNP-RA/17-0034, Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544)2017-05-0202 May 2017 Modification of Request for Technical Specification Change to Change Technical Specification Surveillance Requirement Frequencies to Support 24-Month Fuel Cycles (MF9544) RNP-RA/15-0083, Submits Request for Technical Specification Change to Reactor Coolant System Pressure and Temperature Limits2015-11-0202 November 2015 Submits Request for Technical Specification Change to Reactor Coolant System Pressure and Temperature Limits RNP-RA/13-0077, License Amendment Request for Technical Specification(Ts) Change to Use NRC-Approved TSTF-491, Revision 2, Removal of Main Steam and Main Feedwater Valve Isolation Times from Technical Specifications2013-09-30030 September 2013 License Amendment Request for Technical Specification(Ts) Change to Use NRC-Approved TSTF-491, Revision 2, Removal of Main Steam and Main Feedwater Valve Isolation Times from Technical Specifications RNP-RA/12-0033, Application for Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers Using the Consolidated Line Item Improvement Process2012-08-0606 August 2012 Application for Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers Using the Consolidated Line Item Improvement Process ML0828301372008-10-0606 October 2008 License Amendment Request to Eliminate Work Hour Controls to Support Compliance with Revised 10 CFR 26 RNP-RA/08-0006, Request for Technical Specifications Changes Related to Control Room Habitability - Supplement2008-04-0101 April 2008 Request for Technical Specifications Changes Related to Control Room Habitability - Supplement RNP-RA/08-0016, Supplement to the Request for Administrative Changes to the Technical Specifications2008-02-0404 February 2008 Supplement to the Request for Administrative Changes to the Technical Specifications RNP-RA/07-0126, Request for Technical Specifications Change to Section 3.6.8 Isolation Valve Seal Water System2007-11-29029 November 2007 Request for Technical Specifications Change to Section 3.6.8 Isolation Valve Seal Water System RNP-RA/07-0073, Request for Administrative Changes to the Operating License and Technical Specifications2007-11-19019 November 2007 Request for Administrative Changes to the Operating License and Technical Specifications RNP-RA/07-0124, Request for Technical Specifications Change to Section 3.1.7 Rod Position Indication2007-11-15015 November 2007 Request for Technical Specifications Change to Section 3.1.7 Rod Position Indication RNP-RA/07-0056, Request for Technical Specifications Changes Related to Control Room Habitability2007-07-17017 July 2007 Request for Technical Specifications Changes Related to Control Room Habitability RNP-RA/06-0095, Request for Technical Specifications Change to Section 3.3.3, Post Accident Monitoring2007-02-0202 February 2007 Request for Technical Specifications Change to Section 3.3.3, Post Accident Monitoring ML0634104702006-11-29029 November 2006 Technical Specification Pages Re Core Operating Limit Report References, ML0628900812006-10-12012 October 2006 Submittal of H. B. Robinson, Unit 2 - Request for Technical Specifications Change Regarding Steam Generator Alternate Repair Criteria RNP-RA/05-0107, Request for Technical Specifications Change to Section 3.8.1 for the Diesel Generator Automatic Trips Bypass2005-11-30030 November 2005 Request for Technical Specifications Change to Section 3.8.1 for the Diesel Generator Automatic Trips Bypass ML0522003672005-08-0202 August 2005 Technical Specification Pages Re Bases Control Program (Tac No. MC3636) ML0511102212005-04-19019 April 2005 Enclosure, Amendment No. 204 on TS Revisions to Eliminate Monthly Operating and Annual Occupational Radiation Exposure Report Requirements (Tac No. MC5129) RNP-RA/05-0005, Request for Technical Specifications Change to Section 3.8.4, DC Sources - Operating2005-02-14014 February 2005 Request for Technical Specifications Change to Section 3.8.4, DC Sources - Operating ML0405707052004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Techncial Specification Pages 3.3-29 Through 3.3-32 for Amendment 176 ML0405706622004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 1.3-1 Through 1.3-13 for Amendment 176 ML0405706652004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 1.1-1 Through 1.2-3 for Amendment 176 ML0405706702004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 1.4-1 Through 1.4-4 for Amendment 176 ML0405706752004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Operating License Effective Pages Through Technical Specifications Effictive Pages ML0405706832004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Table of Contents for Amendment 176 ML0405706872004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 2.0-1 Through 2.0-2 for Amendment 176 ML0405706912004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.0.1 Through 3.0.5 for Amendment 176 ML0405706942004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.1-1 Through 3.1-21 for Amendment 176 ML0405706962004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.2-1 Through 3.2-14 for Amendment 176 ML0405706992004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.3-1 Through 3.3-19 for Amendment 176 ML0405707022004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.3-20 Through 3.3-28 for Amendment 176 ML0405707072004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.3-33 Through 3.3-34 for Amendment 176 ML0405707112004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.3-35 Through 3.3-36 for Amendment 176 ML0405707132004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.3-37 for Amendment 176 Through 3.3-39 for Amendment 195 ML0405707182004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.3-40 for Amendment 195 Through 3.3-43 for Amendment 176 ML0405707202004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.3-44 Through 3.3-47 for Amendment 176 ML0407804912004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.4-29 Through 3.4-51 for Amendment 176 ML0407804942004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.4-1 Through 3.4-28 for Amendment 176 ML0407804962004-02-18018 February 2004 Informational Copy of Operating License & Appendices. Technical Specification Pages 3.5-1 Through 3.5-11 for Amendment 176 2024-05-23
[Table view] |
Text
Containment Ventilation Isolation Instrumentation 3.3.6 Table 3.3.6-1 (page I of 1)
Containment Ventilation Isolation Instrumentation FUNCTION APPLICABLE REQUIRED SURVEILLANCE TRIP MODES OR OTHER CHANNELS REQUIREMENTS SETPOINT SPECIFIED CONDITIONS Manual Initiation 1.2.3.4.(a) 2 SR 3.3.6.6 NA 1.
2 trains SR 3.3.6.2 NA
- 2. Automatic Actuation Logic and Actuation Relays 1.2.3.4.(a) SR 3.3.6.3 SR 3.3.6.5
- 3. Containment Radiation Gaseous 1.2.3.4.(a) 1 SR 3.3.6.1 (b) a.
SR 3.3.6.4 SR 3.3.6.7
- b. Particulate 1.2.3.4.(a) 1 SR 3.3.6.1 (b)
SR 3.3.6.4 SR 3.3.6.7
- 4. Safety Injection Refer to LCO 3.3.2. "ESFAS Instrumentation,' Functions l.a-f. for all initiation functions and requirements.
(a) During movement of recently irradiated fuel assemblies within the containment.
(b) Trip Setpoint shall be in accordance with the methodology in the Offsite Dose Calculation Manual.
HBRSEP Unit No. 2 3.3-39 Amendment No. 176,195
CREFS Actuation Instrumentation 3.3.7 3.3 INSTRUMENTATION 3.3.7 Control Room Emergency Filtration System (CREFS) Actuation Instrumentati on LCO 3.3.7 The CREFS actuation instrumentation for each Function in Table 3.3.7-1 shall be OPERABLE.
APPLICABILITY: MODES 1, 2. 3, 4 During movement of irradiated fuel assemblies I ACTIONS
..................................... NOTE .....................................
Separate Condition entry is allowed for each Function.
CONDITION REQUIRED ACTION COMPLETION TIME A. One automatic A.1 Place one CREFS train 7 days actuation train in emergency inoperable, pressurization mode.
B. Two automatic B.1 Place one CREFS train Immediately in emergency actuation trains pressurization mode.
inoperable.
OR One radiation monitoring channel inoperable.
_________ 1____________________ .7___________
(continued) 3.3-40 Amendment No. 176, 195 HBRSEP Unit No. 2
CREFS Actuation Instrumentation 3.3.7 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME C. Required Action and C.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time for Condition A AND or B not met in MODE 1. 2, 3. or 4. C.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> D. Required Action and D.1 Suspend movement of Immediately associated Completion irradiated fuel Time for Condition A assemblies.
or B not met during movement of irradiated fuel assemblies.
SURVEILLANCE REQUIREMENTS
. . --.. NOTE... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Refer to Table 3.3.7-1 to determine which SRs apply for each CREFS Actuation Function.
SURVEILLANCE FREQUENCY SR 3.3.7.1 Perform CHANNEL CHECK. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> SR 3.3.7.2 Perform COT. 92 days SR 3.3.7.3 Perform ACTUATION LOGIC TEST. 31 days on a STAGGERED TEST BASIS (continued) 3.3-41 Amendment No. 4;6,195 HBRSEP Unit No. 2
CREFS 3.7.9 3.7 PLANT SYSTEMS 3.7.9 Control Room Emergency Filtration System (CREFS)
LCO 3.7.9 Two CREFS trains shall be OPERABLE.
APPLICABILITY: MODES 1. 2, 3, and 4 During movement of iirradiated fuel assemblies. I ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One CREFS train A.1 Restore CREFS train 7 days inoperable, to OPERABLE status.
B. Required Action and B.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition A AND not met in MODE 1, 2, 3, or 4. B.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> C. Required Action and C.1 Place OPERABLE CREFS Immediately associated Completion train in emergency Time of Condition A pressurization mode.
not met during movement of irradiated OR fuel assemblies.
C.2 Suspend movement of Immediately irradiated fuel assemblies.
(continued)
Amendment No. 1-;6. 195 HBRSEP Unit 2 3.7-22
CREFS 3.7.9 ACTIONS (continued)
D. Two CREFS trains D.1 Suspend movement of Immediately inoperable during irradiated fuel movement of irradiated assemblies.
fuel assemblies.
E. Two CREFS trains E.1 Restore at least one 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> inoperable in MODE 1. CREFS train to 2, 3, or 4. OPERABLE status.
F. Required Action and F.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition E AND not met in MODE 1, 2.
3, or 4. F.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.9.1 Operate each CREFS train for Ž 15 minutes. 31 days SR 3.7.9.2 Perform required CREFS filter testing in In accordance accordance with the Ventilation Filter with VFTP Testing Program (VFTP).
SR 3.7.9.3 Verify each CREFS train actuates on an 18 months actual or simulated actuation signal.
SR 3.7.9.4 Verify one CREFS train can maintain a 18 months on a positive pressure of 2 0.125 inches water STAGGERED TEST gauge, relative to the outside atmosphere BASIS and a positive pressure relative to adjacent building areas during the emergency pressurization mode of operation at a makeup flow rate of ; 400 cfm.
3.7-23 Amendment No. 1-76, 195 HBRSEP Unit 2
CREFS 3.7.9 Page is intentionally blank I 3.7-24 Amendment No. 4.-, 195 HBRSEP Unit 2
CREATC 3.7.10 3.7 PLANT SYSTEMS 3.7.10 Control Room Emergency Air Temperature Control (CREATC)
LCO 3.7.10 Two CREATC Water Cooled Condensing Unit (WCCU) trains shall be OPERABLE.
APPLICABILITY: MODES 1. 2, 3, and 4 During movement of i rradiated fuel assemblies. I ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One CREATC WCCU train A.1 Restore CREATC WCCU 30 days inoperable, train to OPERABLE status.
B. Required Action and B.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition A AND not met in MODE 1. 2, 3, or 4. B.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> (continued) 3.7-25 Amendment No. 1-76,195 HBRSEP Unit No. 2
CREATC 3.7.10 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME C. Required Action and C.1 Place OPERABLE CREATC Immediately associated Completion WCCU train in Time of Condition A operation.
not met during movement of irradiated OR
.fuel assemblies.
C.2 Suspend movement of Immediately irradiated fuel assemblies.
D. Two CREATC WCCU trains D.1 Suspend movement of Immediately inoperable during irradiated fuel movement of irradiated assemblies.
fuel assemblies.
E. Two CREATC WCCU trains E.1 Restore at least one 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> inoperable in MODE 1, CREATC WCCU train to 2, 3, or 4. OPERABLE status.
F. Required Action and F.1 Be in MODE 3. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> associated Completion Time of Condition E AND not met in MODE 1. 2.
3, or 4. F.2 Be in MODE 5. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> HBRSEP Unit No. 2 3.7-26 Amendment No. -1.76, 195
Containment Penetrations 3.9.3 3.9 REFUELING OPERATIONS 3.9.3 Containment Penetrations LCO 3.9.3 The containment penetrations shall be in the following status:
- a. The equipment hatch closed and held in place by four bolts;
- b. One door in the air lock closed; and
- c. Each penetration providing direct access from the containment atmosphere to the outside atmosphere either:
- 1. closed by a manual or automatic isolation valve, blind flange, or equivalent, or
- 2. capable of being closed by an OPERABLE Containment Ventilation Isolation System.
APPLICABILITY: During movement of recently irradiated fuel assemblies within containment. I ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One or more containment A.1 Suspend movement of Immediately penetrations not in recently irradiated required status. fuel assemblies within containment.
HBRSEP Unit No. 2 3.9-4 Amendment No. 1-7-6,195
Refueling Cavity Water Level 3.9.6 3.9 REFUELING OPERATIONS 3.9.6 Refueling Cavity Water Level LCO 3.9.6 Refueling cavity water level shall be maintained ; 23 ft above the top of reactor vessel flange.
APPLICABILITY: During movement of irradiated fuel assemblies within containment.
I ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Refueling cavity water A.1 Suspend movement of Immediately level not within irradiated fuel limit, assemblies within containment.
SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.9.6.1 Verify refueling cavity water level is 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
- 23 ft above the top of reactor vessel flange.
HBRSEP Unit No. 2 3.9-10 Amendment No. 6, 195
Containment Purge Filter System 3.9.7 3.9 REFUELING OPERATIONS 3.9.7 Containment Purge Filter System LCO 3.9.7 The Containment Purge Filter System shall be OPERABLE and operating.
APPLICABILITY: During movement of recently irradiated fuel assemblies in I containment.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Containment Purge A.1 Close each Immediately Filter System penetration providing inoperable, direct access from the containment OR atmosphere to the outside atmosphere by Containment Purge a manual or automatic Filter System not in valve, blind flange.
operation. or equivalent method.
OR A.2 Suspend movement of Immediately recently irradiated fuel assemblies within containment.
HBRSEP Unit No. 2 3.9-11 Amendment No. ,76,195