Category:INTERVENTION PETITIONS
MONTHYEARML20206G4051999-05-0505 May 1999 Applicant Answer to Petitioner Board of Commissioners of Orange County Contentions.* Requests That Technical Contentions in Section III & Environ Contentions in Section IV Not Be Admitted.With Certificate of Svc ML20206F9491999-05-0505 May 1999 NRC Staff Response to Orange County Supplemental Petition to Intervene.* None of Petitioner Proposed Contentions Meet Commission Requirements for Admissible Contention.Petitioner 990212 Request Should Be Denied.With Certificate of Svc ML20206A0851999-04-22022 April 1999 Erratum to Orange County Supplemental Petition to Intervene.* Citation to Vermont Yankee LBP-87-17,should Be Amended to Read Vermont Yankee Nuclear Power Co (Vermont Yankee Nuclear Power Station).With Certificate of Svc ML20196K8771999-04-0505 April 1999 Orange County Supplemental Petition to Intervene.* Informs That Orange County Contentions Should Be Admitted for Litigation in Proceeding ML20206J9151986-06-24024 June 1986 Response to Petition of Coalition for Alternatives to Shearon Harris (Cash) for Leave to Intervene.Petition Filed on 860609,4 Yrs After Deadline.Cash Should Be Foreclosed from Participation.W/Certificate of Svc ML20205T4071986-06-0909 June 1986 Petition of Coalition for Alternatives to Shearon Harris for Leave to Intervene & Request for Hearing.Certificate of Svc Encl ML20204A4891986-05-0808 May 1986 Response to Conservation Council of North Carolina & W Eddleman Request for Admission of New Contention WB-4 Re Falsification of Exposure Records.Request Should Be Denied. Certificate of Svc & SA Browne Affidavits Encl ML20210K6981986-04-22022 April 1986 Motion for Admission of New Contention WB-4, Falsification of Exposure Records. Records Systematically Falsified to Reflect Lower Doses to Workers.Requests Opportunity to Respond If Contention Opposed ML20136J4171986-01-0303 January 1986 Answer to W Eddleman 851223 Response to Contention 57-C-57 Re Contaminated Injured Persons.Contentions Should Be Limited to Issues Heard in Guard Vs Nrc.Contention Opposed. Certificate of Svc Encl ML20137H7251985-11-22022 November 1985 Petition of Atty General of State of Nc for Leave to Intervene ML20133J2301985-10-15015 October 1985 Response in Opposition to W Eddleman Proposed Contention Re Emergency Planning Exercise.Svc List,Exercise Evaluation Rept,Operations Journal & Insp Rept 50-400/85-20 Encl ML20133K6601985-10-15015 October 1985 Response to W Eddleman 850930 Proposed Contentions Based on Emergency Planning Exercise.Certificate of Svc Encl ML20133F3661985-09-30030 September 1985 Requests That Listed Contentions Based on May 1985 Emergency Planning Exercise Be Admitted as There Are No Other Means or Parties to Protect or Represent Author Interests in Matters.Certificate of Svc Encl ML20134H2051985-08-26026 August 1985 Response in Opposition to W Eddleman Contentions Re Spill of Reactor Water.Contention Should Be Rejected for Failure to Comply w/10CFR2.714(b).Certificate of Svc Encl ML20134H2201985-08-23023 August 1985 Response to W Eddleman Proposed Contentions EM-1,EM-2 & EM-3 Re Notification of State & Local Emergency Mgt Agencies. Contentions Should Not Be Admitted Due to Lack of Requisite Basis & Specificity.Certificate of Svc Encl ML20133A0341985-07-31031 July 1985 Petition of Lh Thornburg for Leave to Intervene ML20128H4071985-05-22022 May 1985 Response Opposing W Eddleman 850429 Proffered Contentions 227-CC & 227-DD Re Allegations That Public Info Brochure Must Provide Directions to Evacuation Shelters & Title on Evacuation Routes Chart Misleading.Certificate of Svc Encl ML20117H6751985-05-0909 May 1985 Response Opposing Eddleman Proposed Contentions 227-CC & 227-DD Re Brochure Evacuation Route Chart.Contentions Constitute Editing of Brochure & Therefore Not Litigable. Certificate of Svc Encl ML20116L7211985-04-29029 April 1985 Petition Requesting Admittance of Contentions 227-CC & DD Re Brochure Additions Served on 850416 Concerning Emergency Plan Evacuation & Shelter for Settlement or Litigation. Certificate of Svc Encl ML20102A7691985-02-0606 February 1985 Response Opposing Intervenor 850118 Request for New Contention WB-3 Re Drug Use During Const.Contention Lacks Basis & Specificity & Unsubtantiated Broad Issues Delay Proceeding.Certificate of Svc Encl ML20102A4201985-02-0404 February 1985 Submits Diesel Generator Info & Contentions 178-AA & 179-AA for Litigation,In Response to Past ASLB Order ML20113D9501985-01-18018 January 1985 Request for Admission of New Contention WB-3 Re Drug & Alcohol Abuse at Const Site.News Article Supporting Contention & Certificate of Svc Encl ML20108A2281984-11-13013 November 1984 Response to Late Filed Contentions of W Eddleman & Conservation Council of North Carolina Based on Cv Vo Affidavit.Contentions WB-1-2 & 41C-414H Should Be Rejected. Certificate of Svc Encl ML20096B8661984-08-31031 August 1984 Responses to Discovery on Emergency Planning Contentions (First Set).Certificate of Svc Encl.Related Correspondence ML20096B5131984-08-28028 August 1984 Response to Eddleman 840810 Contentions on Emergency Plan Brochure.Certificate of Svc Encl ML20094N1511984-08-10010 August 1984 Eddleman Contentions on Emergency Plan Brochure, Safety Info for Shearon Harris Nuclear Power Plant. Certificate of Svc Encl ML20093G1341984-07-20020 July 1984 Response in Support of Preamble to Revised Contention 9 Re Environ Qualification of Electrical Equipment.Certificate of Svc Encl ML20092N7151984-06-29029 June 1984 Response to Eddleman Proposed Contentions 65-A & 65-B Re Questionable Structural Integrity Due to Voids from out-of-spec Sump & Improper Vibration Technique. Certificate of Svc Encl ML20092D9521984-06-19019 June 1984 Response Opposing W Eddleman 840605 Motion to Reinstate Contention 58(2d) Re Financial Qualifications.Certificate of Svc Encl ML20197H3921984-06-14014 June 1984 New Eddleman Contention 65-A Re Questionable Structural Integrity Due to Voids from out-of-spec Slump,Improper Vibration Technique & Inadequate Strength of Harris Containment Concrete ML20091M5611984-06-0505 June 1984 Withdrawal of Eddleman Contentions 85/86 & Second Motion to Reinstate Contention 58(2d) Re Financial Qualifications ML20084E1331984-04-28028 April 1984 Answer Opposing Eddleman Proposed Contentions on Emergency Response Plans.Certificate of Svc Encl ML20084D0341984-04-27027 April 1984 Response Opposing R Wilson 840413 Contentions Re State of Nc Emergency Response Plan.All Contentions Should Be Rejected. Certificate of Svc Encl ML20083P7471984-04-16016 April 1984 Motion to Require Svc of All Amends & Changes to Emergency Plan on Intervenor & Motion to Amend Emergency Planning Contentions.Certificate of Svc Encl.Related Correspondence ML20083L2951984-04-13013 April 1984 Contentions on State of Nc Emergency Response Plan. Certificate of Svc Encl ML20083M0871984-04-12012 April 1984 Contentions on Emergency Plan (Second Set).Plan Fails to Indicate Number of Volunteer Personnel Necessary or Assuredly Available to Perform Assigned Responsibilities. Certificate of Svc Encl ML20088A0771984-04-0505 April 1984 Suppl to Feb 1984 Petition for Leave to Intervene in Intervenor Charge Re State of Nc Emergency Response Plan. Certificate of Svc Encl ML20087P5211984-04-0303 April 1984 Partial Response & Contentions 157 & 151 Re Offsite Emergency Plan ML20087P8701984-04-0303 April 1984 Contentions Arising from Review of Emergency Response Plan, Per ASLB 840308 Order.Certificate of Svc Encl ML20086R9141984-02-28028 February 1984 Response Opposing W Eddleman Motion to Admit Contention 58(2d) on Financial Qualifications of co-applicants.ASLB Has No Basis or Authority to Reconsider Original Ruling on Contention & Motion Must Be Denied.Certificate of Svc Encl ML20086M8231984-02-15015 February 1984 Certification to Applicant 840118 Motion for Summary Disposition of Eddleman Contention 65.Motion Identifies One Instance of Honeycombing or Voids in Containment Base Mat, Exterior Walls & Dome.Certificate of Svc Encl ML20086N5051984-02-15015 February 1984 Motion to Withdraw Contention III Re Mgt Capability. Certificate of Svc Encl ML20080L0401984-02-13013 February 1984 Motion to Reconsider & Admit Contention 58 Re Financial Qualifications of co-applicants.Certificate of Svc Encl ML20080D2701984-02-0606 February 1984 Answer to W Eddleman Motion for Further Deferral of Parts of Contention 107 & Eddleman New Contentions & Amended Deferred Contentions in Response to NRC Ser.Aslb Should Deny Motion & Reject New SER Contentions.Certificate of Svc Encl ML20080G2391984-02-0606 February 1984 Request for Clarification & Objections to ASLB 840127 Order Re Eddleman Contentions 37A,37B & 8F2.Certificate of Svc Encl ML20079L4371984-01-23023 January 1984 Response Opposing Eddleman Contentions 169-172 Re Safety Parameter Display Sys.Contentions Wholly W/O Basis, Operate on Faulty Understanding of Sys & Should Not Be Admitted.Certificate of Svc Encl ML20079H4571984-01-17017 January 1984 New Contentions & Amended Deferred Contentions,In Response to NRC SER ML20083H5711984-01-0303 January 1984 Filing of New Contentions 169,170,171 & 172 Re Inadequate Safety Parameter Display Sys Design ML20081K0091983-11-0404 November 1983 Response to Applicant & NRC 830929 Responses to Joint Intervenors 830906 Contentions Re Security Plan.Encl Withheld (Ref 10CFR73.21).Certificate of Svc Encl ML20081E0091983-10-28028 October 1983 Response to Util Motion for Summary Disposition of Contention Ii.Veracity of All General Facts Disputed.List of Matters in Dispute on Contention II & Certificate of Svc Encl 1999-05-05
[Table view] Category:RESPONSES & CONTENTIONS
MONTHYEARML20206G4051999-05-0505 May 1999 Applicant Answer to Petitioner Board of Commissioners of Orange County Contentions.* Requests That Technical Contentions in Section III & Environ Contentions in Section IV Not Be Admitted.With Certificate of Svc ML20206F9491999-05-0505 May 1999 NRC Staff Response to Orange County Supplemental Petition to Intervene.* None of Petitioner Proposed Contentions Meet Commission Requirements for Admissible Contention.Petitioner 990212 Request Should Be Denied.With Certificate of Svc ML20206A0851999-04-22022 April 1999 Erratum to Orange County Supplemental Petition to Intervene.* Citation to Vermont Yankee LBP-87-17,should Be Amended to Read Vermont Yankee Nuclear Power Co (Vermont Yankee Nuclear Power Station).With Certificate of Svc ML20196K8771999-04-0505 April 1999 Orange County Supplemental Petition to Intervene.* Informs That Orange County Contentions Should Be Admitted for Litigation in Proceeding ML20206J9151986-06-24024 June 1986 Response to Petition of Coalition for Alternatives to Shearon Harris (Cash) for Leave to Intervene.Petition Filed on 860609,4 Yrs After Deadline.Cash Should Be Foreclosed from Participation.W/Certificate of Svc ML20205T4071986-06-0909 June 1986 Petition of Coalition for Alternatives to Shearon Harris for Leave to Intervene & Request for Hearing.Certificate of Svc Encl ML20204A4891986-05-0808 May 1986 Response to Conservation Council of North Carolina & W Eddleman Request for Admission of New Contention WB-4 Re Falsification of Exposure Records.Request Should Be Denied. Certificate of Svc & SA Browne Affidavits Encl ML20210K6981986-04-22022 April 1986 Motion for Admission of New Contention WB-4, Falsification of Exposure Records. Records Systematically Falsified to Reflect Lower Doses to Workers.Requests Opportunity to Respond If Contention Opposed ML20136J4171986-01-0303 January 1986 Answer to W Eddleman 851223 Response to Contention 57-C-57 Re Contaminated Injured Persons.Contentions Should Be Limited to Issues Heard in Guard Vs Nrc.Contention Opposed. Certificate of Svc Encl ML20137H7251985-11-22022 November 1985 Petition of Atty General of State of Nc for Leave to Intervene ML20133J2301985-10-15015 October 1985 Response in Opposition to W Eddleman Proposed Contention Re Emergency Planning Exercise.Svc List,Exercise Evaluation Rept,Operations Journal & Insp Rept 50-400/85-20 Encl ML20133K6601985-10-15015 October 1985 Response to W Eddleman 850930 Proposed Contentions Based on Emergency Planning Exercise.Certificate of Svc Encl ML20133F3661985-09-30030 September 1985 Requests That Listed Contentions Based on May 1985 Emergency Planning Exercise Be Admitted as There Are No Other Means or Parties to Protect or Represent Author Interests in Matters.Certificate of Svc Encl ML20134H2051985-08-26026 August 1985 Response in Opposition to W Eddleman Contentions Re Spill of Reactor Water.Contention Should Be Rejected for Failure to Comply w/10CFR2.714(b).Certificate of Svc Encl ML20134H2201985-08-23023 August 1985 Response to W Eddleman Proposed Contentions EM-1,EM-2 & EM-3 Re Notification of State & Local Emergency Mgt Agencies. Contentions Should Not Be Admitted Due to Lack of Requisite Basis & Specificity.Certificate of Svc Encl ML20133A0341985-07-31031 July 1985 Petition of Lh Thornburg for Leave to Intervene ML20128H4071985-05-22022 May 1985 Response Opposing W Eddleman 850429 Proffered Contentions 227-CC & 227-DD Re Allegations That Public Info Brochure Must Provide Directions to Evacuation Shelters & Title on Evacuation Routes Chart Misleading.Certificate of Svc Encl ML20117H6751985-05-0909 May 1985 Response Opposing Eddleman Proposed Contentions 227-CC & 227-DD Re Brochure Evacuation Route Chart.Contentions Constitute Editing of Brochure & Therefore Not Litigable. Certificate of Svc Encl ML20116L7211985-04-29029 April 1985 Petition Requesting Admittance of Contentions 227-CC & DD Re Brochure Additions Served on 850416 Concerning Emergency Plan Evacuation & Shelter for Settlement or Litigation. Certificate of Svc Encl ML20102A7691985-02-0606 February 1985 Response Opposing Intervenor 850118 Request for New Contention WB-3 Re Drug Use During Const.Contention Lacks Basis & Specificity & Unsubtantiated Broad Issues Delay Proceeding.Certificate of Svc Encl ML20102A4201985-02-0404 February 1985 Submits Diesel Generator Info & Contentions 178-AA & 179-AA for Litigation,In Response to Past ASLB Order ML20113D9501985-01-18018 January 1985 Request for Admission of New Contention WB-3 Re Drug & Alcohol Abuse at Const Site.News Article Supporting Contention & Certificate of Svc Encl ML20108A2281984-11-13013 November 1984 Response to Late Filed Contentions of W Eddleman & Conservation Council of North Carolina Based on Cv Vo Affidavit.Contentions WB-1-2 & 41C-414H Should Be Rejected. Certificate of Svc Encl ML20096B8661984-08-31031 August 1984 Responses to Discovery on Emergency Planning Contentions (First Set).Certificate of Svc Encl.Related Correspondence ML20096B5131984-08-28028 August 1984 Response to Eddleman 840810 Contentions on Emergency Plan Brochure.Certificate of Svc Encl ML20094N1511984-08-10010 August 1984 Eddleman Contentions on Emergency Plan Brochure, Safety Info for Shearon Harris Nuclear Power Plant. Certificate of Svc Encl ML20093G1341984-07-20020 July 1984 Response in Support of Preamble to Revised Contention 9 Re Environ Qualification of Electrical Equipment.Certificate of Svc Encl ML20092N7151984-06-29029 June 1984 Response to Eddleman Proposed Contentions 65-A & 65-B Re Questionable Structural Integrity Due to Voids from out-of-spec Sump & Improper Vibration Technique. Certificate of Svc Encl ML20092D9521984-06-19019 June 1984 Response Opposing W Eddleman 840605 Motion to Reinstate Contention 58(2d) Re Financial Qualifications.Certificate of Svc Encl ML20197H3921984-06-14014 June 1984 New Eddleman Contention 65-A Re Questionable Structural Integrity Due to Voids from out-of-spec Slump,Improper Vibration Technique & Inadequate Strength of Harris Containment Concrete ML20091M5611984-06-0505 June 1984 Withdrawal of Eddleman Contentions 85/86 & Second Motion to Reinstate Contention 58(2d) Re Financial Qualifications ML20084E1331984-04-28028 April 1984 Answer Opposing Eddleman Proposed Contentions on Emergency Response Plans.Certificate of Svc Encl ML20084D0341984-04-27027 April 1984 Response Opposing R Wilson 840413 Contentions Re State of Nc Emergency Response Plan.All Contentions Should Be Rejected. Certificate of Svc Encl ML20083P7471984-04-16016 April 1984 Motion to Require Svc of All Amends & Changes to Emergency Plan on Intervenor & Motion to Amend Emergency Planning Contentions.Certificate of Svc Encl.Related Correspondence ML20083L2951984-04-13013 April 1984 Contentions on State of Nc Emergency Response Plan. Certificate of Svc Encl ML20083M0871984-04-12012 April 1984 Contentions on Emergency Plan (Second Set).Plan Fails to Indicate Number of Volunteer Personnel Necessary or Assuredly Available to Perform Assigned Responsibilities. Certificate of Svc Encl ML20088A0771984-04-0505 April 1984 Suppl to Feb 1984 Petition for Leave to Intervene in Intervenor Charge Re State of Nc Emergency Response Plan. Certificate of Svc Encl ML20087P5211984-04-0303 April 1984 Partial Response & Contentions 157 & 151 Re Offsite Emergency Plan ML20087P8701984-04-0303 April 1984 Contentions Arising from Review of Emergency Response Plan, Per ASLB 840308 Order.Certificate of Svc Encl ML20086R9141984-02-28028 February 1984 Response Opposing W Eddleman Motion to Admit Contention 58(2d) on Financial Qualifications of co-applicants.ASLB Has No Basis or Authority to Reconsider Original Ruling on Contention & Motion Must Be Denied.Certificate of Svc Encl ML20086M8231984-02-15015 February 1984 Certification to Applicant 840118 Motion for Summary Disposition of Eddleman Contention 65.Motion Identifies One Instance of Honeycombing or Voids in Containment Base Mat, Exterior Walls & Dome.Certificate of Svc Encl ML20086N5051984-02-15015 February 1984 Motion to Withdraw Contention III Re Mgt Capability. Certificate of Svc Encl ML20080L0401984-02-13013 February 1984 Motion to Reconsider & Admit Contention 58 Re Financial Qualifications of co-applicants.Certificate of Svc Encl ML20080D2701984-02-0606 February 1984 Answer to W Eddleman Motion for Further Deferral of Parts of Contention 107 & Eddleman New Contentions & Amended Deferred Contentions in Response to NRC Ser.Aslb Should Deny Motion & Reject New SER Contentions.Certificate of Svc Encl ML20080G2391984-02-0606 February 1984 Request for Clarification & Objections to ASLB 840127 Order Re Eddleman Contentions 37A,37B & 8F2.Certificate of Svc Encl ML20079L4371984-01-23023 January 1984 Response Opposing Eddleman Contentions 169-172 Re Safety Parameter Display Sys.Contentions Wholly W/O Basis, Operate on Faulty Understanding of Sys & Should Not Be Admitted.Certificate of Svc Encl ML20079H4571984-01-17017 January 1984 New Contentions & Amended Deferred Contentions,In Response to NRC SER ML20083H5711984-01-0303 January 1984 Filing of New Contentions 169,170,171 & 172 Re Inadequate Safety Parameter Display Sys Design ML20081K0091983-11-0404 November 1983 Response to Applicant & NRC 830929 Responses to Joint Intervenors 830906 Contentions Re Security Plan.Encl Withheld (Ref 10CFR73.21).Certificate of Svc Encl ML20081E0091983-10-28028 October 1983 Response to Util Motion for Summary Disposition of Contention Ii.Veracity of All General Facts Disputed.List of Matters in Dispute on Contention II & Certificate of Svc Encl 1999-05-05
[Table view] Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20217L8481999-10-25025 October 1999 NRC Staff First Supplemental Response to Applicant First Set of Discovery Requests to NRC Staff.* Staff Objects to Document Request as Being Overly Broad & Unduly Burdensome. with Certification of Svc ML20217H9661999-10-20020 October 1999 NRC Staff Second Supplemental Response to Orange County First Set of Discovery Requests to NRC Staff.* Listed Documents Requested to Be Produced.With Certificate of Svc. Related Correspondence ML20217E0881999-10-18018 October 1999 Order (Granting Discovery Extension Request).* Board of Commission of Orange County 991013 Motion for Extension of 991031 Discovery Deadline,Granted,In That Parties Shall Have Up to 991104.With Certificate of Svc.Served on 991018 ML20217F7711999-10-17017 October 1999 Corrected Notice of Deposition of SE Turner.* Orange County Gives Notice That on 991104 Deposition Upon Oral Exam of Turner Will Be Deposed with Respect to Contention TC-2. Related Correspondence ML20217F7681999-10-17017 October 1999 Orange County Third Set of Discovery Requests to NRC Staff.* Submits Third Set of Discovery Requests & Requests Order by Presiding Officer That Discovery Be Answered within 14 Days. with Certificate of Svc.Related Correspondence ML20217D6181999-10-14014 October 1999 Request for Entry Upon Harris Site.* Staff Hereby Requests That Applicant,Cp&L Permit Entry Into Shearon Harris Nuclear Plant,For Viewing & Insp of Plant Spent Fuel Pool Bldg. with Certificate of Svc.Related Correspondence ML20217E2611999-10-13013 October 1999 Orange County Second Suppl Response to Applicant First Set of Discovery Requests & First Suppl Response to NRC Staff First Set of Discovery Requests.* Clarifies That G Thompson Sole Witness.With Certificate of Svc.Related Correspondence ML20217E2581999-10-13013 October 1999 Orange County Motion for Extension of Discovery Deadline.* Orange County Requests Extension of 991031 Deadline for Concluding Discovery Proceeding.Extension Needed to Permit Dispositions of Two CP&L Witnesses.With Certificate of Svc ML20217E1461999-10-13013 October 1999 Request for Entry Upon Harris Site.* Entry Requested for Purpose of Inspecting SFP Bldg & Associated Piping.With Certificate of Svc.Related Correspondence ML20217D5561999-10-13013 October 1999 Applicant Second Set of Discovery Requests Directed to Board of Commissioners of Orange County.* Applicant Requests Answers to Listed Interrogatories & Requests for Admission. with Certificate of Svc.Related Correspondence ML20217D5761999-10-13013 October 1999 Applicant Third Supplement Response to Board of Commissioners of Orange County First Set of Discovery Requests.* Provides Addl Responses to General Interrogatory 3.With Certificate of Svc.Related Correspondence ML20217D6201999-10-12012 October 1999 NRC Staff Response to Applicant First Set of Discovery Requests to NRC Staff.* Staff Will Respond to Applicant Specific Requests within 30 Days of Receipt of Applicant Requests.With Certificate of Svc.Related Correspondence ML20217D5661999-10-12012 October 1999 NRC Staff First Supplemental Response to Orange County First Set of Discovery Requests to NRC Staff.* Supplements Response by Naming C Gratton as Person Likely to Provide Affidavit.With Certificate of Svc.Related Correspondence ML20212M0271999-10-0707 October 1999 Notice (Opportunity to Make Oral or Written Limited Appearance Statements).* Board Will Entertain Oral Limited Appearance Statements Re CP&L 981223 Amend Request. with Certificate of Svc.Served on 991007 ML20212L1441999-10-0505 October 1999 NRC Staff Response to Orange County First Set of Discovery Requests to NRC Staff.* Staff Is Now Voluntarily Providing Responses to Orange County'S Request for Production of Documents.With Certificate of Svc.Related Correspondence ML20212J0801999-09-29029 September 1999 Orange County Second Set of Document Requests to NRC Staff.* Submits Second Set of Document Requests to NRC Pursuant to 10CFR2.744 & Board Memorandum & Order,Dtd 990729.With Certificate of Svc.Related Correspondence ML20212G0001999-09-24024 September 1999 Applicant First Set of Discovery Requests Directed to NRC Staff.* Requests Access to Documents Given to Board of Commissioners by Staff Pursuant to 990920 Discovery Request. with Certificate of Svc.Related Correspondence ML20212G0081999-09-24024 September 1999 Applicant First Suppl Response to Board of Commissioners of Orange County First Set of Discovery Requests.* Suppl Provides Addl Responses to General Interrogatories 2 & 3. with Certificate of Svc.Related Correspondence ML20212D7151999-09-20020 September 1999 Applicant Response to General Interrogatories & General Document Requests in NRC Staff First Set of Discovery Requests.* CP&L Filing Responses Per Staff Request within 14 Days....With Certificate of Svc.Related Correspondence ML20212D8521999-09-20020 September 1999 Orange County First Set of Discovery Requests to NRC Staff Including Request for Order Directing NRC Staff to Answer Certain Discovery Requests.* with Certificate of Svc. Related Correspondence ML20212C1231999-09-17017 September 1999 Orange County Responses to Applicant First Set of Document Production Request.* Orange County Has No Documents Responsive to Request.With Certificate of Svc.Related Correspondence ML20211N7481999-09-10010 September 1999 NRC Staff First Set of Discovery Requests Directed to Applicant Cp&L.* Staff Requests Applicant Produce All Documents Requested by & Provided to Bcoc. with Certificate of Svc.Related Correspondence ML20211N5021999-09-0808 September 1999 Orange County Objections & Responses to NRC Staff First Set of Discovery Requests.* County Objects to Questions to Extent That Staff Seek Discovery Beyond Scope of County Two Contentions.With Certificate of Svc.Related Correspondence ML20211M4201999-09-0707 September 1999 Applicant Response to Specific Document Requests in Board of Commissioners of Orange County First Set of Discovery Requests.* with Certificate of Svc.Related Correspondence ML20211M5001999-09-0303 September 1999 Orange County Supplemental Response to Applicant First Set of Interrogatories.* with Certificate of Svc.Related Correspondence ML20211H4931999-08-30030 August 1999 Orange County Objections to Applicant First Set of Discovery Requests & Response to Applicant First Set of Interrogatories.* Objects to First Set of Discovery Requests.With Certificate of Svc.Related Correspondence ML20211B7951999-08-23023 August 1999 NRC Staff First Set of Discovery Requests Directed to Board of Commissioners of Orange County (Bcoc).* Staff Requests That Bcoc Produce All Documents Requested by Applicant. with Certificate of Svc.Related Correspondence ML20211B8361999-08-23023 August 1999 Applicant Response to General Interrogatories & General Document Requests in Board of Commissioners of Orange County First Set of Discovery Requests.* with Certificate of Svc. Related Correspondence ML20210T3531999-08-16016 August 1999 Applicant First Set of Discovery Requests Directed to Board of Commissioners of Orange County (Bcoc).* CP&L Requests That Bcoc Answer Listed General Interrogatories by 990830. with Certificate of Svc.Related Correspondence ML20210L9571999-08-0606 August 1999 Orange County First Set of Discovery Requests Directed to Applicant.* Interrogatories & Document Production Requests Cover All Info in Possession,Custody & Control of Cp&L.With Certificate of Svc.Related Correspondence ML20216E2041999-07-29029 July 1999 Memorandum & Order (Granting Request to Invoke 10CFR Part 2, Subpart K Procedures & Establishing Schedule).* Board Grants Carolina Power & Light Co 990721 Request to Proceed Under Subpart K.With Certificate of Svc.Served on 990730 ML20210B2271999-07-21021 July 1999 Applicant Request for Oral Argument to Invoke Subpart K Hybrid Hearing Procedures & Proposed Schedule.* Applicant Recommends Listed Schedule for Discovery & Subsequent Oral Argument.With Certificate of Svc ML20209G7371999-07-16016 July 1999 Notice of Hearing (License Amend Application to Expand Sf Pool Capacity).* Provides Notice of Hearing in Response to Commissioners of Orange County Request for Hearing Re CP&L Amend Application.With Certificate of Svc.Served on 990716 ML20209D1791999-07-12012 July 1999 Memorandum & Order (Ruling on Standing & Contentions).* Grants Petitioner 990212 Hearing Request Re Intervention Petition Challenging CP&L 981223 Request for Increase in Sf Storage Capacity.With Certificate of Svc.Served on 990712 ML20212J5831999-07-0101 July 1999 Notice of Appearance.* Informs That SL Uttal Will Enter Appearance in Proceeding Re Carolina Power & Light Co.Also Encl,Notice of Withdrawal for ML Zobler,Dtd 990701. with Certificate of Svc ML20196A8751999-06-22022 June 1999 Order (Corrections to 990513 Prehearing Conference Transcript).* Proposed Corrections to Transcript of Board 990513 Initial Prehearing Conference Submitted by Petitioner & Application.With Certificate of Svc.Served on 990622 ML20207D6991999-05-27027 May 1999 Orange County Proposed Corrections to Transcript of 990113 Prehearing Conference.* Orange County Submits Proposed Corrections to Transcript of Prehearing Conference of 990513.With Certificate of Svc ML20207D6651999-05-27027 May 1999 Applicant Proposed Corrections to Prehearing Conference Transcript.* ASLB Ordered That Any Participant Wishing to Propose Corrections to Transcript of 990513 Prehearing Conference Do So by 990527.With Certificate of Svc ML20207D6891999-05-27027 May 1999 Orange County Response to Applicant Proposed Rewording of Contention 3,regarding Quality Assurance.* County Intends to Renew Request for Admission of Aspect of Contention.With Certificate of Svc ML20206R8731999-05-20020 May 1999 Memorandum & Order (Transcript Corrections & Proposed Restatement of Contention 3).* Any Participant Wishing to Propose Corrections to Transcript of 990513,should Do So on or Before 990527.With Certificate of Svc.Served on 990520 ML20206R2411999-05-13013 May 1999 Transcript of 990513 Prehearing Conference in Chapel Hill,Nc Re Carolina Power & Light Co.Pp 1-176.Supporting Documentation Encl ML20206H9331999-05-11011 May 1999 Notice (Changing Location & Starting Time for Initial Prehearing Conference).* New Location for Conference, Southern Human Resources Ctr,Main Meeting Room,Chapel Hill, Nc.With Certificate of Svc.Served on 990511 ML20206G4051999-05-0505 May 1999 Applicant Answer to Petitioner Board of Commissioners of Orange County Contentions.* Requests That Technical Contentions in Section III & Environ Contentions in Section IV Not Be Admitted.With Certificate of Svc ML20206F9491999-05-0505 May 1999 NRC Staff Response to Orange County Supplemental Petition to Intervene.* None of Petitioner Proposed Contentions Meet Commission Requirements for Admissible Contention.Petitioner 990212 Request Should Be Denied.With Certificate of Svc ML20206A0851999-04-22022 April 1999 Erratum to Orange County Supplemental Petition to Intervene.* Citation to Vermont Yankee LBP-87-17,should Be Amended to Read Vermont Yankee Nuclear Power Co (Vermont Yankee Nuclear Power Station).With Certificate of Svc ML20205Q8121999-04-21021 April 1999 Order (Granting Motion to Relocate Prehearing Conference).* Initial Prehearing Conference Will Be Held in District Court of Orange County Courtroom,Chapel Hill,Nc on 990513 as Requested.With Certificate of Svc.Served on 990421 ML20196K8771999-04-0505 April 1999 Orange County Supplemental Petition to Intervene.* Informs That Orange County Contentions Should Be Admitted for Litigation in Proceeding ML20196K8861999-04-0505 April 1999 Declaration of Gordon Thompson.* Informs of Participation in Preparation of Orange County Contentions Re Proposed License Amend ML20205E3101999-04-0101 April 1999 Memorandum & Order (Protective Order).* Grants 990326 Motion of Petitioner for Approval of Proposed Protective Order to Govern Use & Dissemination of Proprietary or Other Protected Matls.With Certificate of Svc.Served on 990203 ML20196K9041999-03-31031 March 1999 Declaration of DA Lochbaum,Nuclear Safety Engineer Union of Concerned Scientists,Re Technical Issues & Safety Matters Involved in Harris Nuclear Plant License Amend for Sfs.* with Certificate of Svc 1999-09-08
[Table view] |
Text
rf e
. UY?k January 25, 1983 E3 JAN27 Pi:30 UNITED STATES OF AMERICA-NUCLEAR REGULATORY COMMISSION
- 1 ;
C'l
((['
BEFORE THE ATOMIC SAFETY AND LICENSING POARD In the Matter of )
)
CAROLINA POWER & LIGHT COMPANY ) Docket Nos. 50-400 OL AND NORTH CAROLINA EASTERN ) 50-401 OL MUNICIPAL POWER AGENCY ) *
)
(Shearon Harris Nuclear Power )
Plant, Units 1 and 2) )
' APPLICANTS' RESPONSE TO INTERVENOR WELLS EDDLEMAN'S MOTION CONCERNING DCRDR INFORMATION AND PROPOSED NEW CONTENTIONS By letter dated December 7, 1982, Applicants filed with the NRC Staff a Detailed Control Room Design Review ("DCRDR")
Report prepared by Essex Corporation for Harris Unit 1. Copies of the DCRDR Report were filed with certain lead intervenors and the public documents rooms in Chapel Hill and Wake County, North Carolina. On December 17, 1982, the NRC Office of Nuclear Reactor Regulation issued Generic Letter No. 82-33, Supplement 1 to NUREG-0737. The purpose of Supplement 1 to NUREG-0737 is, inter alia, to provide additional clarification regarding DCRDR's. Enclosures to Supplement 1 to NUREG-0737
. set forth certain requirements that must be met by all l
l l
DR 0 000 0 [k G PDR
\ U/
licensees and list guidance documents which establish acceptable means for meeting those requirements.
The DCRDR Report discusses the human factors engineering evaluation of the Harris Unit 1 control room design. This evaluation was conducted between April 1980 and January 1981, and consisted of a review of all available design documentation and a survey of the Harris simulator. It included a review of human engineering requirements specifications, the main control board design, annunciators, work space, systems operation analysis and emergency procedures review. A number of recom-mendations were made to improve the control room' design and layout. Based on the DCRDR, the Harris Unit 1 control room design and layout were substantially revised.
Mr. Eddleman complains that he does not have access to all of the Applicants' information relating to the DCRDR. In fact, he accuses Applicants of withholding from him information necessary to formulate contentions.1/ Mr. Eddleman echos Dr.
Wilson's request that he be allowed to file late contentions without showing good cause if such late contentions are based i
! on information referenced in the DCRDR but not yet available to him. For the reasons set forth in " Applicants' Response to Intervenor Wilson's Response to Human Factors Design Evaluation 1/ Mr. Eddleman's accusation is unfounded. The DCRDR Report that is available to him is the only document on human factors engineering and control design that has been submitted thus far by Applicants to the NRC Staff.
l t
I i
Report For the Shearon Harris I Control Room," dated January 21, 1983, Mr. Eddleman has no right to insist on discovery as a means to obtain information to formulate a contention or to establish the basis for a generalized contention.
All holders of construction permits are given until April 15, 1983 to propose a schedule for completing each of the basic requirements identified in Supplement 1 to NUREG-0737. Mr.
Eddleman has proposed new contentions by simply using Supplement 1 to NUREG-0737 to critique Applicants' DCRDR. It should not come as a shock to anyone that Applicants did not address in the DCRDR Report requirements that did'not exist at the time the Report was written. Applicants oppose Mr.
Eddleman's contentions on the DCRDR, which are based solely on inadequacies perceived as a result of new requirements set forth in Supplement 1 to NUREG-0737. While we discuss below each proposed contention, in general Mr. Eddleman's contentions are premature. Applicants have until April 15, 1983 to set forth a schedule for compliance with Supplement 1 to NUREG-0737. Until such time that Applicants have had an opportunity to respond to new requirements, Mr. Eddleman is not in a position to provide a reasonable basis with any spe-cificity to support a contention alleging that Applicants will not meet such requirements. To simply state that Applicants have not yet addressed a new requirement, while true, does not present a litigable issue.
i
Applicants objections to Mr. Eddleman's approach in formulating his proposed new contentions is not so much procedural as a substantive objection to what should be litigated in an operating license proceeding. Mr. Eddleman is provided an opportunity to litigate those issues about which he has a specific concern and regarding which he can establish he has a sound basis with requisite specificity to support that concern. The DCRDR Report and the wealth of information promulgated by the NRC on the issue of control room design and human factors, engineering provides ample substance for formulating a contention that reflects a true con ~cern. Mr.
Eddleman has not set forth such a contention. Instead, he has, in effect, demanded that Applicants prove that they will meet new regulatory requirements. Mr. Eddleman's role is not to serve as a surrogate NRC reviewer.
Contention 132B (Safety Parameter Display System)
This Contention states that the design of the Harris Unit 1 control room does not comply with the requirements of Supplement 1 to NUREG-0737 because the DCRDR fails to provide for a Safety Parameter Display System ("SPDS"). It is true that the DCRDR, which predated Supplement 1 to NUREG-0737, does
! not include provisions for an SPDS. For the reasonc discussed above, Contention 132B.is premature. Applicants will respond I
i to this new requirement on or before April 15, 1983, as required by Supplement 1 to NUREG-0737. Mr. Eddleman has not
! _4 l 1 l
i
.4 alleged that Applicants will not comply with the SPDS requirement. Certainly he has not provided any basis with requisite specificity for a contention that Applicants will not meet the SPDS requirement in its final control room design. He simply alleges that the DCRDR does not now incorporate the SPDS. Contention 132B should be rejected for failure to state a litigable contention.
Contention 132C (Qualifications of DCRDR Review Team)
This Contention faults Applicants for not establishing the multi-disciplinary qualifications of the Essex Corporation review team which prepared the DCRDR Report. In effect, Mr.
Eddleman is asking for the professional qualifications of the Essex Corporation personnel and CP&L personnel who performed the control room design evaluation. There is no requirement that Applicants set forth in the DCRDR Report the specific qualifications of the review team members, who are known both to Applicants and to the NRC Staff. Mr. Eddleman does not set forth any basis with requisite specificity to support an allegation that the personnel who performed the DCRDR do not meet the requirements of Supplement 1 to NUREG-0737. Without some basis to support such an allegation Applicants are not required to provide detailed information to satisfy Mr.
Eddleman's curiosity. Contention 132C must be rejected for failure to state a contention with basis and requisite spe-cificity.
I
Contention 132(C)(II)2/ (DCRDR Fails to Comply with Supplement 1 to NUREG-0737)
This Contention alleges that the DCRDR fails to comply with a series of specific requirements set forth in Supplement 1 to NUREG-0737, which Applicants are required to meet. In some cases, e.g., where procedures have yet to be written, Applicants are not in a position to demonstrate that all of the requirements of Supplement 1 to NUREG-0737 have been met. In other cases, the requirement set forth in Supplement 1 to NUREG-0737 have been met, but information to demonstrate that
-fact was not detailed in the DCRDR Report, nor was there any requirement that such information be provided in the Report.
Applicants oppose admission of Contention 132(C)(II) as premature for the reasons set forth in response to the Contentions 132B and 132C. Mr. Eddleman has set himself up as a technical reviewer. He has not established an independent concern regarding the control room design. Again, Mr. Eddleman has not set forth with basis and requisite specificity an allegation that Applicants will not meet applicable regulatory requirements.
Contention 132D (Harris Unit 2 Control Room Design)
This Contention states that the DCRDR " utterly fails to comply with the requirements of NUREG-0737 Rev. 1 with respect to Harris Unit 2." The DCRDR was only intended to address the
. 2/ This is the second contention denominated Contention 132C.
O 1
control room design for Harris Unit 1. Once the control room design for Harris Unit 1 is completed and approved by the NRC, the Unit 2 control room design will simply replicate the approved Unit 1 control room design. Mr. Eddleman has failed to state a contention that is a matter in controversy and is litigable in this proceeding.
Contention 142 (Meteorological Monitoring at Harris)
This Contention alleges that Applicants meteorological monitoring at Harris "is unable to accurately represent meteorological conditions within ten miles of the Plant." This contention is untimely. Mr. Eddleman fails to address the five factors for late filed contentions and fails to explain clearly, in appropriate detail, and separate from the rest of the Contention, just what is new about the Contention and why it could not have been advanced previously. See 10 C.F.R.
5 2.714(a)(1). Absent this explanation and a showing on the five lateness factors, a new proposed contention may not be considered. Duke Power Co. (Catawba Nuclear Station, Units 1 and 2), Docket Nos. 50-413 and 50-414, Memorandum and Order, (Reflecting Decisions Made Following Second Prehearing Conference), slip opinion at 7-8 (December 1, 1982).
Meteorological conditions and monitoring at the Harris site are discussed in considerable detail in the FSAR f 2,3.
Mr. Eddleman fails to point to any inadequacy in Applicants' discussion in the FSAR of meteorological data collection and
its applicability for emergency response. Furthermore, he has failed to state a basis with requisite specificity for the allegations made in this contention. In particular, he fails to indicate any correlation between meteorological data on wind direction and wind speed taken at North Carolina State University (in a city environment 21 miles northeast of the Harris site) and at the Raleigh-Du ham Airport (in a flat terrain without interfering trees or hills 19 miles north-northeast of the Harris site) with conditions within ten miles of the Harris site (which generally encompasses a wooded, rolling terrain). In any event in an emergency r'esponse situation meteorological data from the Harris tower would be supplemented by data from the Raleigh-Durham Airport, North Carolina state cooperative weather network, the Carolina Power
& Light Company Weather Center in Raleigh and National Weather Service Meteorological Stations.
For all of these reasons, Contention 142 must be rejected.
Contention 143 (Emergency Response Facilities)
This contention is overly broad, unfocused, and unsubstan-tiated to the extent it does not lend itself to a response. It is also untimely. See response to Contention 142 above. Mr.
Eddleman has not explained what new information is available which now prompted his generalized broadside on emergency response facilities. Mr. Eddleman simply asserts that Applicants' Emergency Operations Facility, alternate Emergency 1
Operations Facility, Emergency Operations Procedures, Technical Support Center, Operational Support Center and required communications between and among all of the above are inadequate and do not comply with requirements of Supplement 1 to NUREG-0737. He references 17 pages of requirements. He offers as the basis of his assertion the simple fact that "these facilities are either incomplete or unbuilt now, the communication lines do not exist and have not been tested, and NRC has not assessed CP&L's compliance with NUREG-0737 Rev. 1."
Applicants are entitled to be told at the outset "with clarity and precision" what arguments are being advanced.
Kansas Gas and Electric Company (Wolf Creek Generating Station, Unit No. 1), ALAB-279, 1 N.R.C. 559, 576 (1975). Mr.
Eddleman's contention is simply too broad to address with any 4 particularity.
Beyond that, the facts that facilities have not yet been built or communication lines have not yet been tested do not support a contention that these facilities will not be ade-quate. The fact that the NRC Staff has not yet assessed Applicants' compliance with Supplement 1 to NUREG-0737, which were only recently issued, does not give rise to a litigable contention.
Contention 143 is untimely, vague and imprecise, and without supporting basis with requisite specificity. It must be rejected.
i
Contention 144 (Emergency and Security Personnel Levels)
This contention alleges that Applicants' emergency and security personnel levels do not meet the requirements of Supplement 1 to NUREG-0737, Table 2. Contention 144 is untimely. Table 2 in Supplement 1 to NUREG-0737 simply summarizes information found in NUREG-0654, which was available prior to the date for timely filing of contentions. Mr.
Eddleman has not demonstrated good cause for late filing. See response to Contention 142 above.
The staffing levels set forth in Table 2 are goals, not requirements, in any event. See, e.g. Section 8.4.l(i),
Supplement 1 to NUREG-0737.
Similar to Contention 143, this contention is too broad and imprecise for response. There is no citation to which staffing levels, set forth in the FSAR, Mr. Eddleman finds insufficient. There is no basis with requisite specificity to support the generalized attack on staffing levels.
Contention 144 must be rejected as untimely, overly broad and unsupported.
For the foregoing reasons, Mr. Eddleman's motion must be denied and none of his new contentions should be admitted for litigation, esp ctfu ly submitt s .
- D 7 GQrge F. Trowbridge/,
- ?)C.
Th4 mas A. Baxter, P.IC.
John H. O'Neill, Jr, S W, PITTMAN, POTTE TROWBRIDGE 00 M Street, N.W.
Washington, D.C. 20036 (202) 822-1000
~
Richard E. Jones Samantha Francis Flynn CAROLINA POWER & LIGHT COMPANY P. O. Box 1551 Raleigh, North Carolina 27602 Counsel for Applicants Dated: January 25, 1983 t
l l
l l
I
~
s ,
~
January 25, 1983 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD l
, c-In the Matter of )
) , i CAROLINA POWER & LIGHT COMPANY ) Docket Nos. 50-400 OL <
AND NORTH CAROLINA EASTERN ) 50-401 OL -
MUNICIPAL POWER AGENCY )
)
(Shearon Harris Nuclear Power )
Plant, Units 1 and 2) ) -
1 CERTIFICATE OF SERVICE I hereby certify that copies of " Applicants' Response to Intervenor Wells Eddleman's Motion Concerning DCRDR 7
)
Information and Proposed New Contentions," dated January 25, /
1983, are being served to all those an the attached Service List by deposit in the U.S. Mail, first class, postage prepaid, this 25th day of January, 1983.
f I '
Dated: January 25, 1983 I
UNITED STATES OF AMERICA l NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )
)
CAROLINA POWER & LIGHT COMPANY ) Docket Nos. 50-400 OL AND NORTH CAROLINA EASTERN ) 50-401 OL MUNICIPAL POWER AGENCY )
) .
(Shearon Harris Nuclear Power )
Plant, Units 1 and 2) )
SERVICE LIST James L. Kelley, Esquire John D. Runkle, Esquire Atmic Safety and Licensing Board Conservation, Council of North Carolina U.S. Nuclear Regulatory Ccmnission 307 Granville Road Washington, D.C. 20555 Chapel Hill, North Carolina 27514 Mr. Glenn O. Bright M. Travis Payne, Esquire Ato 4c Safety and Licensing Board Edelstein and Payne U.S. Nuclear Regulatory Ccmnission P.O. Box 12643 Washington, D.C. 20555 Raleigh, North Carolina 27605 Dr. Janes H. Carpenter Dr. Richard D. Wilson Atcmic Safety and Licensing Board 729 Hunter Street U.S. Nuclear Regulatory Cenniasion Apex, North Carolina 27502 Washington, D.C. 20555 Mr. Wells Eddleman Charles A. Barth, Esquire 718-A Iredell Street Myron Karman, Esquire Durhan, North Carolina 27705 Office of Executive Iegal Director U.S. Nuclear Regulatory Ccmnission Ms. Patricia T. Newnan Washington, D.C. 20555 Mr. Slater E. Newman Citizens Against Nuclear Pcwer Docketing ard Servi Section 2309 Weymouth Court Office of the Secretary Raleigh, North Carolina 27612 U.S. Nuclear Regulatory Ccmnission Washington, D.C. 20555 Richard E. Jones, Esquire Vice President & Senior Counsel Mr. Daniel F. Read, President Carolina Power & Light Ccmpany Chapel Hill Anti-Nuclear Group Effort P.O. Box 1551 P.O. Box 524 Raleigh, Nortn Carolina 27602
'hapel Hill, North Carolina 27514