MONTHYEARGNRO-2008/00034, Three Month Response Extension Request to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2008-04-10010 April 2008 Three Month Response Extension Request to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Request ML0811304492008-04-30030 April 2008 Response to Request for 3-Month Extension, Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other GNRO-2008/00033, Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2008-05-0606 May 2008 Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Request GNRO-2008/00050, Clarification of Commitment in Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems2008-06-30030 June 2008 Clarification of Commitment in Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Request ML0816402662008-09-24024 September 2008 Month Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternative Course of Action Project stage: Other ML1110102282011-05-0202 May 2011 Closeout of Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other 2008-05-06
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000416/20240112024-10-16016 October 2024 – Fire Protection Team Inspection Report 05000416/2024011 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24257A0172024-09-17017 September 2024 Request for Withholding Information from Public Disclosure Unit 1 IR 05000416/20240122024-09-17017 September 2024 License Renewal Post Approval Phase 2 Inspection Report 05000416/2024012 ML24254A3602024-09-10010 September 2024 Pre-Submittal Slides for License Amendment Request, Criticality Safety Analysis, Technical Specification 4.3.1, Criticality and Technical Specification 5.5.14, Spent Fuel Storage Rack Neutron Absorber Monitoring Program IR 05000416/20244022024-09-0909 September 2024 Security Baseline Inspection Report 05000416/2024402 05000416/LER-2024-003, Feedwater Inlet Check Valve Incorrectly Determined Operable2024-08-26026 August 2024 Feedwater Inlet Check Valve Incorrectly Determined Operable ML24235A0832024-08-22022 August 2024 Evaluations Performed in Accordance with 10 CFR 50.54(q) for Changes to Emergency Planning Documents IR 05000416/20240052024-08-21021 August 2024 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24176A1202024-07-29029 July 2024 Issuance of Amendment 234 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b IR 05000416/20240022024-07-29029 July 2024 Integrated Inspection Report 05000416/2024002 ML24172A2502024-07-29029 July 2024 – Issuance of Amendment No. 233 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML24204A2432024-07-23023 July 2024 Notification of Cyber Security Baseline Inspection and Request for Information (05000416/2024403) ML24191A2432024-07-0909 July 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operations IR 05000416/20240102024-06-27027 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000416/2024010 ML24156A1762024-06-24024 June 2024 Regulatory Audit Summary in Support of License Amendment Requests to Adopt TSTF-505, Revision 2 and 10 CFR 50.69 (Epids L-2023-LLA-0081 and L-2023-LLA-0080) ML24165A1512024-06-13013 June 2024 Second Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk-Informe ML24163A2652024-06-11011 June 2024 Inservice Inspection Summary Report ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 05000416/LER-2024-002, Automatic Actuation of Reactor Protection System2024-05-28028 May 2024 Automatic Actuation of Reactor Protection System ML24130A0912024-05-0909 May 2024 Request for Information Letter License Renewal Phase 2 Inspection ML24128A1512024-05-0909 May 2024 Project Manager Assignment ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions IR 05000416/20240012024-05-0202 May 2024 Integrated Inspection Report 05000416 2024001 ML24122C6112024-05-0101 May 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. ML24116A0372024-04-25025 April 2024 Report of Technical Specification Bases Changes ML24113A0952024-04-22022 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24113A0972024-04-22022 April 2024 Annual Report of Individual Monitoring - NRC Form 5 for 2023 Per 1 0 CFR 20.2206 ML24107B0402024-04-16016 April 2024 Notification by Entergy Operations, Inc., of Proposed Economic Performance Incentive and Reliance on Post-Event Improvements in Plant Procedures And/Or Methods of Operation in FERC ML24107A8872024-04-16016 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair ML24100A0692024-04-0909 April 2024 Report of Changes or Errors to 10 CFR 50.46 Analysis ML24094A0992024-04-0303 April 2024 (GGNS) Core Operating Limits Report (COLR) Cycle 25, Revision O ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24087A1962024-03-27027 March 2024 High Pressure Core Spray Inoperable Due to Minimum Flow Valve Failure to Close IR 05000416/20220042024-03-19019 March 2024 – Amended Integrated Inspection Report 05000416/2022004 and Exercise of Enforcement Discretion ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24058A3512024-02-28028 February 2024 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000416/20230062024-02-28028 February 2024 Annual Assessment Letter for Grand Gulf Nuclear Station - Report 05000416/2023006 IR 05000416/20233012024-02-26026 February 2024 NRC Examination Report 05000416-2023301 ML24043A1892024-02-12012 February 2024 Spent Fuel Storage Radioactive Effluent Release Report for 2023 ML24012A1422024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0051 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24043A0732024-01-29029 January 2024 2024-01 Post Examination Comments IR 05000416/20230042024-01-25025 January 2024 Integrated Inspection Report 5000416/2023004 IR 05000416/20234012024-01-18018 January 2024 Cyber Security Inspection Report 05000416/2023401 (Public) ML24018A0222024-01-18018 January 2024 Core Operating Limits Report (COLR) Cycle 24, Revision 2 IR 05000416/20243012024-01-16016 January 2024 NRC Initial Operator Licensing Examination Approval 05000416/2024301 2024-09-09
[Table view] |
Text
April 30, 2008 Vice President, Operations Entergy Operations, Inc.
Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150
SUBJECT:
GRAND GULF NUCLEAR STATION, UNIT 1 - GENERIC LETTER 2008-01, MANAGING GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS, RESPONSE TO EXTENSION REQUEST (TAC NO. MD7831)
Dear Sir or Madam:
Generic Letter (GL) 2008-01, Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal, And Containment Spray Systems, was issued by the Nuclear Regulatory Commission (NRC) on January 11, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML072910759). In GL 2008-01, the NRC requested licensees to submit information to demonstrate that the emergency core cooling, decay heat removal, and containment spray systems are in compliance with the applicable regulatory requirements, and that suitable design, operational, and testing control measures are in place for maintaining this compliance. The GL 2008-01 states that each licensee is requested to submit a written response within 9 months to provide requested information and that if a licensee cannot meet the requested 9-month response date, a 3-month written response is required that describes the licensee's proposed alternative course of action, including the basis for the acceptability of the proposed alternative course of action. The 3-month response was due April 11, 2008.
By letter dated April 10, 2008 (ADAMS Accession No. ML081020366), Entergy Operations, Inc.
(the licensee), stated that it had a telephone conversation with Jared Wermiel, Deputy Director, Division of Safety Systems, Office of Nuclear Reactor Regulation, NRC, on April 10, 2008, in which the licensee requested an extension to the date for the above 3-month response to the GL for the Grand Gulf Nuclear Station, Unit 1 (GGNS). In the call, the licensee verbally requested an extension to May 8, 2008, to provide the 3-month response to the GL so that it can accurately assess the scope of work required to complete the 9-month response to the GL. There is no planned outage for the station prior to the due date for the 9-month response. The licensee stated that it was granted the request.
This letter is to formally acknowledge the approval of the requested extension to the due date for submitting the 3-month response to GL 2008-01 and to document the telephone call(s) with the NRC staff. Specifically, Entergy Operations, Inc. requested an extension for providing the above 3-month response from April 11, 2008, to May 8, 2008, for GGNS. The NRC staff finds that the justification for GGNS to extend the due date for the 3-month written response to GL 2008-01 to May 8, 2008, is acceptable, and the extension request is granted. This letter does not alter or change the required 9-month response date of October 11, 2008.
If you have any questions regarding this issue, please contact Jack Donohew, your assigned project manager, at 301-415-1307 or, via email, at jack.donohew@nrc.gov.
Sincerely,
/RA/
Thomas G. Hiltz, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-416 cc: See next page
ML081130449 NRR-106 OFFICE DORL/LPL4/PM DORL/LPL4/LA DSS/DD DPR/PGCB/BC DORL/LPL4/BC NAME JDonohew JBurkhardt JWermiel MMurphy THiltz DATE 4/28/08 4/28/08 4/28/08 4/29/08 4/30/08 Grand Gulf Nuclear Station (2/25/08) cc:
Senior Vice President Office of the Governor Entergy Nuclear Operations State of Mississippi P.O. Box 31995 Jackson, MS 39201 Jackson, MS 39286-1995 Attorney General Vice President, Oversight Department of Justice Entergy Nuclear Operations State of Louisiana P.O. Box 31995 P.O. Box 94005 Jackson, MS 39286-1995 Baton Rouge, LA 70804-9005 Senior Manager, Nuclear Safety President
& Licensing Claiborne County Entergy Nuclear Operations Board of Supervisors P.O. Box 31995 P.O. Box 339 Jackson, MS 39286-1995 Port Gibson, MS 39150 Senior Vice President Richard Penrod, Senior Environmental
& Chief Operating Officer Scientist/State Liaison Officer Entergy Operations, Inc. Office of Environmental Services P.O. Box 31995 Northwestern State University Jackson, MS 39286-1995 Russell Hall, Room 201 Natchitoches, LA 71497 Associate General Counsel Entergy Nuclear Operations Chief, Energy and Transportation Branch P.O. Box 31995 Environmental Compliance and Jackson, MS 39286-1995 Enforcement Division Mississippi Department of Environmental Manager, Licensing Quality Entergy Operations, Inc. P.O. Box 10385 Grand Gulf Nuclear Station Jackson, MS 39289-0385 P.O. Box 756 Port Gibson, MS 39150 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission State Health Officer 611 Ryan Plaza Drive, Suite 400 State Health Board Arlington, TX 76011-8064 P.O. Box 1700 Jackson, MS 39215 Senior Resident Inspector U.S. Nuclear Regulatory Commission Attorney General P.O. Box 399 Asst. Attorney General Port Gibson, MS 39150 State of Mississippi P.O. Box 22947 Jackson, MS 39225-2947