MONTHYEARML23353A1022023-12-19019 December 2023 Vendor Inspection of Korea Hydro & Nuclear Power Co. Safeguards Information Program Implementation ML20366A1162020-11-30030 November 2020 Korea Hydro & Nuclear Power Co., Ltd, APR1400 Response to NRC Regulatory Issue Summary 2020-02, Review of New Licensing Applications for Light-Water Reactors and Non-Light Water Reactors ML20143A0902020-05-13013 May 2020 Korea Hydro & Nuclear Power Co, Ltd., 10 CFR 50.46 Annual Report for the APR1400 Standard Plant Design ML21124A2362020-03-0404 March 2020 KHNP Request for Approval of New Reviewing Official ML19231A2092019-08-23023 August 2019 Nuclear Regulatory Commission Vendor Inspection Report of KHNP Washington, Dc. 05200046/2019201 ML19228A2142019-08-20020 August 2019 Signing Ceremony for the Advanced Power Reactor 1400 Design Certification ML19207A2742019-07-26026 July 2019 LLC Response to NRC Request for Additional Information No. 386 (Erai No. 9316) on the NuScale Design Certification Application ML19207A2572019-07-26026 July 2019 LLC Response to NRC Request for Additional Information No. 427 (Erai No. 9408) on the NuScale Design Certification Application ML19177A3522019-06-27027 June 2019 Vendor Inspection of KHNP Washington, DC Center Announcement Letter ML19116A2452019-04-26026 April 2019 Schedule to Complete Rulemaking and Certification of the Advanced Power Reactor 1400 Reactor Design ML19106A2642019-04-18018 April 2019 Response Letter to Charles J Poppe on APR1400 FSER ML19081A2042019-03-0808 March 2019 Letter from Charles Poppe to William Ward on APR1400 FSER ML18282A2182018-10-0909 October 2018 Korea Hydro & Nuclear Power Co., Ltd. - Review Result to Final Safety Evaluation Report for Chapter 18 ML18274A4032018-09-28028 September 2018 Korea Hydro & Nuclear Power Co., Ltd - Review Results to Final Safety Evaluation Report for Six Chapters ML18261A1872018-09-28028 September 2018 Letter from F. Brown to Kepco/Khnp Issuing the Standard Design Approval for the Advanced Power Reactor 1400 ML18263A2652018-09-28028 September 2018 Letter from R. Taylor to Korea Electric Power Corporation / Korea Hydro & Nuclear Power Co., Ltd, Issuing the Final Safety Evaluation Report for the Advanced Power Reactor 1400 Design ML18262A0632018-09-25025 September 2018 Advanced Power Reactor 1400 Design Certification Application - Final Safety Evaluation for Six Chapters - Letter ML18264A1272018-09-21021 September 2018 Korea Hydro & Nuclear Power Co., Ltd - Review Results to Final Safety Evaluation Report for Thirteen Chapters ML18262A0642018-09-19019 September 2018 Advanced Power Reactor 1400 Design Certification Application - Final Safety Evaluation for Thirteen Chapters ML18243A4652018-08-31031 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of LTR-RAM-17-81, Revision 4, Work Order 89: Response to Digital I&C Questions. ML18240A0422018-08-28028 August 2018 Korea Hydro & Nuclear Power Co., Ltd., Submittal of Confirmation of Final Safety Evaluation for the APR1400 Generic Report, Ptlm for RCS Heatup and Cooldown ML18199A3332018-08-23023 August 2018 APR1400, Generic Pressure-Temperature Limits Report, Final Safety Evaluation Report - Letter to KHNP ML18234A4292018-08-22022 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Updated Technical Report ML18235A1572018-08-14014 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Samdas Technical Reports ML18225A1372018-08-13013 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 520-8693 for Question 06.02.02-43 (Rev.1) ML18225A3342018-08-13013 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of APR1400 Applicant'S Environmental Report (Rev.2) ML18222A2582018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Technical Report on CCF Coping Analysis ML18222A3492018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd. - Transmittal of Response to RAI Er 1-8428 for Question EIS ACC/SA-15 (Rev.4) ML18232A1412018-08-10010 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Accepted Versions of Topical Report APR1400-F-M-TR-13001-P-A/-NP-A, PLUS7 Fuel Design for the APR1400. ML18233A4322018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Accepted Versions of Topical Report APR1400-F-A-TR-12004-P-A/-NP-A, Realistic Evaluation Methodology for Large-Break LOCA of the APR1400 ML18221A5152018-08-0909 August 2018 Korea Hydro & Nuclear Power Co., Ltd. - Submittal of Response to RAI 452-8545 for the Question 10.03.06-21 (Rev.1) ML18218A2042018-08-0606 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 312-8343 for Question 19-16 (Rev. 3) ML18218A2092018-08-0606 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 271-8290 for Question 19-15 (Rev. 5) ML18218A1962018-08-0606 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 434-8352 for Question 19-92 (Rev.5) ML18180A3272018-07-31031 July 2018 APR1400 Topical Report Safety Evaluation, Realistic Evaluation Methodology for Large Break Loss of Coolant Accident of the APR1400 - KHNP Letter ML18212A3462018-07-31031 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Technical Reports for APR1400 Design Certification ML18207A2252018-07-30030 July 2018 LTR-18-0307-1 - Letter from M. Doane to M. Corradini Report on the Safety Aspects of the APR1400 Pressurized-Water Reactor ML18225A1182018-07-27027 July 2018 Ametek Solidstate Controls - Notification of Potential Defect-10CFR Part 21 ML18206B0862018-07-26026 July 2018 Report on the Safety Aspects of the APR1400 Pressurized-Water Reactor ML18269A2412018-07-26026 July 2018 APR1400 Final Safety Evaluation Report, Appendix F - ACRS Report on APR1400 Design ML18214A5642018-07-25025 July 2018 Korea Hydro - Transmittal of Revised Technical Reports for APR1400 Design Certification ML18205A6382018-07-24024 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 356-7881 for the Question 07-18 (Rev.3) ML18205A7322018-07-24024 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1) ML18204A4082018-07-23023 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Transmittalof Revised Response to RAI 374-8481 for the Question 18-101 (Rev.1) ML18204A4332018-07-23023 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 63-7983 for Question 06.02.02-13 (Rev.2) ML18207A4572018-07-20020 July 2018 Korea Hydro - Transmittal of Revised Response to RAI 112-8015 for Question 13.05.02.01-5, Revision 3 ML18201A4002018-07-20020 July 2018 LLC Response to NRC Request for Additional Information No. 491 (Erai No. 9557) on the NuScale Design Certification Application ML18207A4512018-07-20020 July 2018 Korea Hydro - Transmittal of Revised Response to Section 19.1 Issue #PRA-135, Revision 1 ML18199A5612018-07-18018 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Revised Technical Reports for APR1400 Design Certification ML18194A4152018-07-13013 July 2018 OEDO-18-00316 - Letter from M. Doane to M. Corradini Safety Evaluation of Topical Report, APR1400-F-A-TR-12004-P, Revision 1, Realistic Evaluation Methodology for Large-Break Loss of Coolant Accident of the APR1400 2023-12-19
[Table view] |
Text
70-1312-gil, Yuseong-daero, Yuseong-gu, Daejeon, 305-343, KOREA Tel: +82-42-870-5400 / Fax: +82-42-870-5449 http://www.khnp.co.kr January 23, 2018 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. Frederick Brown Docket No.52-046 Office of New Reactors MKD/NW-18-0016L
Subject:
Resolution Plan of PRA-based SMA for APR1400 design certification Based on the January 9th, 2018 meeting between the NRC and KHNP on the APR1400 Seismic Margin Analysis (SMA) it is KHNPs understanding that NRC management has begun investigating the removal of the SMA insights from the scope of the APR1400 Design Certification Application (DCA) review in order to maintain a 42 month schedule for the review of the design certification application It is KHNPs current understanding that this action would result in the SMA insights being specifically excluded from the rule certifying the APR1400 design when it is issued. The exclusion of the SMA insights would not appear to save much time on the schedule and introduce additional uncertainties:
- There is very little difference in the time needed to revise the DCD to either remove the SMA insights from the DCD or to fully incorporate the SMA insights into the DCD o Either way the Staff would still need to review and concur with the DCD changes resulting from either change, carving out SMA insights or the proper incorporation SMA insights, were properly made o In carving out the SMA insights from the DCD review, it is believed that the NRC staff may introduce some uncertainty regarding the process and schedule going forward. This uncertainty or risk would be the result of the Staff adopting a new process, and perhaps policy, regarding Part 52 and could potentially impact the 42 month schedule.
- Either way the Staff would need to reschedule both Phase 4 and the Phase 5 ACRS meeting (from April to a future date) for Chapter 19 to accommodate the required changes to Chapter.
KHNPs current position is to retain the SMA insights in the current scope for the APR1400 DCA and maintain the original 42 month review for Phase 6. In support of KHNPs position, KHNP is applying all necessary resources to completing the SMA and has taken the actions to revise and enhance its SMA analysis to be in line with NRC Staff expectations. These actions were identified in our recent meeting with the Staff, and include:
- Applying methodology familiar to the NRC and improving the SMA model, adding seismic failure of BOP SSCs,
- Analyzing and presenting the results based on HCLPF
- Including insights of Random Failures and Operator Actions KHNPs revised SMA, including the insights, will be completed and formally submitted by February 14 (as final).
KHNP offers the following schedule for NRC planning:
- Draft results of the SMA cutsets and Plant HCLPF to be completed by Jan 26 and placed in the electronic reading room (ERR)
- Draft responses to RAI 19-10, and 19-85 with DCD markups by Feb 2 placed in ERR
- Face to face meeting to walk through the SMA results and address preliminary/initial questions on Feb 6
- Establish prompt, frequent (and effective) communication to rapidly respond to NRC comments
- Locate APR1400 teams SME for SMA in WDCC, as necessary, to facilitate an efficient NRC review of the SMA
- Issue final RAI 19-10 and 19-85 with DCD mark ups by Feb 14 KHNP would be prepared to meet with the ACRS subcommittee for Chapter 19 on June 5 and full committee around July 11 (depending on ACRS schedule).
Please note that KHNP has already begun the necessary actions to complete and submit this work on the time line provided above.
It is recognized that the interim Phase 4 and 5 milestones will need to be readjusted. KHNP respectfully requests that the NRC staff and ACRS continue the necessary support to allow the SMA to be included in the APR1400 DCA and to be reviewed within the original 42 month schedule.
Please be assured KHNP recognizes the importance of on time delivery and a complete and high quality response to support this schedule.
KHNP looks forward to your response.
Sincerely, Han-gon Kim Project Manager Advanced Reactors Development Laboratory Korea Hydro & Nuclear Power Co., Ltd.
Cc: Frank Akstulewicz Mike McCoppin Bill Ward YunHo Kim Daegeun Ahn