Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 434-8352 for Question 19-92 (Rev.5)
ML18218A196
Person / Time
Site: 05200046
Issue date: 08/06/2018
From: Yeon Kim
Korea Hydro & Nuclear Power Co, Ltd
To: William Ward
Document Control Desk, Office of New Reactors
Shared Package
ML18218A194 List:
References
MKD/NW-18-0105L
Download: ML18218A196 (2)


Text

70-1312-gil, Yuseong-daero, Yuseong-gu, Daejeon, 34101, KOREA Tel: +82-42-870-5740 / Fax: +82-42-870-5779 http://www.khnp.co.kr August 6, 2018 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. William Ward Docket No.52-046 Division of New Reactor Licensing MKD/NW-18-0105L

Subject:

Revised Response to RAI 434-8352 for Question 19-92 (Rev.5)

References:

1) NRC Request for Additional Information 434-8352, dated March 8, 2016
2) KHNP Letter MKD/NW-16-0862L, Response to RAI 434-8352 for Question 19-92, dated August 9, 2016
3) KHNP Letter MKD/NW-17-0317L, Revised Response to RAI 434-8352 for Question 19-92, dated September 29, 2017
4) KHNP Letter MKD/NW-17-0379L, Revised Response to RAI 434-8352 for Question 19-92 (Rev.2), dated December 28, 2017
5) KHNP Letter MKD/NW-18-0014L, Revised Response to RAI 434-8352 for Question 19-92 (Rev.3), dated January 22, 2018
6) KHNP Letter MKD/NW-18-0049L, Revised Response to RAI 434-8352 for Question 19-92 (Rev.4), dated April 10, 2018 KHNP is hereby submitting the revised response to RAI 434-8352, dated March 8, 2016. The revised response addresses Question 19-92 to reflect changes due to the updated APR1400 PRA-based SMA, certain revised COL items and RAI responses, as well as some editorial corrections.

The enclosure provides the revised response to RAI 434-8352 for Question 19-92 (Rev.5) (Non-Proprietary).

If additional information or clarification is required, please contact Daegeun Ahn, Director of KHNP Washington DC Center at ahn.daegeun@khnp.co.kr or 703-388-0592.

Sincerely, Yun-ho Kim Project Manager Advanced Reactors Development Laboratory Korea Hydro & Nuclear Power Co., Ltd.

Enclosure:

Revised Response to RAI 434-8352 for Question 19-92 (Rev.5) (Non-Proprietary)

Enclosure Revised Response to RAI 434-8352 for Question 19-92 (Rev.5)

(Non-Proprietary)

August 6, 2018