Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1)
ML18205A732
Person / Time
Site: 05200046
Issue date: 07/24/2018
From: Yeon Kim
Korea Hydro & Nuclear Power Co, Ltd
To: William Ward
Document Control Desk, Office of New Reactors
Shared Package
ML18205A729 List:
References
MKD/NW-18-0114L
Download: ML18205A732 (2)


Text

70-1312-gil, Yuseong-daero, Yuseong-gu, Daejeon, 34101, KOREA Tel: +82-42-870-5740 / Fax: +82-42-870-5779 http://www.khnp.co.kr July 24, 2018 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. William Ward Docket No.52-046 Division of New Reactor Licensing MKD/NW-18-0114L

Subject:

Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1)

References:

1) NRC Request for Additional Information 558-9456, dated March 15, 2018
2) KHNP Letter MKD/NW-18-0070L, Response to RAI 558-9456 for Question 14.03.01-1, dated May 17, 2018 KHNP is hereby submitting the response to RAI 558-9456, dated March 15, 2018. The revised response addresses Question 14.03.01-1 relating to ITAAC for the turbine and turbine valve in service test and inspection program. The enclosure provides the revised response to RAI 558-9456 for Question 14.03.01-1 (Rev.1) (Non-Proprietary).

If additional information or clarification is required, please contact Daegeun Ahn, Director of KHNP Washington DC Center at ahn.daegeun@khnp.co.kr or 703-388-0592.

Sincerely, Yun-ho Kim Project Manager Advanced Reactors Development Laboratory Korea Hydro & Nuclear Power Co., Ltd.

Enclosure:

Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1) (Non-Proprietary)

Enclosure Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1)