Category:License-Operator
MONTHYEARML22332A0562022-11-21021 November 2022 301 License Exam Corporate Notification Letter L-2022-065, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment2022-04-20020 April 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment L-2021-146, Change Requested to Schedule of Operator Licensing Examination2021-07-19019 July 2021 Change Requested to Schedule of Operator Licensing Examination ML21137A3652021-05-13013 May 2021 Plan, Unit 1 and 2, Operator Licensing Retake Written Examination Approval 05000335/2021301 and 05000389/2021301 ML21083A1332021-03-19019 March 2021 Notification of Licensed Operator Intake Initial Examination 05000335/2021301 and 05000389/2021301 ML21034A5192021-02-0303 February 2021 1A -PSL L-20-1 RO and SRO Student Exam Final as Given with Key ML21034A5312021-02-0303 February 2021 1B Psl 2020-301 NRC Exam Post Exam Comments and References_Redacted (PII Redacted) ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML21193A0872020-12-16016 December 2020 File 2A3 Exam Administrative Items ML21193A1052020-12-16016 December 2020 File 2A2 Exam Final Items ML21193A0522020-12-16016 December 2020 File 2B Normal Release Exam Administrative Items ML20351A2022020-12-15015 December 2020 301 Written Exam Approval Letter ML20339A6782020-12-0404 December 2020 Operator Licensing Operating Test Approval 05000335/2020301 and 05000389/2020301 ML20115E3532020-04-24024 April 2020 Psl 2020 Exam Corporate Notification Letter Aka 210-day Letter NUREG Rev 111 L-2020-038, Preparation and Scheduling of Operator Licensing Examinations2020-03-0606 March 2020 Preparation and Scheduling of Operator Licensing Examinations ML20007F7572020-01-0707 January 2020 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2020 ML19158A3312019-06-0707 June 2019 SL-2019-301 Exam Administrative Items (ADAMS 2D) ML19100A2442019-04-10010 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for St. Lucie Nuclear Power Plant ML19099A2902019-04-0909 April 2019 2019 Schedule Confirmation for St. Lucie ML19045A3712019-02-12012 February 2019 March 2019 GFE Cover Letter Rii ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 ML18086B0442018-02-16016 February 2018 Facility Cover Letter - Rii - March 2018 - GFE ML18039A9282018-02-0808 February 2018 301 Exam Report Items RO as Given - Delay Release 2 Yrs ML18039A9332018-02-0808 February 2018 301 Exam Report Items SRO as Given - Delay Release 2 Yrs ML17164A0852017-06-0909 June 2017 Notification of Licensed Operator Initial Examination 05000335/2017301 and 05000389/2017301 IR 05000335/20173012017-06-0909 June 2017 Notification of Licensed Operator Initial Examination 05000335/2017301 and 05000389/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 L-2016-033, NRC Regulatory Issue Summary 2015-05 Preparation and Scheduling of Operator Licensing Examinations - Update2016-02-22022 February 2016 NRC Regulatory Issue Summary 2015-05 Preparation and Scheduling of Operator Licensing Examinations - Update ML15201A5382015-07-16016 July 2015 301 Draft Simulator Scenarios ML15201A5642015-07-16016 July 2015 301 Other Documents for Retention ML15201A5612015-07-16016 July 2015 301 Final Administrative JPMs ML15201A5602015-07-16016 July 2015 301 Final Simulator and in Plant JPMs ML15201A5582015-07-16016 July 2015 301 Final Simulator Scenarios ML15201A5572015-07-16016 July 2015 301 Final Administrative Documents ML15201A5532015-07-16016 July 2015 301 Draft Administrative JPMs ML15201A5452015-07-16016 July 2015 301 Draft Simulator and in Plant JPMs ML15201A5372015-07-16016 July 2015 301 Draft SRO Written Exam ML15201A4962015-07-13013 July 2015 301 Draft RO Written Exam ML15201A4942015-07-13013 July 2015 301 Draft Administrative Documents ML15142A4002015-05-21021 May 2015 Initial Exam 2009302 Final Admin Documents ML15142A4012015-05-21021 May 2015 Initial Exam 2009302 Draft Admin Documents ML15097A2692015-04-0707 April 2015 301 Post Exam Comments ML15097A2672015-04-0707 April 2015 301 Final SRO Written Exam ML15097A2642015-04-0707 April 2015 301 Final RO Written Exam ML14318A9192014-11-12012 November 2014 Notification of Licensed Operator Initial Examination 05000335/2015301 and 05000389/2015301 ML13225A1322013-08-0808 August 2013 Initial Exam 2012-301 Draft SRO Written Exam ML13225A1352013-08-0808 August 2013 Initial Exam 2012-301 Draft Simulator Scenarios ML13225A1382013-08-0808 August 2013 Initial Exam 2012-301 Draft Sim/In-plant JPMs ML13225A1402013-08-0808 August 2013 Initial Exam 2012-301 Draft Administrative JPMs ML13225A1662013-08-0808 August 2013 Initial Exam 2012-301 Final Administrative Documents 2022-04-20
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML22332A0562022-11-21021 November 2022 301 License Exam Corporate Notification Letter L-2022-065, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment2022-04-20020 April 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations; Request for Comment L-2021-146, Change Requested to Schedule of Operator Licensing Examination2021-07-19019 July 2021 Change Requested to Schedule of Operator Licensing Examination ML21137A3652021-05-13013 May 2021 Plan, Unit 1 and 2, Operator Licensing Retake Written Examination Approval 05000335/2021301 and 05000389/2021301 ML21083A1332021-03-19019 March 2021 Notification of Licensed Operator Intake Initial Examination 05000335/2021301 and 05000389/2021301 ML21034A5312021-02-0303 February 2021 1B Psl 2020-301 NRC Exam Post Exam Comments and References_Redacted (PII Redacted) ML21034A5192021-02-0303 February 2021 1A -PSL L-20-1 RO and SRO Student Exam Final as Given with Key ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML21193A0522020-12-16016 December 2020 File 2B Normal Release Exam Administrative Items ML21193A1052020-12-16016 December 2020 File 2A2 Exam Final Items ML21193A0872020-12-16016 December 2020 File 2A3 Exam Administrative Items ML20351A2022020-12-15015 December 2020 301 Written Exam Approval Letter ML20339A6782020-12-0404 December 2020 Operator Licensing Operating Test Approval 05000335/2020301 and 05000389/2020301 ML20115E3532020-04-24024 April 2020 Psl 2020 Exam Corporate Notification Letter Aka 210-day Letter NUREG Rev 111 L-2020-038, Preparation and Scheduling of Operator Licensing Examinations2020-03-0606 March 2020 Preparation and Scheduling of Operator Licensing Examinations ML19158A3312019-06-0707 June 2019 SL-2019-301 Exam Administrative Items (ADAMS 2D) ML19100A2442019-04-10010 April 2019 March 6, 2019, NRC Generic Fundamentals Examination Results for St. Lucie Nuclear Power Plant ML19099A2902019-04-0909 April 2019 2019 Schedule Confirmation for St. Lucie ML18039A9282018-02-0808 February 2018 301 Exam Report Items RO as Given - Delay Release 2 Yrs ML18039A9332018-02-0808 February 2018 301 Exam Report Items SRO as Given - Delay Release 2 Yrs ML17164A0852017-06-0909 June 2017 Notification of Licensed Operator Initial Examination 05000335/2017301 and 05000389/2017301 IR 05000335/20173012017-06-0909 June 2017 Notification of Licensed Operator Initial Examination 05000335/2017301 and 05000389/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 L-2016-033, NRC Regulatory Issue Summary 2015-05 Preparation and Scheduling of Operator Licensing Examinations - Update2016-02-22022 February 2016 NRC Regulatory Issue Summary 2015-05 Preparation and Scheduling of Operator Licensing Examinations - Update ML15201A5372015-07-16016 July 2015 301 Draft SRO Written Exam ML15201A5642015-07-16016 July 2015 301 Other Documents for Retention ML15201A5612015-07-16016 July 2015 301 Final Administrative JPMs ML15201A5602015-07-16016 July 2015 301 Final Simulator and in Plant JPMs ML15201A5582015-07-16016 July 2015 301 Final Simulator Scenarios ML15201A5572015-07-16016 July 2015 301 Final Administrative Documents ML15201A5532015-07-16016 July 2015 301 Draft Administrative JPMs ML15201A5452015-07-16016 July 2015 301 Draft Simulator and in Plant JPMs ML15201A5382015-07-16016 July 2015 301 Draft Simulator Scenarios ML15201A4962015-07-13013 July 2015 301 Draft RO Written Exam ML15201A4942015-07-13013 July 2015 301 Draft Administrative Documents ML15142A4002015-05-21021 May 2015 Initial Exam 2009302 Final Admin Documents ML15142A4012015-05-21021 May 2015 Initial Exam 2009302 Draft Admin Documents ML15097A2642015-04-0707 April 2015 301 Final RO Written Exam ML15097A2672015-04-0707 April 2015 301 Final SRO Written Exam ML15097A2692015-04-0707 April 2015 301 Post Exam Comments ML14318A9192014-11-12012 November 2014 Notification of Licensed Operator Initial Examination 05000335/2015301 and 05000389/2015301 ML13225A1382013-08-0808 August 2013 Initial Exam 2012-301 Draft Sim/In-plant JPMs ML13225A1282013-08-0808 August 2013 Initial Exam 2012-301 Draft Administrative Documents ML13225A1352013-08-0808 August 2013 Initial Exam 2012-301 Draft Simulator Scenarios ML13225A1322013-08-0808 August 2013 Initial Exam 2012-301 Draft SRO Written Exam ML13225A1302013-08-0808 August 2013 Initial Exam 2012-301 Draft RO Written Exam ML13225A1402013-08-0808 August 2013 Initial Exam 2012-301 Draft Administrative JPMs ML13225A1722013-08-0808 August 2013 Initial Exam 2012-301 Final Administrative JPMs ML13225A1712013-08-0808 August 2013 Initial Exam 2012-301 Final Sim/In-plant JPMs ML13225A1692013-08-0808 August 2013 Initial Exam 2012-301 Final Simulator Scenarios 2022-04-20
[Table view] |
Text
ES-301 Administrative Topics Outline Form ES-301-1 Facility: St. Lucie Date of Examination: 11/17/11 Examination Level (circle one): RO/SRO Operating Test Number: NRC HLC-20A Administrative Topic Type Describe activity to be performed (see Note) Code*
M, R A1 Conduct of Operations Determine time to boil upon loss of Shutdown Cooling, Unit 1.
N, S A2 Conduct of Operations Perform manual RCS inventory balance.
N, S or R A3 Equipment Control Develop ECO for 2B Component Cooling water pump.
M, S or R A4 Radiation Control Determine radiation exposure limits under non emergency conditions.
Emergency Plan NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.
- Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)
(N)ew or (M)odified from bank (> 1)
(P)revious 2 exams ( 1; randomly selected)
NUREG-1021, Revision 9
ES-301 Administrative Topics Outline Form ES-301-1 ADMINISTRATIVE JPM
SUMMARY
A1: Determine time to boil upon loss of Shutdown Cooling. Given plant conditions of reduced inventory and time after shutdown, determine time to boil the RCS and the required RCS makeup.
A2: Perform manual RCS inventory balance. Applicant will perform a manual RCS inventory balance on the simulator. The simulator will be turned over at 100% power steady state.
After the Applicant takes the initial data, the simulator will initialize to a new 100% power steady state set of conditions, simulated to 120 minutes after the initial set of data. The Applicant will use this new set of data to complete the final RCS leak rate.
A3: Develop ECO for 2B Component Cooling water pump. Directions to generate an equipment clearance to remove the 2B Component cooling water pump for pump overhaul.
A4: Determine radiation exposure limits under non emergency conditions. Four individuals, two contract personnel and two FPL personnel are assigned to repair the spreader on the refueling machine. Given previous radiation exposure, determine the individuals that can perform the repair without Site VP approval.
NUREG-1021, Revision 9
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: St. Lucie Date of Examination: 11/17/11 Exam Level (circle one): RO, SRO(I), SRO(U) Operating Test No.: NRC HLC-20A Control Room Systems@ (8 for RO; 7 for SRO-I; 2 or 3 for SRO-U, including 1 ESF)
System / JPM Title Type Code* Safety Function S-1 Respond to loss of RCP Controlled Bleedoff and failed RCP D, E, A, S 4p Seals.
S-2 Restore offsite power with both Diesel Generators in D, E, S, L 6 operation.
S-3 Respond to alarms on SFP monitors D, A, S 7 S-4 Transfer Letdown Level control to the alternate Level Control P, S 2 valve S-5 Start 2C AFW to feed the 2A and 2B SG M, E, L, S, A 4s S-6 Initiate Once Through Cooling M, E, S, A 3 S-7 Emergency Borate using V2504, Refuel to Charging pumps M, E, S, A 1 C-1 Pump ECCS area sumps to RDT post LOCA - Unit 1 D, E, C 5 In-Plant Systems@ (3 for RO; 3 for SRO-I; 3 or 2 for SRO-U)
P-1 Align U-2 CST to supply 1C AFW pump D, E 4s P-2 Initiate Containment hydrogen purge D, E, R 5 P-3 Perform actions outside Control Room for dropped / D, E, A 1 misaligned CEA - Unit 1
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2
@ All control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank 9/8/4 (E)mergency or abnormal in-plant 1/1/1 (EN)gineered safety feature - / - / > 1 (control room system)
(L)ow-Power / Shutdown 1/1/1 (N)ew or (M)odified from bank including 1(A) 2/2/1 (P)revious 2 exams 3 / 3 / 2 (randomly selected)
(R)CA 1/1/1 (S)imulator JPM
SUMMARY
DESCRIPTION S-1 Respond to loss of RCP Controlled Bleedoff and failed RCP Seals.
The Applicant will be directed to respond to loss of RCP controlled bleedoff at 100% power. Applicant will be required to recognize V2505, RCP bleedoff valve is closed and will not open. As a result V2507, bleedoff to Quench Tank will be aligned. Upon opening V2507, three seals on the 2B1 RCP will fail requiring a manual Reactor trip and stopping the 2B1RCP.
S-2 Restore offsite power with both Diesel Generators in operation.
A LOOP has occurred and both Diesel Generators are loaded on their respective busses. Offsite power is now available and direction will be given to restore offsite power to the A side first. The Applicant will be expected to bring offsite power back and stop the 2A Diesel generator.
S-3 Respond to alarms on SFP monitors.
During refueling operations a fuel handling accident occurs. The spent fuel radiation monitors went to high alarm and the ventilation system aligned and started on the Spent Fuel pool. The applicant is directed to use the AOP and verify proper alignment. Various equipment failures are to be noted and corrected by the Applicant.
S-4 Transfer Letdown Level control to the alternate Level Control valve.
The in-service letdown level control valve is operating erratically. Direction will be given to place the alternate level control valve in service.
S-5 Start 2C AFW and feed the 2A and 2B SG Direction will be given to start the 2C AFW pump and feed the 2A and 2B Steam Generator. When the pump is started, it will trip on mechanical overspeed. The applicant will be required to communicate and work with the field operator to reset the overspeed trip and align the pump to feed the 2A and 2B Steam Generators.
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 S-6 Initiate Once Through Cooling.
A total loss of feedwater has occurred. Direction will be given to initiate Once Through Cooling. Upon attempt to open the block valve on the normally isolated PORV the breaker will trip just as the valve starts to open. Procedure guidance will continue with the lineup using the other PORV by pulling two RPS High Pressure Bistables. When Bistable pulled the PORV with the block valve open will not open. Procedure guidance states continue efforts to open at least one PORV and associated block valve. The Applicant will contact the field operator to reset the breaker on the tripped PORV block valve. Once the breaker is reset the block valve can be opened and Once Through Cooling can be initiated. Although not directly procedurally driven to reset the breaker, OP-1250020, Valve, Breaker, Motor and Instrument Instructions states If breaker trips on a piece of equipment AND is needed to protect the health and safety of the public, Then the breaker may be reset and / or one reclosure attempted. (step 8.3.4)
S-7 Emergency Borate using V2504, Refuel to Charging pumps.
Direction will be given to respond to a reactor trip. The applicant must recognize that two CEAs are not inserted and should emergency borate. When aligning for emergency boration, the emergency borate valve and the gravity feeds will not open. Procedural guidance will be to use V2504, RWT valve to the suction of the Charging Pumps, C-1 Pump ECCS area sumps to RDT post LOCA - Unit 1.
Unit 1 has experienced a LOCA. RAS has occurred and direction is given to align the ECCS area sumps to the RDT IAW 1-EOP-03, LOCA.
P-1 Align U-2 CST to supply 1C AFW pump.
Unit 1 CST is not available due to tornado damage. Direction will be given to align the Unit 2 CST to the suction of the Unit 1, 1C Auxiliary feedwater pump.
P-2 Initiate Containment hydrogen purge.
Uni1 has experienced a large break LOCA. The TSC has requested to align the Hydrogen Purge system in accordance with 1-EOP-99, Appendix N.
P-3 Perform actions outside Control Room for dropped / misaligned CEA - Unit 1.
A CEA has dropped on Unit 1. Attachment 6, CEA Functional test and Operability Determination is being performed. The Applicant will be directed to perform section 3 of Attachment 6. This is performed in the electrical switchgear room. Various malfunctions should be noted and corrected by the Applicant.
.