Letter Sequence Other |
---|
TAC:MC5449, Removal of Monthly Operating Report and Occupational Radiation Exposure Report, Changes to Section 5.0, Administrative Controls (Open) |
|
|
|
---|
Category:Letter
MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle IR 05000313/20243012023-08-14014 August 2023 Notification of NRC Initial Operator Licensing Examination 05000313/2024301 IR 05000313/20230022023-08-11011 August 2023 Integrated Inspection Report 05000313/2023002 and 05000368/2023002 and Notice of Violation ML23209A6022023-08-0909 August 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk- Informed Completion Times IR 05000416/20230022023-08-0808 August 2023 Integrated Inspection Report 05000416/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200050/2023001 ML23208A2132023-08-0303 August 2023 Regulatory Audit Summary Concerning Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23208A2112023-07-27027 July 2023 Entergy Operations Inc., Application to Revise Technical Specifications to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23188A1732023-07-12012 July 2023 Request for Withholding Information from Public Disclosure ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements IR 05000313/20234032023-06-28028 June 2023 Security Baseline Inspection Report 05000313/2023403 and 05000368/2023403 ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23180A1082023-06-20020 June 2023 ANO Unit 1 SAR Amendment 31, TRM, TS Bases, 10 CFR 50.59 Report, and Commitment Change Summary Report IR 05000313/20234012023-06-13013 June 2023 Cyber Security Inspection Report 05000313/2023401 and 05000368/2023401 ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23121A3012023-05-10010 May 2023 Regulatory Audit Plan in Support of License Amendment Request to Revise Technical Specifications to Adopt Risk - Informed Completion Times ML23114A3572023-05-10010 May 2023 Regulatory Audit Summary Concerning Review of Request for Alternative ANO-CISI-002 Regarding Containment Inservice Inspection Frequency ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000313/20230012023-05-0909 May 2023 Integrated Inspection Report 05000313/2023001 and 05000368/2023001 ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) IR 05000368/20233012023-05-0101 May 2023 NRC Examination Report 05000368/2023301 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23108A1362023-04-24024 April 2023 Approval of Request for Half-Nozzle Repair of Reactor Vessel Closure Head Penetration No. 46 ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G 2024-01-24
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23020A9362023-01-27027 January 2023 Audit Plan to Support Review of License Amendment Request to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML22263A1912022-12-0909 December 2022 Issuance of Amendment No. 278 Revision to Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations (EPID L-2021-LLA-0181) - Non-Proprietary ML22291A2392022-10-28028 October 2022 Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed Nshcd, and Opportunity for a Hearing and Order Imposing Procedures for Document Access to SUNSI (EPID L-2021-LLA-0181) Letter ML22165A2442022-07-19019 July 2022 Issuance of Amendment No. 331 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML22138A4312022-06-23023 June 2022 Issuance of Amendment No. 277 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML22104A2222022-05-12012 May 2022 Issuance of Amendments Revise Technical Specifications to Adopt TSTF 554 ML22083A1242022-04-28028 April 2022 Arkansas, Units 1 and 2; Grand Gulf Nuclear Station; River Bend Station; and Waterford Steam Electric Station - Issuance of Amendments Revise Technical Specifications to Adopt TSTF-541, Revision 2 ML22039A2822022-03-15015 March 2022 Issuance of Amendment Nos. 274 and 328 One-Time Change to Support Proactive Upgrade of the Emergency Cooling Pond Supply Piping ML21225A0552021-12-17017 December 2021 Issuance of Amendment No. 327 Addition of Technical Specification Limiting Condition for Operation 3.0.6 and Adoption of Safety Function Determination Program ML21341B2262021-12-13013 December 2021 Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations ML21313A0082021-12-0808 December 2021 Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21320A2122021-11-17017 November 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request Concerning Revised Dose Calculations ML21281A2542021-10-15015 October 2021 Audit Meeting Agenda & Audit Questions for LAR to Adopt 10 CFR 50.69,Risk-Informed Categorization and Treatment of Structures, System, and Components for Nuclear Power Reactors (EPIDs L-2021-LLA-0105, L-2021-LLA-0106 ML21208A4492021-09-20020 September 2021 Issuance of Amendment No. 325 Revise Loss of Voltage Relay Allowable Values and Number of Degraded Voltage Channels ML21088A4332021-04-14014 April 2021 Issuance of Amendment No. 324 Adoption of Technical Specification Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition ML21027A4282021-03-23023 March 2021 Issuance of Amendment No. 272 Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent ML21040A5132021-03-10010 March 2021 Issuance of Amendment No. 271 Revision to Loss of Voltage Relay Allowable Values ML20351A1532021-02-0808 February 2021 Issuance of Amendment No. 323 Technical Specification Deletions, Additions, and Relocations NUREG-1432, Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-14322020-10-30030 October 2020 Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-1432 ML20135H1412020-06-30030 June 2020 Issuance of Amendment Nos. 269 and 321 Request to Incorporate the Tornado Missile Risk Evaluator Into the Licensing Basis ML20160A1472020-06-30030 June 2020 Issuance of Amendment No. 270 to Adopt TSTF 563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20087L8032020-04-0808 April 2020 Issuance of Amendment No. 320 to Revise Control Element Assembly Drop Times ML19231A2972020-01-29029 January 2020 Issuance of Amendment No. 318 Addition of Technical Specification Actions to Address Inoperability of the Containment Building Sump ML19269B6722019-10-22022 October 2019 Issuance of Amendment Nos. 267 and 317 to Extend Implementation Dates for Amendment Nos. 263 and 314, Revision to Emergency Action Level Scheme ML19220A9382019-09-27027 September 2019 Issuance of Amendment No. 266 Adoption of Technical Specifications Task Force Traveler TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML19098A9552019-05-22022 May 2019 Issuance of Amendment No. 264 Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-425, Revision 3 ML19127A2992019-05-15015 May 2019 Correction to Amendment No. 315 Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-425, Revision 3 ML19063B9482019-04-23023 April 2019 Issuance of Amendment No. 315 Adoption of Technical Specification Task Force Traveler TSTF-425, Revision 3 ML18337A2472019-01-17017 January 2019 Issuance of Amendment Nos. 263 and 314 Revision to Emergency Action Level Scheme ML18317A3822018-12-19019 December 2018 Issuance of Amendment No. 313, Revise Technical Specification 3.3.3.6, Post-Accident Instrumentation ML18306A5132018-11-30030 November 2018 Issuance of Conforming Amendment Nos. 262, 312 and 215 Transfers of Renewed Facility Operating Licenses ML18298A0122018-11-27027 November 2018 Issuance of Amendment No. 311 Updating the Reactor Coolant System Pressure Temperature Limits ML18260A3392018-10-24024 October 2018 Issuance of Amendment No. 261 Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves ML18115A2822018-06-19019 June 2018 Issuance of Amendment No. 260 Technical Specification Changes Pursuant to Technical Specifications Task Force (TSTF) Traveler TSTF-412 Revision 3 (CAC No. MG0009; EPID L-2017-LLA-0267) ML18134A2532018-06-19019 June 2018 Issuance of Amendment No. 310 Technical Specification Changes to Provide Actions for Emergency Feedwater Pump Inoperability Consistent with NUREG-1432, Revision 4 (CAC No. MG0016; EPID L-2017-LLA-0268) ML18051A5892018-02-26026 February 2018 Issuance of Amendment No. 309 to Adopt TSTF-427, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability (CAC No. MG0131; EPID L-2017-LLA-0302) ML18033A1752018-02-26026 February 2018 Issuance of Amendment No. 259 to Adopt TSTF-427, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability (CAC No. MG0132; EPID L-2017-LLA-0301) ML18011A0642018-01-18018 January 2018 Issuance of Amendment No. 308 to Exclude Exercise of Control Element Assembly 4 with Respect to Surveillance Requirement 4.1.3.1.2 for the Remainder of Cycle 26 (Exigent Circumstances) ML17251A2112017-10-10010 October 2017 Issuance of Amendment No. 307 Revision of Steam Generator Technical Specifications to Reflect Adoption of Technical Specifications Task Force Traveler TSTF-510 (CAC MF9654; EPID L-2017-LLA-0222) ML17235A5192017-10-10010 October 2017 Issuance of Amendment No. 258 Revision of Steam Generator Technical Specifications to Reflect Adoption of TSTF-510 (CAC MF9653; EPID L-2017-LLA-0221) ML17096A2352017-05-12012 May 2017 Issuance of Amendment No. 306 Request to Revise the National Fire Protection Association (NFPA) Standard 805 Modifications ML16215A3712017-03-29029 March 2017 Issuance of Amendment No. 305 to Adopt Technical Specifications Task Force Traveler TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing... ML16165A4232017-03-10010 March 2017 Issuance of Amendment No. 257 Adoption of Technical Specifications Task Force Traveler TSTF-545, Revision 3, ML16267A1392016-12-29029 December 2016 Issuance of Amendment Revise Technical Specfications to Adopt TSTF-426, to Revise or Add Actions to Preclude Entry Into Lco 3.0.3 Ritstf Initiative 6b & 6c ML16223A4812016-10-0707 October 2016 Issuance of Amendment No. 256 Regarding Transition to a Risk-Informed, Performance-Based Fire Protection Program in Accordance with 10 CFR 50.48(c) (Cac No. MF3419) ML16027A1092016-02-24024 February 2016 Issuance of Amendment Nos. 255 and 303 Cyber Security Plan Implementation Schedule (CAC Nos. MF6258 and MF6259) ML15096A3812015-04-29029 April 2015 Issuance of Amendment No. 302, Revise Technical Specification Surveillance Requirement 4.1.3.1.2 Note to Eliminate Movement of Control Element Assembly 18 for Remainder of Operating Cycle 24 2024-01-24
[Table view] Category:Safety Evaluation
MONTHYEARML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation ML23142A2022023-06-29029 June 2023 Issuance of Amendment Nos. 279 and 332 Emergency Plan Staffing Requirements ML23166B0902023-06-21021 June 2023 Request for Relief ANO1 ISI 036 Regarding Volumetric Examination Requirements ML23142A1062023-05-24024 May 2023 Authorization and Safety Evaluation for Alternative Request No. ANO1-ISI-035 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML22342B1602023-01-10010 January 2023 Requests for Relief ANO2-ISI-023, -024, -025, -026, -027, and -028 to Permit Reduction of Inspection Area Due to Interference (EPIDs L-2022-LLR-0022,-0023, -0024, -0025, -0026, and -0027) ML22263A1912022-12-0909 December 2022 Issuance of Amendment No. 278 Revision to Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations (EPID L-2021-LLA-0181) - Non-Proprietary ML22236A5452022-08-26026 August 2022 Correction to Issuance of Amendment No. 331 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML22138A4312022-06-23023 June 2022 Issuance of Amendment No. 277 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML22104A2222022-05-12012 May 2022 Issuance of Amendments Revise Technical Specifications to Adopt TSTF 554 ML22083A1242022-04-28028 April 2022 Arkansas, Units 1 and 2; Grand Gulf Nuclear Station; River Bend Station; and Waterford Steam Electric Station - Issuance of Amendments Revise Technical Specifications to Adopt TSTF-541, Revision 2 ML22039A2822022-03-15015 March 2022 Issuance of Amendment Nos. 274 and 328 One-Time Change to Support Proactive Upgrade of the Emergency Cooling Pond Supply Piping ML22007A3172022-01-18018 January 2022 1, River Bend Station 1, and Waterford Steam Electric Station 3 - Request to Use a Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI ML21225A0552021-12-17017 December 2021 Issuance of Amendment No. 327 Addition of Technical Specification Limiting Condition for Operation 3.0.6 and Adoption of Safety Function Determination Program ML21341B2262021-12-13013 December 2021 Acceptance of Requested Licensing Action License Amendment Request to Revise Technical Specifications 3.4.12 and 3.4.13 Based on Revised Dose Calculations ML21313A0082021-12-0808 December 2021 Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21208A4492021-09-20020 September 2021 Issuance of Amendment No. 325 Revise Loss of Voltage Relay Allowable Values and Number of Degraded Voltage Channels ML21132A2792021-05-19019 May 2021 Request for Approval of Change to the Entergy Quality Assurance Program Manual ML21088A4332021-04-14014 April 2021 Issuance of Amendment No. 324 Adoption of Technical Specification Task Force Traveler, TSTF-569, Revision 2, Revise Response Time Testing Definition ML21027A4282021-03-23023 March 2021 Issuance of Amendment No. 272 Replacement of Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent ML21040A5132021-03-10010 March 2021 Issuance of Amendment No. 271 Revision to Loss of Voltage Relay Allowable Values ML20351A1532021-02-0808 February 2021 Issuance of Amendment No. 323 Technical Specification Deletions, Additions, and Relocations ML20288A8242020-11-16016 November 2020 Regulatory Audit Summary Concerning License Amendment Request to Replace the Reactor Building Spray Sodium Hydroxide Additive with a Passive Reactor Building Sump Buffering Agent NUREG-1432, Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-14322020-10-30030 October 2020 Issuance of Amendment No. 322 Technical Specification Changes Related to Revised Fuel Handling Accident Analysis and Adoption of Technical Specification Improvements Consistent with NUREG-1432 ML20226A2722020-08-18018 August 2020 Request to Use a Provision of a Later Edition of the ASME BPV Code, Section XI ML20160A1472020-06-30030 June 2020 Issuance of Amendment No. 270 to Adopt TSTF 563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20135H1412020-06-30030 June 2020 Issuance of Amendment Nos. 269 and 321 Request to Incorporate the Tornado Missile Risk Evaluator Into the Licensing Basis ML20121A1932020-05-0606 May 2020 Alternative Requests for the Fifth 10 Year Interval Inservice Testing of Low Pressure Safety Injection Pumps and Service Water Valves ML20107J3172020-04-23023 April 2020 Relief Request ANO1-ISI-033 Related to ASME Code Case N-729-4 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles ML20087L8032020-04-0808 April 2020 Issuance of Amendment No. 320 to Revise Control Element Assembly Drop Times ML20083J9682020-03-26026 March 2020 Approval of Request for Alternative ANO 2-PT-002 End-of-Internal System Leakage Test for Extended Reactor Coolant Pressure Boundary Piping ML19231A2972020-01-29029 January 2020 Issuance of Amendment No. 318 Addition of Technical Specification Actions to Address Inoperability of the Containment Building Sump ML19220A9382019-09-27027 September 2019 Issuance of Amendment No. 266 Adoption of Technical Specifications Task Force Traveler TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML19254A6032019-09-19019 September 2019 Units 2 and 3; Palisades Nuclear Plant; River Bend; and Waterford Steam Electric Station, Unit 3 - Relief Request No. EN-19-RR-1, Use of ASME Code Case N-831-1 ML19175A0422019-09-11011 September 2019 Arkansas Units 1 and 2; Grand Gulf, Unit 1; Indian Point 2 and 3; Palisades; River Bend, Unit 1; Waterford Unit 3 - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules ML19184A5542019-07-15015 July 2019 Request for Relief ANO1-ISI-032 from the ASME Code Section XI Visual Examination Requirements for the Fourth 10-Year Inservice Inspection Interval ML19156A4002019-06-11011 June 2019 Request for Alternative ANO2-ISI-021 to Permit Continued Application of the 2007 Edition Through the 2008 Addenda of ASME Code ML19098A9552019-05-22022 May 2019 Issuance of Amendment No. 264 Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-425, Revision 3 ML19063B9482019-04-23023 April 2019 Issuance of Amendment No. 315 Adoption of Technical Specification Task Force Traveler TSTF-425, Revision 3 ML18337A2472019-01-17017 January 2019 Issuance of Amendment Nos. 263 and 314 Revision to Emergency Action Level Scheme ML18346A3142019-01-0707 January 2019 Relief Nos. ANO1-ISI-027, -028, -029, -030, and -031 from ASME Code, Section XI, Examination Requirements for Fourth 10-Year Inservice Inspection Interval (EPID L-2018-LLR-0063, -0064, -0065, -0066, -0067) ML18317A3822018-12-19019 December 2018 Issuance of Amendment No. 313, Revise Technical Specification 3.3.3.6, Post-Accident Instrumentation ML18298A0122018-11-27027 November 2018 Issuance of Amendment No. 311 Updating the Reactor Coolant System Pressure Temperature Limits ML18260A3392018-10-24024 October 2018 Issuance of Amendment No. 261 Revision to Technical Specification Bases Related to Emergency Feedwater Turbine-Driven Pump Steam Supply Valves ML18192A1042018-08-15015 August 2018 Alternative to Examination of Reactor Pressure Vessel Flange Threads ML18173A0192018-06-27027 June 2018 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule (CAC MG0244; EPID L-2017-LLL-0020) ML18115A2822018-06-19019 June 2018 Issuance of Amendment No. 260 Technical Specification Changes Pursuant to Technical Specifications Task Force (TSTF) Traveler TSTF-412 Revision 3 (CAC No. MG0009; EPID L-2017-LLA-0267) ML18134A2532018-06-19019 June 2018 Issuance of Amendment No. 310 Technical Specification Changes to Provide Actions for Emergency Feedwater Pump Inoperability Consistent with NUREG-1432, Revision 4 (CAC No. MG0016; EPID L-2017-LLA-0268) ML18128A0672018-06-0808 June 2018 Arkansas, Units 1 and 2; Grand Gulf, Unit 1; Indian Point Unit Nos. 2 and 3; Palisades; Pilgrim; River Bend Station, Unit 1; and Waterford, Unit-3 Relief Request No. EN-17-RR-1, Alternative to Use ASME Code Case N-513-4 2024-01-24
[Table view] |
Text
April 14, 2005 Mr. Jeffrey S. Forbes Site Vice President Arkansas Nuclear One Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT NO. 1 ISSUANCE OF AMENDMENT RE: ELIMINATION OF REQUIREMENTS TO PROVIDE MONTHLY OPERATING REPORTS AND ANNUAL OCCUPATIONAL RADIATION EXPOSURE REPORTS (TAC NO. MC5449)
Dear Mr. Forbes:
The Commission has issued the enclosed Amendment No. 223 to Renewed Facility Operating License No. DPR-51 for Arkansas Nuclear One, Unit No. 1. The amendment consists of changes to the Technical Specifications (TSs) in response to your application dated December 20, 2004.
The amendment deletes TS 5.6.1, ?Occupational Radiation Exposure Report, and TS 5.6.4,
?Monthly Operating Reports, as described in the Notice of Availability published in the Federal Register on June 23, 2004 (69 FR 35067).
A copy of our related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
Bhalchandra Vaidya, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-313
Enclosures:
- 1. Amendment No. 223 to DPR-51
- 2. Safety Evaluation cc w/encls: See next page
Mr. Jeffrey S. Forbes April 14, 2005 Site Vice President Arkansas Nuclear One Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT NO. 1 ISSUANCE OF AMENDMENT RE: ELIMINATION OF REQUIREMENTS TO PROVIDE MONTHLY OPERATING REPORTS AND ANNUAL OCCUPATIONAL RADIATION EXPOSURE REPORTS (TAC NO. MC5449)
Dear Mr. Forbes:
The Commission has issued the enclosed Amendment No. 223 to Renewed Facility Operating License No. DPR-51 for Arkansas Nuclear One, Unit No. 1. The amendment consists of changes to the Technical Specifications (TSs) in response to your application dated December 20, 2004.
The amendment deletes TS 5.6.1, ?Occupational Radiation Exposure Report, and TS 5.6.4,
?Monthly Operating Reports, as described in the Notice of Availability published in the Federal Register on June 23, 2004 (69 FR 35067).
A copy of our related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.
Sincerely,
/RA/
Bhalchandra Vaidya, Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-313
Enclosures:
- 1. Amendment No. 223 to DPR-51
- 2. Safety Evaluation cc w/encls: See next page DISTRIBUTION: RidsNrrPMBVaidya PUBLIC PDIV-1 Reading RidsNrrDlpmLpdiv (HBerkow)
RidsNrrDlpmLpdiv1 (AHowe) RidsNrrPMTAlexion RidsNrrLADBaxley RidsOgcRp RidsAcrsAcnwMailCenter GHill (2)
RidsNrrDipmIrob (TBoyce) RidsRgn4MailCenter (AHowell) RidsNrrDlpmDpr (RKuntz)
Accession No.:ML050810657 OFFICE CLIIP LPM PDIV-1/PM PDIV-1/LA PDIV-1/SC NAME WReckley BVaidya DBaxley AHowe DATE 3/14/05 4/12/05 4/12/05 4/13/05 OFFICIAL RECORD COPY
ENTERGY OPERATIONS INC.
DOCKET NO. 50-313 ARKANSAS NUCLEAR ONE, UNIT NO. 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 223 Renewed License No. DPR-51
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Entergy Operations, Inc. (the licensee) dated December 20, 2004, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this license amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
2
- 2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.c.(2) of Renewed Facility Operating License No. DPR-51 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 223, are hereby incorporated in the renewed license.
EOI shall operate the facility in accordance with the Technical Specifications.
- 3. The license amendment is effective as of its date of issuance and shall be implemented within 90 days from the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Allen G. Howe, Chief, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: April 14, 2005
ATTACHMENT TO LICENSE AMENDMENT NO. 223 RENEWED FACILITY OPERATING LICENSE NO. DPR-51 DOCKET NO. 50-313 Replace the following pages of the Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert 5.0-26 5.0-26 5.0-27 5.0-27
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 223 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-51 ENTERGY OPERATIONS, INC.
ARKANSAS NUCLEAR ONE, UNIT NO. 1 DOCKET NO. 50-313
1.0 INTRODUCTION
By application dated December 20, 2004 (ADAMS Accession No. ML050130161), Entergy Operations, Inc. (the licensee), submitted a request for changes to the Arkansas Nuclear One, Unit No. 1 (ANO-1) Technical Specifications (TSs). The requested changes would delete TS 5.6.1, Occupational Radiation Exposure Report, and TS 5.6.4, Monthly Operating Reports, as described in the Notice of Availability published in the Federal Register on June 23, 2004 (69 FR 35067).
2.0 REGULATORY EVALUATION
Section 182a. of the Atomic Energy Act of 1954, as amended, (the Act) requires applicants for nuclear power plant operating licenses to state TS to be included as part of the license. The Commissions regulatory requirements related to the content of TSs are set forth in Section 50.36, Technical specifications of Title 10 of the Code of Federal Regulatons (10 CFR). The regulation requires that TSs include items in five specific categories, including (1) safety limits, limiting safety system settings, and limiting control settings; (2) limiting conditions for operation (LCOs); (3) surveillance requirements; (4) design features; and (5) administrative controls. However, the regulation does not specify the particular requirements to be included in a plants TSs.
The Commission has provided guidance for the content of TSs in its Final Policy Statement on Technical Specification Improvements for Nuclear Power Reactors (58 FR 39132, published July 22, 1993), in which the Commission indicated that compliance with the Final Policy Statement satisfies Section 182a. of the Act. The Final Policy Statement identified four criteria to be used in determining whether a particular item should be addressed in the TSs as an LCO.
The criteria were subsequently incorporated into 10 CFR 50.36 (60 FR 36593, published July 19, 1995). While the criteria specifically apply to LCOs, the Commission indicated that the intent of these criteria may be used to identify the optimum set of administrative controls in TSs.
Addressing administrative controls, 10 CFR 50.36 states that they are the provisions relating to organization and management, procedures, recordkeeping, review and audit, and reporting necessary to assure operation of the facility in a safe manner. The specific content of the administrative controls section of the TS is, therefore, related to those programs and reports
that the Commission deems essential for the safe operation of the facility, which are not adequately covered by regulations or other regulatory requirements. Accordingly, the staff may determine that specific requirements, such as those associated with this change, may be removed from the administrative controls in the TS if they are not explicitly required by 10 CFR 50.36(c)(5) and are not otherwise necessary to obviate the possibility of an abnormal situation or event giving rise to an immediate threat to the public health and safety.
The impetus for the monthly operating report (MOR) came from the 1973-1974 oil embargo.
Regulatory Guide 1.16, Revision 4, "Reporting of Operating Information - Appendix A Technical Specifications," published for comment in August 1975, identifies operating statistics and shutdown experience information that was desired in the operating report at that time. In the mid-1990s, the NRC staff assessed the information that is submitted in the MOR and determined that while some of the information was no longer used by the staff, the MOR was the only source of some data used in the NRC Performance Indicator (PI) Program of that time period (see NRC Generic Letter (GL) 97-02, Revised Contents of the Monthly Operating Report). Beginning in the late 1990s, the NRC developed and implemented a major revision to its assessment, inspection, and enforcement processes through its Reactor Oversight Process (ROP). The ROP uses both plant-level PIs and inspections performed by NRC personnel. In conjunction with the development of the ROP, the NRC developed the Industry Trends Program (ITP). The ITP provides the NRC a means to assess overall industry performance using industry level indicators and to report on industry trends to various stakeholders (e.g., Congress). Information from the ITP is used to assess the NRCs performance related to its goal of having no statistically significant adverse industry trends in safety performance.
The ITP uses some of the same PIs as the PI Program from the mid-1990s and, therefore, the NRC has a continuing use for the data provided in MORs. The NRC also uses some data from the MORs to support the evaluation of operating experience, licensee event reports, and other assessments performed by the staff and its contractors.
Licensees are required by TSs to submit annual occupational radiation exposure reports (ORERs) to the NRC. The reports, developed in the mid-1970s, supplement the reporting requirements currently defined in 10 CFR 20.2206, Reports of individual monitoring, by providing a tabulation of data by work areas and job functions. The NRC included data from the ORERs in its annual publication of NUREG-0713, Occupational Radiation Exposure at Commercial Nuclear Power Reactors and Other Facilities, through the year 1997, but no longer includes the data in that or other reports.
3.0 TECHNICAL EVALUATION
3.1 Monthly Operating Reports As previously mentioned, the administrative requirements in TSs are reserved for the provisions relating to organization and management, procedures, recordkeeping, review and audit, and reporting necessary to assure operation of the facility in a safe manner. The current use of the information from the MORs is not related to reporting on or confirming the safe operation of specific nuclear power plants. Instead, the data is used by the NRC to assess and communicate with stakeholders regarding the overall performance of the nuclear industry. Data related to PIs for specific plants are reported to the NRC as part of the ROP. The staff has determined that the MORs do not meet the criteria defined for requirements to be included in the administrative section of TSs and the reporting requirement may, therefore, be removed.
Although the MORs do not satisfy the criteria for inclusion in TSs, the NRC staff nevertheless has a continuing need to receive the data in order to compile its reports on industry trends and to support other evaluations of operating experience. In addition, information such as plant capacity factors that are reported in the MORs are useful to the staff and are frequently asked for by agency stakeholders.
The NRC staff interacted with licensees, industry organizations, and other stakeholders during the development of the Consolidated Data Entry (CDE) program (currently being developed and maintained by the Institute of Nuclear Power Operation), regarding the use of an industry database like CDE to provide data currently obtained from MORs. These discussions also involved the related Revision 1 to TS Task Force No. 369 (TSTF-369), Removal of Monthly Operating Report and Occupational Radiation Exposure Report. As described in Section 4 of this safety evaluation, the licensee is making a regulatory commitment to continue to provide the data identified in GL 97-02, following the removal of the TS requirement to submit MORs, and will, therefore, continue to meet the needs of the NRC staff for the ITP and other evaluations. The use of an industry database such as CDE is more efficient and cost-effective for both the NRC and licensees than would be having the NRC staff obtain the needed information from other means currently available. Should a licensee fail to satisfy the regulatory commitment to voluntarily provide the information, the NRC could obtain the information through its inspection program (similar to the process described in NRC Inspection Procedure 71150, Discrepant or Unreported Performance Indicator Data) with the licensee being charged for the time spent by the NRC staff.
The only significant changes resulting from the adoption of TSTF-369 are that the information will be provided quarterly instead of monthly (although the operating data will still be divided by month) and the form of the reporting will be from a consolidated database such as CDE instead of in correspondence from individual licensees. The change of reporting frequency to quarterly has some advantages for both the staff and licensees, since it will coincide with the collection and submission of the ROP PI data. In terms of the specific method used to transmit the data to the NRC, the licensee has committed (see Section 4.0) to provide data identified in GL 97-02 on a quarterly basis. The staff believes that the most efficient process for licensees and the NRC will be for all licensees to use a system such as CDE. Such systems have advantages in terms of improved data entry, data checking, and data verification and validation. The NRC will recognize efficiency gains by having the data from all plants reported using the same computer software and format. Although the data may be transmitted to the NRC from an industry organization maintaining a database such as CDE, the licensee provides the data for the system and remains responsible for the accuracy of the data submitted to the NRC for its plant.
The public will continue to have access to the data through official agency records accessible on the Agencywide Documents Access and Management System. Therefore, the NRC staff finds it acceptable that TS 5.6.4 is being deleted and the MOR will no longer be submitted by the licensee.
3.2 Occupational Radiation Exposure Report The information that the NRC staff needs regarding occupational doses is provided by licensees in the reports required under 10 CFR Part 20. The data from the Part 20 reports are sufficient to support the NRC trending programs, radiation related studies, and preparation of reports such as NUREG-0713. Accordingly, the NRCs limited use of the ORER submitted pursuant to the existing TS requirements no longer warrants the regulatory burden imposed on licensees. Therefore, the staff finds it acceptable that TS 5.6.1 is being deleted and the ORER will no longer be submitted by the licensee.
4.0 VERIFICATIONS AND COMMITMENTS In order to efficiently process incoming license amendment applications, the staff requested each licensee requesting the changes addressed by TSTF-369 using the CLIIP to address the following plant-specific regulatory commitment.
Each licensee should make a regulatory commitment to provide to the NRC using an industry database the operating data (for each calender month) that is described in Generic Letter 97-02 Revised Contents of the Monthly Operating Report, by the last day of the month following the end of each calendar quarter. The regulatory commitment will be based on use of an industry database (e.g., the industrys Consolidated Data Entry (CDE) program, currently being developed and maintained by the Institute of Nuclear Power Operations).
The licensee has made a regulatory commitment to provide the requested data via an industry database (e.g., the CDE) by the end of the month following each calendar quarter.
The NRC staff finds that reasonable controls for the implementation and for subsequent evaluation of proposed changes pertaining to the above regulatory commitment can be provided by the licensees administrative processes, including its commitment management program. The NRC staff has agreed that Nuclear Energy Institute 99-04, Revision 0, Guidelines for Managing NRC Commitment Changes, provides reasonable guidance for the control of regulatory commitments made to the NRC staff (see Regulatory Issue Summary 2000-17, "Managing Regulatory Commitments Made by Power Reactor Licensees to the NRC Staff," dated September 21, 2000). The staff notes that this amendment establishes a voluntary reporting system for the operating data that is similar to the system established for the ROP PI program. Should the licensee choose to incorporate a regulatory commitment into the final safety analysis report or other document with established regulatory controls, the associated regulations would define the appropriate change-control and reporting requirements.
5.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Arkansas State official was notified of the proposed issuance of the amendment. The State official had no comments.
6.0 ENVIRONMENTAL CONSIDERATION
The amendment relates to changes in recordkeeping, reporting, or administrative procedures or requirements. Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(10). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
7.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: W. Reckley Date: April 14, 2005
Arkansas Nuclear One cc:
Senior Vice President Vice President, Operations Support
& Chief Operating Officer Entergy Operations, Inc.
Entergy Operations, Inc. P. O. Box 31995 P. O. Box 31995 Jackson, MS 39286-1995 Jackson, MS 39286-1995 Wise, Carter, Child & Caraway Director, Division of Radiation P. O. Box 651 Control and Emergency Management Jackson, MS 39205 Arkansas Department of Health 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Winston & Strawn 1400 L Street, N.W.
Washington, DC 20005-3502 Mr. Mike Schoppman Framatome ANP 3815 Old Forest Road Lynchburg, VA 24501 Senior Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 310 London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 County Judge of Pope County Pope County Courthouse Russellville, AR 72801 July 2004