MONTHYEARML24295A3742024-10-23023 October 2024 Project Manager Assignment IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities 05000354/LER-2024-001-01, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement2024-09-0505 September 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums 05000354/LER-2023-003-01, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges 05000354/LER-2023-003, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-02-12012 February 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers 2024-09-05
[Table view] |
Text
January 10, 2005 Commissioner Bradley M. Campbell State of New Jersey Department of Environmental Protection P.O. Box 402 Trenton, NJ 08625-0402
Dear Mr. Campbell:
I am responding to your letter of December 29, 2004, to Chairman Diaz, regarding the B reactor recirculation pump at the Hope Creek Generating Station (Hope Creek). In your letter, you stated your belief that Public Service Enterprise Group, Nuclear LLC (PSEG) should replace the shaft in the B recirculation pump prior to startup of the Hope Creek unit from the refueling outage.
The NRC staff has closely followed PSEGs efforts to address the issues associated with the B reactor recirculation pump. On December 17, 2004, members of the NRC Region I and Headquarters technical staffs met with PSEG in a public meeting to gather information and to ask questions about the recirculation pump and other related technical issues. The NRC has completed its review and issued a summary of the results in a letter dated January 10, 2005.
The outcome of the review of the recirculation pump issues will be discussed at a public meeting scheduled for January 12, 2005.
The NRC is committed to ensuring the protection of public health and safety through oversight of the facilities that we regulate. NRC actions have been focused on ensuring safe operations at Hope Creek. Results of the NRCs review indicate that the licensees proposal for continuously monitoring the Hope Creek recirculation pumps provides reasonable assurance that a potential crack in the recirculation pump shaft can be detected in time for operators to take appropriate actions to reduce the pump speed or remove the pump from service in order to prevent a complete shaft failure. The NRC intends to issue a Confirmatory Action Letter that will be used to formalize commitments made by PSEG to the NRC regarding implementation of a continuous monitoring program for the B recirculation pump, actions to be taken in the event of abnormal indications, and future repairs of the pump. Additionally, I want to assure you that we will continue to closely oversee PSEGs actions to address technical issues at Hope Creek, and will maintain openness for public involvement in the regulatory process. We plan to discuss the results of our reviews of the October 10, 2004, steam pipe break, the B reactor recirculation pump issues, and other technical issues at the public meeting on January 12, 2005. This meeting, along with issuing the preliminary results of the special inspection and summaries of NRC technical issue reviews, will provide an opportunity for the public to review the results of our assessments. If you have further questions, please feel free to contact me.
Sincerely,
/RA/
J.E. Dyer, Director Office of Nuclear Reactor Regulation
January 10, 2005 Commissioner Bradley M. Campbell State of New Jersey Department of Environmental Protection P.O. Box 402 Trenton, NJ 08625-0402
Dear Mr. Campbell:
I am responding to your letter of December 29, 2004, to Chairman Diaz, regarding the B reactor recirculation pump at the Hope Creek Generating Station (Hope Creek). In your letter, you stated your belief that Public Service Enterprise Group, Nuclear LLC (PSEG) should replace the shaft in the B recirculation pump prior to startup of the Hope Creek unit from the refueling outage.
The NRC staff has closely followed PSEGs efforts to address the issues associated with the B reactor recirculation pump. On December 17, 2004, members of the NRC Region I and Headquarters technical staffs met with PSEG in a public meeting to gather information and to ask questions about the recirculation pump and other related technical issues. The NRC has completed its review and issued a summary of the results in a letter dated January 10, 2005.
The outcome of the review of the recirculation pump issues will be discussed at a public meeting scheduled for January 12, 2005.
The NRC is committed to ensuring the protection of public health and safety through oversight of the facilities that we regulate. NRC actions have been focused on ensuring safe operations at Hope Creek. Results of the NRCs review indicate that the licensees proposal for continuously monitoring the Hope Creek recirculation pumps provides reasonable assurance that a potential crack in the recirculation pump shaft can be detected in time for operators to take appropriate actions to reduce the pump speed or remove the pump from service in order to prevent a complete shaft failure. The NRC intends to issue a Confirmatory Action Letter that will be used to formalize commitments made by PSEG to the NRC regarding implementation of a continuous monitoring program for the B recirculation pump, actions to be taken in the event of abnormal indications, and future repairs of the pump. Additionally, I want to assure you that we will continue to closely oversee PSEGs actions to address technical issues at Hope Creek, and will maintain openness for public involvement in the regulatory process. We plan to discuss the results of our reviews of the October 10, 2004, steam pipe break, the B reactor recirculation pump issues, and other technical issues at the public meeting on January 12, 2005. This meeting, along with issuing the preliminary results of the special inspection and summaries of NRC technical issue reviews, will provide an opportunity for the public to review the results of our assessments. If you have further questions, please feel free to contact me.
Sincerely,
/RA/
J.E. Dyer, Director Office of Nuclear Reactor Regulation DISTRIBUTION See next page Package No.: ML050050018 Incoming No.: ML050050002 Accession No.: ML050050002 OFFICE PDI-2/PM PDI-2/LA PDI-2/SC D:PDI RI/RA NAME DCollins CRaynor DRoberts CHolden SCollins (DRoberts for) (RBlough for)
DATE 01/10/05 01/06/05 01/06/05 01/06/05 01/07/05 OFFICE TechEd D:DLPM AD:ADPT D:NRR NAME PKleene LMarsh BSheron JDyer (JLyons for)
DATE 01/05/05 01/06/05 01/10/05 01/10/05 OFFICIAL RECORD COPY