|
---|
Category:Letter
MONTHYEARML24324A3472024-11-14014 November 2024 $300,000.00 Cash Secured Irrevocable Standby by Letter of Credit as Required in Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML16333A448 ML24270A2422024-09-26026 September 2024 OIG Case 21-012 Response to OIG Letter Dated September 4, 2024 Regarding NRC-OIG Decision to Carry Over Case 21-012 Investigation Findings to Report for Case 21-016 ML24235A5122024-08-22022 August 2024 NRC-OIG_Failure_8-22-24_final ML24220A0532024-08-12012 August 2024 Response to Dr. Slaughter on Final Denial of Claims ML24197A1112024-07-10010 July 2024 Letter Regarding Denying Reimbursement for Service the NRC Did Not Perform in a Satisfactory Manner ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24134A2072024-05-13013 May 2024 Aerotest - NRC Acknowledgment Letter for CFH Program NOV EA-23-118 ML24108A0762024-05-0606 May 2024 Missing Documents on Agencywide Documents Access and Management System ML24085A2662024-03-20020 March 2024 Requesting a Comprehensive Congressional Review Be Conducted of the NRCs Performance Concerning Their Actions Associated with Aerotest Operations Inc (AO) as Outlined in NRC-OIG Investigation 021-012 and 021-016 ML24073A2182024-03-18018 March 2024 Inc. - NRC Inspection Report 050 00228/2023001, Response to Disputed Minor Violation ML23310A1122024-03-0606 March 2024 Aerotest - Letter, License Amendment 7 and SE Approving the Decommissioning Plan for the Radiography and Research Reactor ML24061A0232024-02-27027 February 2024 EA-23-118, Violation 050-00228/203-001-00lA ML24057A0102024-02-21021 February 2024 Inc - Minor Violation (TS 12.6.1) 050-00228/2023-001 and NRCs Definition of Annually ML24057A0112024-02-21021 February 2024 Inc - Response to Notice of Violation No 05000228/2020201 IR 05000228/20202012024-02-20020 February 2024 NRC Inspection Report 05000228/2020201, and Disputed Cited Violation Closed ML24054A0542024-02-16016 February 2024 Missing Documents on Agencywide Documents Access and Management System (ADAMS) ML24039A0382024-02-0808 February 2024 NRC Inspection Report 050-00228/2023-001 (Revised), and Notice of Violation ML24025A1672024-02-0505 February 2024 NRC Inspection Report 050-00228/2023-001, Disputed Cited Violation and Minor Violation Revised, EA-23-118 ML24026A0572024-01-23023 January 2024 EA-23-118 - Missing NRCs 90-day Written Response to Aerotest Operations, Inc., Response to NRC Inspection Report 05000228/2023001 and Dispute of Violation ML24011A2242023-11-10010 November 2023 Letter Informing That New Information Is Available to Show Inadequate Oversight by NRC Caused Damage to Other Non-Power Nuclear Facilities ML23279A1062023-10-0202 October 2023 Response to Violation 05000228/2023001-001B ML23255A0362023-09-0909 September 2023 Response to Inspection Report 050-00228/2023-001 ML23255A0342023-09-0909 September 2023 Response to Violation 050-00228/2023-001-00lA IR 05000228/20230012023-08-24024 August 2023 NRC Inspection Report 05000228/2023001, and Notice of Violation ML23187A0562023-07-0101 July 2023 Radiation Safety Officer Change Update ML23187A0582023-07-0101 July 2023 July 1, 2022 Thru June 30, 2023 Summary of Changes, Tests, and Experiments ML23157A0662023-05-24024 May 2023 Letter from David Slaughter, Aerotest Operations, Inc. Inadequate Oversight of Non-Power Reactor OIG Case No. 21-012 and Requested Payment for Damages Caused by the NRCs Inadequate Oversight ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22340A0062022-11-16016 November 2022 Reference Documents from Decommissioning Plan ML22215A1522022-07-21021 July 2022 Aerotest Radiography and Research Reactor - AO RAI Responses for Decommissioning Plan ML22187A0852022-07-0101 July 2022 Inc - July 1, 2021 Thru June 30, 2022 Summary of Changes, Tests, and Experiments ML22152A2522022-06-28028 June 2022 Request for Additional Information on Review of Request for Amendment to Approve Decommissioning Plan, Arrr (License No. R-98, Docket No. 50-228) ML22060A2602022-03-21021 March 2022 Change in NRC Staff Project Management Responsibility for the Aerotest Radiography and Research Reactor ML22040A1992022-03-0909 March 2022 Examination Confirmation Letter No. 50-288/OL-22-03, Reed College ML22025A2002022-01-20020 January 2022 Amendment to AO Decommissioning Plan Submittal Letter Dated July 20, 2021, Agencywide Documents Access, and Management System (ADAMS) Accession No. ML21230A304 ML21307A3242022-01-12012 January 2022 Request for Supplemental Information for Decommissioning Plan, Arrr (License R-98, Docket 50-228) ML21344A0332022-01-0303 January 2022 Aerotest Letter from the Chief Financial Officer Regarding Additional Information for the Fees Assessed Under to Aerotest Operations, Inc. (Aerotest) within Invoice Number Lfb 22-0346 ML21361A0472021-12-21021 December 2021 Response to December 6, 2021 NRC Pol Issuance; the Licensee and Its Reactor Safeguard Committee Request a Reasonable Opportunity to Review and Address Short Comings of the Draft Licensee and Technical Specifications Along with the Draft Sa ML21242A4632021-12-0606 December 2021 Issuance of License Amendment No. 6 to Facility Operating License No. R-98 for the Aerotest Radiography and Research Reactor with Partial Denial of Amendment Request ML21307A1252021-10-28028 October 2021 Letter Regarding Charges Billed ML21209A5192021-07-20020 July 2021 Aerotest Radiography and Research Reactor, Response to NRC Letter Dated July 12, 2021 (ML21188A391) ML21230A3042021-07-20020 July 2021 Decommissioning Plan Submittal (Redacted) ML21147A3732021-07-19019 July 2021 Correction of Letters Regarding Closure of Confirmatory Action Letter No. NRR-04-003 and Review of Physical Security Plan ML21188A3912021-07-12012 July 2021 Inc. - Revised Completion Date Possession-Only License Amendment Request for the Aerotest Radiography and Research Reactor Facility Operating License ML21188A2162021-07-0101 July 2021 July 1, 2020 Through June 30, 2021 Summary of Changes, Tests, and Experiments ML21193A0892021-07-0101 July 2021 Emergency Plan (Redacted) ML21181A1232021-06-22022 June 2021 License and TS Amendments ML21147A0602021-05-19019 May 2021 Response to RAI 28 and 29 ML21056A3172021-04-30030 April 2021 CFO Response to Aerotest November 11 2020 Letter ML21126A1502021-04-28028 April 2021 License and TS Amendments 2024-09-26
[Table view] |
Text
A3455 AEROTEST OPERATIONS, INC.
FOSTORIA WAY
- SAN RAMON, CA 94583 * (925) 866-1212 ° FAX (925) 866-1716 January 9, 2012 AMENDED AND RE-SUBMITTED January 11, 2012 Mr. Spyros Traiforos Attn: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Dear Mr. Traiforos:
As per our telephone discussion earlier today between Jesse Quichocho, Patrick Isaac, Spyros Traiforos and Sandra Warren, we are reporting that in our annual fuel inspection from December 5-12, 2011, we discovered four aluminum TRIGA elements with what we assume are non-displaced cracks. Although not precisely measured, these cracks may be in a non-fuel area. While we do not believe they are an immediate safety issue, they are certainly significant defects.
The following issues were discussed on the phone:
- 1) The site characterization done on the facility in 2011 revealed that the resin in the demineralizer contained some Cesium- 137 and transuranics that would indicate a fuel failure. At that time, we went back through all of our fuel inspections for the last 5 years and realized that there was an element which had been removed from the core in 2007 that was the most likely candidate for a clad failure. We reported that element to Cindy Montgomery on September 19, 2011, and in a later conference call with Al Adams, it was decided that the proper course of action would be for Ms. Montgomery to summarize the call in an email to Patricia Silva, which she did. The monthly pool water surveys on our own equipment had not revealed the presence of Cesium, but the resin does concentrate radioactivity.
- 2) Our fuel inspection for 2011 required us to do a 100% inspection of all fuel elements. Our inspection procedure calls for a different 20% of the core to be inspected annually, and after five fuel movement programs, 100% of the core must be inspected. We performed fuel movements from December 5 -7, 2011, with a normal-speed video review on December 8-12, 2011. Although the fuel inspection remains an open item at this time because there are several maintenance/administrative items left open (such as calibrating the control rods upon re-assembly), we completed the general fuel inspection operations on December 12, 2011, as far as we could go at that time without re-assembly.
A subsidiary of Autoliv ASP, INC.
VIJ,/, ?
- 3) As of the 2011 inspection, we now have 27 elements that cannot be removed from the grid plate because they have swollen in some manner, usually in the upper non-fuel area. We also have 11 stuck graphite elements that have no fuel at all in them. The four elements that were discovered to be cracked in this inspection are all among the 27 stuck elements.
- 4) The continuous air and water monitors were usually set at 10% of the Emergency Action Levels and did not annunciate in the last 5 years except for occasional 3-5 second responses from the water monitor which were assumed to be the "bubbles" that have been discussed in the TRIGA community from uranium trapped in the welds of the stainless steel elements. Base level counts have been increasing since the 1980's but have always remained below 10% of the Emergency Action Levels.
- 5) Aerotest has not discharged any water since the shutdown. The last time the reactor went critical was December 5, 2011 at 100w for an excess reactivity measurement as required before the fuel inspection. We did a loss-to-power briefly at 250kw on October 4, 2011. A thermal power calibration was performed for 1:05 hours at 205kw and 0:01 hours at 250kw for another loss-to-power.
- 6) Paragraph 10.2 of our Technical Specifications requires that we not operate the reactor if any significant defects are present. Our Tech Specs also define "operating" as not being shutdown. Therefore, since the Tech Specs and our Critical Assembly procedure were now in conflict, we wrote a Temporary Change to a Procedure on December 12, 2011 to our Critical Assembly and Power Calibration (attached). The Temporary Procedure will have to be renewed while we apply some engineering to resolve this situation.
- 7) The issues we will work on immediately are: removing the instrumented element, possibly by sawing off the thermocouple; maintaining accountability of the elements if we drop them out from below the grid plate, making a tool to pick them up from the bottom grid plate, discussing the issue with General Atomics, RSC meetings, etc. A potential possession-only license amendment still being discussed would affect how things are handled.
Since we have to access the stuck elements soon, we left the good elements in the storage racks, so what we have now is really a subcritical assembly. We still have all of our compensatory security measures in place.
We will maintain contact with Spyros Traiforos to keep him informed on the status.
On behalf of Aerotest Operations, Inc., I certify that the content of this letter contains information that is true and correct to the best of my knowledge.
Sandra L. Warren General Manager A subsidiary of Autoliv ASP, INC.