ML22152A252

From kanterella
Jump to navigation Jump to search
Request for Additional Information on Review of Request for Amendment to Approve Decommissioning Plan, Arrr (License No. R-98, Docket No. 50-228)
ML22152A252
Person / Time
Site: Aerotest
Issue date: 06/28/2022
From: Jack Parrott
Reactor Decommissioning Branch
To: Slaughter D
Aerotest
Parrott J
References
EPID L‑2021‑LLN‑0004
Download: ML22152A252 (6)


Text

June 28, 2022 Dr. David M. Slaughter, President and Reactor Administrator Aerotest Operations, Inc.

3455 Fostoria Way San Ramon, CA 94583

SUBJECT:

AEROTEST OPERATIONS, INC.-REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO APPROVE THE AEROTEST RADIOGRAPHY AND RESEARCH REACTOR DECOMMISSIONING PLAN (EPID L2021LLN0004)

Dear Dr. Slaughter:

By letter dated December 6, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML18344A049), Aerotest Operations, Inc. (Aerotest) certified that it had permanently ceased operations of the Aerotest Radiography and Research Reactor.

Therefore, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.82(b)(1),

Termination of License, for non-power reactor licensees, Aerotest submitted both an application for license termination and a Decommissioning Plan (DP) by letter dated July 20, 2021 (ML21230A304), as supplemented by letter dated January 20, 2022 (ML22025A200), in the form of a license amendment request (LAR) to the U.S. Nuclear Regulatory Commission (NRC) for approval of the DP.

The NRC staff has identified additional information needed to continue its review of the LAR, as described in the enclosed request for additional information (RAI). Please provide a response to the RAI or a written request for additional time to respond, including the proposed response date and a brief description of the reason, by 30 days from the date of this letter. Following receipt of the complete response to the RAI, the NRC staff will continue its review of the LAR.

The response to the RAI must be submitted in accordance with 10 CFR 50.4, Written communications, and, pursuant to 10 CFR 50.30(b), Oath or affirmation, be executed in a signed original document under oath or affirmation. Information included in the response that you consider sensitive or proprietary, and seek to have withheld from public disclosure, must be marked in accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs ADAMS. ADAMS is accessible from the NRC website at https://www.nrc.gov/reading-rm/adams.html.

D. Slaughter If you have any questions regarding the NRC staffs review or if you intend to request additional time to respond, please contact me at (301) 415-6634, or via email at Jack.Parrott@nrc.gov.

Sincerely, Signed by Parrott, Jack on 06/28/22 Jack D. Parrott, Senior Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards Docket No. 50228 License No. R98

Enclosure:

As stated cc: Aerotest mailing list

OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS REQUEST FOR ADDITIONAL INFORMATION REGARDING AMENDMENT FOR APPROVAL OF THE DECOMMISSIONING PLAN FACILITY OPERATING LICENSE NO. R98 AEROTEST OPERATIONS, INC.

AEROTEST RADIOGRAPHY AND RESEARCH REACTOR DOCKET NO. 50228 The U.S. Nuclear Regulatory Commission (NRC) staff is continuing its review of the Aerotest Operations, Inc. (Aerotest, the licensee) license amendment request (LAR), dated July 20, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21230A304)), as supplemented by letter dated January 20, 2022 (ML22025A200), to approve the Decommissioning Plan (DP) in support of the licensees decision to permanently cease operation of the Aerotest Radiography and Research Reactor (ARRR). This request for additional information was developed based on the following requirements and guidance applicable to the LAR:

The regulations in Title 10 of the Code of Federal Regulations (10 CFR) 50.9, Completeness and accuracy of information, require that information provided to the Commission by a licensee be complete and accurate in all material respects.

The regulations in 10 CFR 50.82(b), Termination of license, for non-power reactor licensees provides requirements for license termination for non-power 10 CFR Part 50 licensees.

The regulations in 10 CFR 51.21, Criteria for and identification of licensing and regulatory actions requiring environmental assessments, provides requirements of environmental assessments for licensing actions.

NUREG1537, Part 2, Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors, Standard Review Plan and Acceptance Criteria, Chapter 17, Decommissioning and Possession-Only License Amendments, dated February 1996 (ML042430048), Appendix 17.1, NRC Review of Decommissioning Plans for Non-Power Reactors, provides guidance on reviewing the format and content of non-power reactor decommissioning plans.

As a result of the Aerotests request to amend its license, the NRC staff performed a comprehensive review of the proposed DP and identified the following request for additional information (RAI).

Enclosure

Application 10 CFR 51.21 states that all licensing and regulatory actions subject to this subpart require an environmental assessment except those identified in § 51.20(b) as requiring an environmental impact statement, those identified in § 51.22(c) as categorical exclusions, and those identified in

§ 51.22(d) as other actions not requiring environmental review.

RAI 1. Please identify if Aerotest believes this request requires an environmental assessment or qualifies for an exception under the regulations cited above, and if so, please provide the basis for that determination.

Decommissioning Organization and Responsibilities 10 CFR 50.82(b)(4)(ii) states that the proposed DP must include a description of the controls and limits on procedures and equipment to protect occupational and public health and safety.

Section 4.4 of the DP, entitled Decommissioning Organization and Responsibilities, states that

[t]he Aerotest President with support from the Reactor Safeguards [emphasis added]

Committee will monitor decommissioning operations to ensure they are being performed safely and according to federal, state, and local regulatory requirements (NRC, EPA, (DOT), etc.)) and will approve of decommissioning procedures used during the decommissioning as described in this plan. Consistent with Aerotest policy, the Radiation Safety [emphasis added] Committee (RSC) has certain responsibilities to review and approve policies, procedures, programs and facilities pursuant to the safe use of radiological materials and radiation producing equipment.

The RSC's jurisdiction will extend to all decommissioning activities dealing with radioactive material and radiological controls.

Figure 43 of the DP, entitled ARRR Decommissioning Organization shows where the Reactor Safety [emphasis added] Committee is in the overall ARRR decommissioning organization.

Section 11.0 of the DP, entitled Changes to the Decommissioning Plan, states that Aerotest requests that changes to the Decommissioning Plan be allowed with local approval by the Aerotest President and the Reactor Safeguard [emphasis added] Committee without prior USNRC approval, unless an unreviewed safety question is involved.

RAI 2. Are the Reactor Safeguard(s) Committee, the Radiation Safety Committee, and the Reactor Safety Committee one and the same? If not, please describe the composition, function, responsibilities, and authority of each of these committees regarding reviews and audits of major decommissioning activities, proposed procedures, radiation exposure records, reportable occurrences, and changes to the DP, or reference where that information is contained in the licensees Possession-only License or Technical Specifications.

RAI 3. If they are the same committee, please clarify the name of the committee.

RAI 4. Please provide the required technical qualifications of the Radiation Safety Officer and the Reactor Administrator, or reference where that information is contained in the licensees Possession-only License or Technical Specifications.

RAI 5. Does the Radiation Safety Officer or radiation safety organization have independent authority to stop work?

RAI 6. Please reconcile the differences in the ARRR Decommissioning Organization presented in Figure 43 of the DP with the Figure 1 of the ARRR Technical Specifications entitled, ARRR ANSI/ANS15.1 Organization in Attachment 2 to Facility Operating License No. R98, Amendment No. 6, dated January 6, 2021 (ML21242A463).

Facility Operating History 10 CFR 50.82(b)(4)(iii) states that the proposed DP must include a description of the planned final radiation survey.

RAI 7. For NRC to fully evaluate the planned final radiation survey in accordance with 10 CFR 50.82(b)(4)(iii), please provide a copy of Ref 41, CSHP-PR004, Historical Site Assessment of the Aerotest Radiography and Research Reactor, San Ramon, California, Revision 0, July 2011.

Facility Radiological Status 10 CFR 50.82(b)(4)(iii) states that the proposed decommissioning plan must include a description of the planned final radiation survey.

RAI 8. For NRC to fully evaluate the planned final radiation survey in accordance with 10 CFR 50.82(b)(4)(iii), please provide a copy of Ref 42, CSHPPR007, Characterization Report/or the Aerotest Radiography & Research Reactor, San Ramon, California, Revision 0, August 2011.

Choice of Decommissioning Alternative RAI 9. For NRC to fully evaluate the factors delaying the completion of decommissioning (10 CFR 50.82(b)(4)(i)) please provide a description of fuel management plans, plans for fuel removal, and plans for ultimate disposition of fuel to the extent they are known at this time (see NUREG1537, Part 2, Chapter 17, Appendix 17.1, Section 3.2.1, Fuel Removal).

Availability of Funds and Estimated Cost 10 CFR 50.82(b)(3) states that for decommissioning plans that delay completion of decommissioning by including a period of storage or surveillance, the licensee shall provide that (i) Funds needed to complete decommissioning be placed into an account segregated from the licensees assets and outside the licensees administrative control during the storage or surveillance period, or a surety method or fund statement of intent be maintained in accordance with the criteria of § 50.75(e); and (ii) Means be included for adjusting cost estimates and associated funding levels over the storage or surveillance period.

Section 3.2.3 of the DP, Availability of Funds, states that, Nuclear Labyrinth, LLC/Aerotest Operations, Inc are committed to providing funding for decommissioning of the ARRR.

However, no information is provided on current decommissioning funding instruments in place or assurance methodology.

RAI 10. Provide information on all funding currently available for ARRR decommissioning.

Include a comparison of available funding to the amount estimated to be needed for SAFSTOR and decommissioning of ARRR, a means for adjusting funding over the SAFSTOR period, and a plan for assuring the availability of funds for completion of decommissioning.

10 CFR 50.82(b)(4)(iv) states, in part, that the proposed decommissioning plan must include an updated cost estimate for the chosen alternative for decommissioning, comparison of that estimate with present funds set aside for decommissioning, and plan for assuring the availability of adequate funds for completion of decommissioning.

Section 3.2.1 of the proposed DP, Reactor Decommissioning Overview, states that the ARRR facility will be placed in SAFSTOR until the fuel is removed and then the facility will be decontaminated to levels that permit release for unrestricted use. Section 3.2.2 of the proposed DP, Estimated Cost states that the estimated cost to cover D&D [Deactivation and Decommissioning] of the ARRR, including dismantlement of the reactor and reactor systems but not site restoration activities, is $2,879,276. For the basis of the estimated cost, the DP references the Decommissioning Cost Estimate for the Aerotest Radiography and Research Reactor, San Ramon CA, dated 2019. However, other than a cost breakdown in Table 33:

Decommissioning Cost Summary - ARRR, the entirety of the decommissioning cost estimate is not presented with the DP as an attachment, or otherwise made available to the NRC for review.

RAI 11. Provide a copy of CSHPPR006, Decommissioning Cost Estimate for the Aerotest Radiography and Research Reactor, San Ramon, Revision 6, January 2019, prepared by EnergySolutions. Include a current estimated cost in 2022 dollars and means for adjusting the cost estimate during the storage and active decommissioning periods.

10 CFR 50.82(b)(4)(iv) states that the proposed decommissioning plan must include an updated cost estimate for the chosen alternative for decommissioning, comparison of that estimate with present funds set aside for decommissioning, and plan for assuring the availability of adequate funds for completion of decommissioning.

RAI 12. To support the updated decommissioning cost estimate, please provide the estimated volumes (if not provided in the above reference requests) of low-level radioactive waste by waste classification that will require offsite disposal.

Ltr ML22152A252

  • via email OGC/GCHA OFFICE NMSS/DUWP/RDB NMSS/DUWP/RDB NMSS/DUWP/RDB

/AGCNRP/NLO*

NAME JParrott JP SAnderson SA KRoach KR JParrott JP DATE Jun 2, 2022 Jun 9, 2022 Jun 28, 2022 Jun 28, 2022