MONTHYEARML24010A0032024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24026A0532024-01-30030 January 2024 Notification of an NRC Fire Protection Team Inspection- (Report 05000348/2024011, 05000364/2024011) and Request for Information IR 05000348/20230402024-01-24024 January 2024 95001 Supplemental Inspection Report 05000348/2023040 and Follow-Up Assessment Letter ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) NL-24-0011, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-01-11011 January 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23346A2222023-12-22022 December 2023 Transmittal of Dam Inspection Report - Public NL-23-0901, 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers2023-12-15015 December 2023 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers NL-23-0908, Cycle 30 Core Operating Limits Report2023-12-13013 December 2023 Cycle 30 Core Operating Limits Report NL-23-0877, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23228A1432023-11-22022 November 2023 Issuance of Amendment Nos. 249 and 246 to Revise TS 3.6.3, Surveillance Requirement 3.6.3.5 to Eliminate Event-Based Testing of Containment Purge Valves with Resilient Seals NL-23-0825, Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection2023-11-14014 November 2023 Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection ML23318A0672023-10-31031 October 2023 1 to Updated Final Safety Analysis Report, Updated NFPA 805 Fire Protection Program Design Basis Document, Technical Specification Bases Changes, Technical Requirements Manual Changes, IR 05000348/20230032023-10-24024 October 2023 Integrated Inspection Report 05000348/2023003 and 05000364/2023003 IR 05000348/20230912023-10-19019 October 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letter NRC Inspection Report 05000348/2023091 IR 05000348/20234022023-10-18018 October 2023 Security Baseline Inspection Report 05000348/2023402 and 05000364/2023402 IR 05000348/20234412023-10-12012 October 2023 Supplemental Inspection Report 05000348/2023441 and 05000364/2023441 and Follow-Up Assessment Letter (Cover Letter) ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report NL-23-0739, Response to NRC Inspection Report and Preliminary White Finding2023-09-0808 September 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000348/20230902023-08-31031 August 2023 NRC Inspection Report 05000348/2023090 and Preliminary White Finding and Apparent Violation ML23164A1202023-08-30030 August 2023 Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.0, to the Requirements of the ASME Code ML23240A0012023-08-30030 August 2023 Correction to Issuance of Amendment Nos. 241, 242, 243, and 244 ML23235A2962023-08-24024 August 2023 Issuance of Amendment Nos. 247 and 244, Regarding License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, (EPID L-2023-LLA-0116) (Emergency Circumstances) NL-23-0716, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0713, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0704, Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-22022 August 2023 Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit IR 05000348/20330012023-08-14014 August 2023 NRC Operator License Examination Report 05000348/203301 and 05000364/2023302 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal IR 05000348/20230022023-08-10010 August 2023 Integrated Inspection Report 05000348/2023002 and 05000364/2023002, and Apparent Violation ML23221A3062023-08-0909 August 2023 Notification of NRC Supplemental Inspection (95002) and Request for Information (Cover Letter) NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI NL-23-0628, Readiness for Supplemental Inspection EA-22-1012023-07-26026 July 2023 Readiness for Supplemental Inspection EA-22-101 NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0506, to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications2023-07-0505 July 2023 to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications ML23136B1542023-07-0303 July 2023 Issuance of Amendment Nos. 246 & 243, Regarding License Amendment Request to Revise Technical Specification 4.3, Fuel Storage, to Correct Tabulated Values from the Associated Spent Fuel Pool (SFP) Criticality Analysis IR 05000348/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 05000348/2023010 and 05000364/2023010 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal ML23164A2182023-06-14014 June 2023 Draft Safety Evaluation for License Amendment Request to Revise Technical Specification 4.3, Fuel Storage, to Correct Tabulated Values from the Associated SFP Criticality Analysis (EPID L-2022-LLA-0138) - Letter NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0449, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2023-06-0202 June 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0337, Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.52023-05-0505 May 2023 Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.5 IR 05000348/20234402023-05-0505 May 2023 Reissue Farley Units-Final Significance Determination for a Security-Related Greater than Green Finding, Nov and Assessment Followup LTR, IR 05000348/2023440 and 05000364/2023440 - Cover IR 05000348/20230012023-05-0404 May 2023 Integrated Inspection Report 05000348/2023001 and 05000364/2023001 NL-23-0295, Reply to a Notice of Violation; EA-22-1012023-05-0101 May 2023 Reply to a Notice of Violation; EA-22-101 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 2024-01-30
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 17, 2012 Mr. Mark J. Ajluni Nuclear Licensing Director Southern Nuclear Operating Company, Inc.
40 Inverness Center Parkway P.O. Box 1295 Bin -038 Birmingham, Alabama 35201
SUBJECT:
JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 - NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 LICENSE AMENDMENT APPLICATION ONLINE REFERENCE PORTAL
Dear Mr. Ajluni:
By letter dated June 29,2011, Southern Nuclear Operating Company (the licensee) provided submittal dates for license amendment application incorporating the National Fire Protection Association Standard (NFPA) 805 for the Joseph M. Farley Nuclear Plant, Units 1 and 2.
To improve the efficiency of the U.S. Nuclear Regulatory Commission (NRC) reviews, the licensees' representatives and the NRC staff have discussed the use of an online reference portal that would allow the NRC staff and contractors limited read-only access to the basis documents and other reference materials cited in the applications. The online reference portal would allow the NRC staff to audit basis documents to determine whether the information included in the documents support the application. Documents identified as necessary for analysis of the application will be identified by the NRC staff. The licensee will be formally requested to submit those documents on the NRC docket. Use of the online reference portal is acceptable as long as the following conditions are met:
- The online reference portal will be password-protected and passwords will be assigned to those directly involved in the review on a need-to-know basis;
- The online reference portal will be sufficiently secure to prevent staff from printing, saving, or downloading any documents; and
- Conditions of use of the online reference portal will be displayed on the login screen and will require concurrence by each user.
The NRC staff would like to request that the portal be populated with the documents listed in the enclosure to this letter when the NFPA 805 license amendment request (LAR) is submitted to the NRC. This will help with the preparation for the site audits and increase effectiveness of the review prior to the audit. Once the NRC accepts the LAR for review, it would be helpful if the portal is ready for immediate access to the NRC staff. Therefore, we request that you send the information to access the portal, such as username and password, immediately after the LAR has been accepted by the NRC.
M. Ajluni -2 The conditions associated with the online reference portal must be maintained throughout the duration of the review process. Please provide written confirmation that the licensee agrees to the terms and conditions set forth in this letter.
Please send the requested information in this letter to the NRC plant project manager. Should you have any questions regarding NFPA 805 portal, please contact Ms. Leslie Fields, Senior Project Engineer, at 301-415-1186, or via email at leslieJields@nrc.gov.
Sincerely,
(~, /--.J? r/Jl v~-J ft j./ ROb~M;rti~, Senior Project Manager Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364 cc w/encl: Distribution via ListServ
GENERIC LIST OF SHAREPOINT PORTAL REQUESTED DOCUMENTS FOR NFPA 805
- 1. National Fire Protection Association (NFPA) Code Deviations and Justifications
- 2. All applicable Probabilistic Risk Assessment (PRA) Peer Review Reports
- 3. All site calculations reference in the License Amendment Request (LAR)
- 4. Credited Fire Protection (FP) System and Feature Drawings
- a. Layout Drawings: fire barriers, installed fire detection and suppression systems, fire areas, fire zones, stairwells, fire doors, fire dampers, etc.
- b. Piping and Instrumentation Diagrams (P&IDs): FP Water System
- c. System Descriptions for Fire Suppression, Water Supply, and Detection (including incipient or very early warning fire detection (VEWFD>>
- d. Hydraulic Calculations for Fire Service and Fire Suppression System Water Demand (if used to support non-fire water use in Title 10 of the Code of Federal Regulations, Section 50.48(c)(2)(vii>>
- 5. Drawings related to systems credited in the Nuclear Safety Capability Assessment (NSCA) as well as those required to fully understand plant response:
- a. P&IDs: Reactor Coolant System, Main Steam, Main Feedwater, Circulating Water, Service Water, etc.
- b. Safe Shutdown/NSCA Logic Diagrams (if used)
- c. Electrical Distribution System One-Lines (alternating current (AC) and direct current (DC>>
- 6. Those documents that fulfill the NFPA 805 requirement for "Design Basis Document (DBD)"
- a. Fire Area Calculations (e.g. Fire Safety Analyses, Fire Risk Analyses, Plant Change Evaluations, Fire Risk Evaluations, etc.)
- b. NSCA Calculation (Safe Shutdown/Circuit Analysis)
- c. Multiple Spurious Operation (MSO) Expert Panel Report
- d. Thermo-Hydraulic Analysis serving as the basis for Variance from Deterministic Requirements (VFDR) and recovery action (RA) timing
- e. Evaluation of Recovery Actions for feasibility
- f. Fire Hazards Analysis (FHA) (if separate from the fire area calculations)
- g. Non-Power Operation (NPO) Calculation(s)
- h. Radioactive Release Calculation(s)
- i. Pre-Fire Plans Enclosure
- 2
- 7. Fire PRA Calculations
- a. Plant Boundary/Partitioning Methods and Results (TASK 1)
- b. Component Selection Calculation (TASK 2)
- c. Cable Selection and Circuit Analysis (TASKS 3, 9, and 10)
- d. Ignition Frequency Calculation (TASK 6)
- e. Fire PRA Quantification Calculations (TASK 5) including:
- i. Seismic Fire Interactions (TASK 13) Methodologies and results (including assumptions) ii. Screening Methodologies and Results (TASKS 4 and 7) (including assumptions) iii. Fire Risk Quantifications (TASK 14) Methodologies and Results (including assumptions) iv. Multi-Compartment Screening and Analysis
- v. Post-Fire Human Reliability Analysis (HRA) Methodologies and Results (including assumptions) (TASK 12) vi. Detailed proposed modification descriptions (Engineering Change Requests/Records) sufficient to comprehend potential impact/improvement to Fire PRA
- f. NFPA 805 Application Calculation (provides all the delta risk calculations for VFDRs)
- g. Control Room Risk Calculation
- h. Uncertainty and Sensitivity Calculations (TASK 15)
- i. Fire Modeling Calculations used to support the Fire PRA (zone of influence (ZOI), hot gas layer, bounding, detailed fire modeling, etc.)
ii Plant Specific Verification and Validation (V&V) Analysis iii. Non-Public V&V References (e.g.; Electric Power Research Institute (EPRI) Fire Modeling, Generic Treatment) iv. Fire Modeling Assumptions and Calculations performed to support target selection (e.g.; ZOI, secondary fires, transient combustible/ignition sources) including those that deviate from NUREG/CR-6850. (TASKS 8 and 11)
- 8. Fire Modeling used in the Fire Modeling Performance-Based Approach
- a. Plant SpeCific V&V Analysis performed
- b. Non-Public V&V References (e.g.; EPRI Fire Modeling, Generic Treatments ... )
- c. Fire Modeling Assumptions and Calculations performed to support Performance Based Evaluations (e.g.; ZOI, secondary fires, transient combustible/ignition sources ... ) considered outside NUREG/CR 6850 Assumptions and Parameters (TASKS 8 and 11)
- d. Hot Gas Layer (HGL) Determination Calculations (including Assumptions)
- 3
- 9. Fire Protection Program Manual
- 10. Fire Protection Quality Assurance (QA) Program (including FP Structure System Components (SSCs) and FP Features)
- 11. NFPA 805 Monitoring Program Calculations and Procedures
- 12. Technical Requirements Manual (TRM)
- 13. Updated Final Safety Analysis Report (UFSAR) Changes (including current UFSAR 9.5.1 Fire Protection and Section 7.4 Alternate Shutdownllnstrumentation)
ML12103A028 OFFICE LPL2-1/PM LPL2-2/LA AFPB/BC LPL2-1/BC LPL2-1/PM NAME RMartin SFigueroa AKlein NSalgado RMartin DATE 04/16/12 04116112 04117112 04117112 04117/12
,