Enclosure 3- NRC Presentation Handout
ML13262A149
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 09/19/2013
From: Bruce Watson
NRC/FSME/DWMEP/DURLD/RDB
To:
Shared Package
ML13262A166 List:
References
Download: ML13262A149 (15)


Text

Three Mile Island - 2 Post Shut Down Activities Report Public Meeting Bruce Watson, CHP Chief, Reactor Decommissioning Branch U.S. Nuclear Regulatory Commission, Washington, D.C. 20555 1

US NRC Decommissioned Facilities 12 10 8

6 4

2 0

1998199920002001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Power Reactors Research Reactors Materials Sites 2

Agenda

  • Discuss the NRC Decommissioning Process
  • Discuss the TMI-2 Post Shutdown Decommissioning Activities Report (PSDAR)
  • Discuss the NRC Inspection Process public comments on PSDAR
  • Hear p 3

Three Mile Island, Unit 2 P t Sh td Post-Shutdown Decommissioning Activities Report John Buckley Reactor Decommissioning Branch U.S. Nuclear Regulatory Commission, Washington D Washington, D.C.

C 20555 4

NRC Decommissioning Process

  • Permanently cease operations
  • Certify permanent cessation of operations
  • Certify fuel removed from reactor
  • Submit PSDAR (within 2 years)
  • SAFSTOR and/or plant decommissioning
  • Application for license termination (LTP)
  • Li License termination i i 5

TMI-2 Decommissioning Process

  • The March 28, 1979, accident made the shutdown of TMI TMI-2 2 different from all other reactors.
  • NRC C approved PDMS SS SAR on September 14, 1993, with License Amendment 45.
  • GPU submits PSDAR on June 28, 2013, to establish compliance with 50.82.

6

PSDAR Requirements

- p planned decommissioning g activities

- decommissioning schedule

- cost estimate for the decommissioning

- environmental impacts of decommissioning deco ss o g 7

PSDAR Review Process

  • NRC notices receipt of PSDAR &

requests public comments

  • NRC schedules PSDAR public meeting
  • NRC considers public comments
  • Review e e PSDAR S in acco accordance da ce with t

Regulatory Guide 1.185

  • PSDAR does not require NRC approval 8

PSDAR Review Criteria

  • Decom can be completed as described
  • Decom can be completed within 60 years
  • Decom can be completed for the estimated cost
  • Decom eco actactivities t es do not ot e endanger da ge pub public c

health and safety or the environment 9

PSDAR Highlights

  • Decommissioning of TMI-2 will start after TMI-1 operating license expires in April 2034
  • TMI-2 TMI 2 willill b be maintained i t i d iin currentt PDMS mode d until til decommissioning begins
  • TMI TMI-22 license termination will occur before September 2053 (60 years after cessation of operations)
  • Decommissioning costs are estimated to be

$844 885 000 (b

$844,885,000 (basedd on 2008 ddollars) ll )

  • Environmental impacts of planned decommissioning activities are bounded by impacts associated with post-post accident cleanup activities and GEIS 10

Conclusion

  • NRC received a PSDAR for TMI-2 on June 2828, 2013
  • Although NRC is not required to approve the PSDAR S by regulation, NRC C will review the PSDAR
  • NRC will consider the public comments in its review of the TMI-2 PSDAR 11

Three Mile Island - Unit 2 Decommissioning Power Reactor Oversight Program PSDAR Public Meeting August 28, 2013 Laurie A. Kauffman Health Physicist Division of Nuclear Materials Safety Region I

Decommissioning Power Reactor Oversight Program

  • Annual A l IInspection ti performed f d by b R Region i I staff t ff

- Verify controls and methods for safe storage of radioactive material and structures at permanently shutdown reactors 13

TMI-2 SAFSTOR PROGRAM

  • No ongoing decommissioning activities
  • Material condition of components remain unchanged
  • Safe storage programs being conducted according to Technical Specifications and site procedures

NRC Contacts

  • John Buckley, Project Manager

- John.Buckley@nrc.gov

- 301-415-6607

- Bruce.Watson@nrc.gov

- 301-415-6221

- Laurie.Kauffman@nrc.gov

- 610-337-5323 610 337 5323 15