MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 IR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) ML24024A2102024-01-29029 January 2024 Summary of Regulatory Audit Regarding a License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24025A0052024-01-25025 January 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23159A2082023-12-20020 December 2023 Request for Withholding Information from Public Disclosure ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23291A4382023-11-30030 November 2023 Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica ML23325A0182023-11-30030 November 2023 Schedule Revision for the License Renewal Application Review IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation ML23308A0032023-11-17017 November 2023 Letter to R. Nelson, Executive Director; Achp; Re., Comanche Peak Draft Environmental Impact Statement ML23308A0022023-11-17017 November 2023 Letter to M. Wolfe, Executive Director; Shpo; Re., Comanche Peak Draft Environmental Impact Statement ML23317A3002023-11-13013 November 2023 Letter to R. Sylestine, Chairman, Alabama-Coushatta Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2972023-11-13013 November 2023 Letter to R. Martin, President, Tonkawa Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2872023-11-13013 November 2023 Letter to J. Garza, Chairman, Kickapoo Traditional Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2832023-11-13013 November 2023 Letter to D. Dotson, President, Delaware Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2852023-11-13013 November 2023 Letter to E. Martinez, President, Mescalero Apache Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23306A0302023-11-13013 November 2023 Letter to J. Cernek, Chairman; Coushatta Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2902023-11-13013 November 2023 Letter to M. Pierite, Chairman, Tunica Biloxi Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2982023-11-13013 November 2023 Letter to R. Morrow, Town King, Thlopthlocco Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2842023-11-13013 November 2023 Letter to D. Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2822023-11-13013 November 2023 Letter to D. Cooper, Chairman, Apache Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2962023-11-13013 November 2023 Letter to M. Woommavovah, Chairman, Comanche Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2812023-11-13013 November 2023 Letter to C. Hoskin, Principal Chief, Cherokee Nation; Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2862023-11-13013 November 2023 Letter to J. Bunch, Chief, United Keetoowah Band of Cherokee Indians Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3032023-11-13013 November 2023 Letter to W. Yargee, Chief, Alabama-Quassarte Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2882023-11-13013 November 2023 Letter to L. Johnson, Chief, Seminole Nation of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3012023-11-13013 November 2023 Letter to S. Yahola, Mekko, Kialegee Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2792023-11-13013 November 2023 Letter to B. Gonzalez, Chairman, Caddo Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3022023-11-13013 November 2023 Letter to T. Parton, President, Wichita and Affiliated Tribes Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2892023-11-13013 November 2023 Letter to L. Spottedbird, Chairman, Kiowa Indian Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23360A6312023-10-26026 October 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the Comanche Peak Nuclear Power Plant Medical Services Drill Evaluated on August 23, 2023 CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23263A0242023-09-21021 September 2023 Revision of Schedule for the Environmental Review of the Comanche Peak Nuclear Power Plant Units 1 and 2 License Renewal Application 2024-01-31
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April14, 2014 Mr. Rafael Flores Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Luminant Generation Company, LLC P.O. Box 1002 Glen Rose, TX 76043
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT, UNIT 1 -RELAXATION OF CERTAIN SCHEDULE REQUIREMENTS FOR ORDER EA-12-049 "ISSUANCE OF ORDER TO MODIFY LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND DESIGN BASIS EXTERNAL EVENTS"
Dear Mr. Flores:
By letter dated March 12, 2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A735), the U.S. Nuclear Regulatory Commission (NRC) ordered Luminant Generation Company, LLC (Luminant Power or the licensee) to take certain actions at Comanche Peak Nuclear Power Plant (Comanche Peak), Units 1 and 2, associated with the Fukushima Near-Term Task Force Recommendations. Order EA-12-049 directed that actions be taken by licensees to develop and implement strategies to maintain or restore core cooling, reactor coolant system inventory, containment cooling, and spent fuel pool (SFP) cooling capabilities during beyond design basis external events (BDBEE).
Section IV of the order states that licensees proposing to deviate from requirements contained in NRC Order EA-12-049 may request that the Director, Office of Nuclear Reactor Regulation, relax or rescind certain requirements. By letter dated February 12, 2014 (ADAMS Accession No. ML14055A330), the licensee informed the NRC of its request for a schedule relaxation of the full implementation schedule requirements for Comanche Peak, Unit 1, as prescribed in Section IV A.2 of NRC Order EA-12-049. Luminant Power has requested an extension of one additional refueling cycle for full implementation, which moves the Unit 1 implementation date from the fall of 2014 to the spring of 2016.
Luminant Power's letter dated February 12, 2014, provided the following basis for the granting of schedule relaxation. Recent testing of reactor coolant pump (RCP) low leakage seals has identified issues with the reliability of the current design to perform as assumed in the Comanche Peak, Unit 1 FLEX strategies. The seal vendor has developed design changes and will provide additional analyses to fully support the basis for crediting the low leakage seals.
Based on this timeline, Luminant Power is requesting a schedule relaxation of one refueling cycle for implementation of the mitigation strategies for Comanche Peak, Unit 1. The requested extension would provide additional time for review of the additional analyses, and for Luminant Power to safely plan, schedule and install the new seals at Comanche Peak, Unit 1.
R. Flores In light of the facts presented in your February 12, 2014, letter, the NRC staff has determined that the licensee has presented good cause for a relaxation of the order implementation date.
The extension would provide additional time to resolve the seal performance issues and fully design and safely implement modifications at Comanche Peak, Unit 1. These are significant actions intended to enhance the licensee's capability to cope with a BDBEE. The NRC staff also considered that, following the accident at Fukushima Dai-ichi, the NRC concluded that a sequence of events such as the Fukushima Dai-ichi accident is unlikely to occur in the United States, based on the current regulatory requirements and existing plant capabilities. Therefore, the extension of time of one additional refueling outage for Comanche Peak, Unit 1 to achieve full implementation of the requirements of the mitigation strategies order is justified and completion before December 2016 is consistent with the intent of the order. These circumstances lead the NRC staff to approve the relaxation of the order implementation date.
Accordingly, based upon the authority granted to the Director, Office of Nuclear Reactor Regulation, the requirement for full order implementation is relaxed for Comanche Peak, Unit 1 until the completion of the spring 2016 refueling outage. The licensee did not request relaxation of the requirement for full order implementation for Comanche Peak, Unit 2, so that requirement, for full implementation by the completion of the Unit 2 fall 2015 refueling outage, is unchanged.
If you have any questions, please contact James Polickoski, 301-415-5430.
Eric . Leeds, Director Office of Nuclear Reactor Regulation Docket No. 50-445 cc: Distribution via Listserv
ML14071A439 OFFICE NRR/MSD/PM NRR/MSD/PM NRR/MSD/LA NRR/MSD/MSPB/BC NAME RHall JPolickoski Slent JBowen DATE 03/12/14 03/13/14 03/12/14 03/14/14 OFFICE OE OGC MSD/D NRR/D NAME RFretz CHair JDavis Eleeds DATE 03/18/14 03/25/14 03/30/14 04/14/14