Other: CP-201301046, First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CP-201400244, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CP-201401055, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CP-201500248, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CP-201500850, Fifth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CP-201500995, Compliance with NRC Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond Design-Basis External Events (Order Number EA-12-049), CP-201600329, Summary of Compliance with EA-12-049, NRC Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond Design-Basis External Events, ML13338A661, ML15076A523, ML15180A261, ML16098A341
|
MONTHYEARCP-201301046, First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13338A6612013-12-18018 December 2013 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Comanche Peak Nuclear Power Plant, TAC Nos.: MF0860 and MF0861 Project stage: Other ML13225A5752013-12-19019 December 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies Project stage: Acceptance Review CP-201400209, (Cpnpp), Docket No. 50-445, Request for Schedule Relaxation for the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events..2014-02-12012 February 2014 (Cpnpp), Docket No. 50-445, Request for Schedule Relaxation for the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events.. Project stage: Request CP-201400244, Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-27027 February 2014 Second Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CP-201401055, Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-08-28028 August 2014 Third Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CP-201500248, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-26026 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15076A5232015-03-26026 March 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15180A2612015-08-0505 August 2015 Report for the Audit Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 Project stage: Other CP-201500850, Fifth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-27027 August 2015 Fifth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CP-201500995, Compliance with NRC Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond Design-Basis External Events (Order Number EA-12-049)2015-11-18018 November 2015 Compliance with NRC Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML16047A3302016-01-20020 January 2016 NEI 12-01 Phase 2 Staffing Assessment, Revision 1 Project stage: Request ML16098A3412016-02-24024 February 2016 Sixth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other CP-201600329, Summary of Compliance with EA-12-049, NRC Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond Design-Basis External Events2016-07-28028 July 2016 Summary of Compliance with EA-12-049, NRC Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond Design-Basis External Events Project stage: Other 2015-11-18
[Table View] |
|
---|
Category:Letter type:CP
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 CP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300391, (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2023-08-24024 August 2023 (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202300361, (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report2023-08-17017 August 2023 (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 CP-202300358, (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 1122023-08-0101 August 2023 (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 112 CP-202300322, Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 32023-07-27027 July 2023 Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 3 CP-202300348, (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48)2023-07-18018 July 2023 (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48) CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300262, Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 22023-06-20020 June 2023 Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 2 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300248, Response to Request for Additional Information Regarding License Renewal Application - Set 12023-06-13013 June 2023 Response to Request for Additional Information Regarding License Renewal Application - Set 1 CP-202300209, Response to Request for Additional Information - License Renewal Application Environmental Review2023-06-0606 June 2023 Response to Request for Additional Information - License Renewal Application Environmental Review CP-202300207, Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-052023-05-25025 May 2023 Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-05 CP-202300182, Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application2023-05-0808 May 2023 Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application CP-202300201, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0)2023-05-0404 May 2023 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0) CP-202300160, (Cpnpp), 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Environmental Operating Report CP-202300159, (Cpnpp), 2022 Annual Radiological Effluent Release Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Effluent Release Report CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300175, Submittal of 2022 Annual Environmental Operating Report (Non-Radiological)2023-04-20020 April 2023 Submittal of 2022 Annual Environmental Operating Report (Non-Radiological) CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300096, License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements2023-04-20020 April 2023 License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements CP-202300140, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-0012023-04-19019 April 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-001 CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300135, License Renewal Application Revision 0 - Supplement 12023-04-0606 April 2023 License Renewal Application Revision 0 - Supplement 1 CP-202300144, (CPNPP) - Decommissioning Report2023-03-30030 March 2023 (CPNPP) - Decommissioning Report CP-202300139, (CPNPP) - Property Damage Insurance2023-03-30030 March 2023 (CPNPP) - Property Damage Insurance CP-202300098, (Cpnpp), Annual Report of Changes in Peak Cladding Temperature2023-03-16016 March 2023 (Cpnpp), Annual Report of Changes in Peak Cladding Temperature CP-202200481, Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST)2022-12-0707 December 2022 Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST) CP-202200454, (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 .2022-12-0101 December 2022 (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 . CP-202200355, Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-0022022-11-21021 November 2022 Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-002 CP-202200380, (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications2022-11-21021 November 2022 (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications CP-202200450, (CPNPP) - Registration of Dry Spent Fuel Storage Canisters2022-11-16016 November 2022 (CPNPP) - Registration of Dry Spent Fuel Storage Canisters CP-202200435, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2022-11-0808 November 2022 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters CP-202200419, (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report2022-11-0303 November 2022 (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report CP-202200357, (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report2022-09-14014 September 2022 (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report CP-202200358, (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46)2022-09-14014 September 2022 (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46) CP-202200246, Evacuation Time Estimate Analysis2022-08-25025 August 2022 Evacuation Time Estimate Analysis CP-202200306, (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22)2022-08-11011 August 2022 (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22) CP-202200273, Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative2022-07-20020 July 2022 Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative CP-202200276, (CPNPP) - Relief Request Application P-1, Inservice Testing (IST)2022-07-20020 July 2022 (CPNPP) - Relief Request Application P-1, Inservice Testing (IST) CP-202200247, (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 0172022-06-30030 June 2022 (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 017 2024-01-31
[Table view] |
Text
Rafael Flares Luminant Power Senior Vice President P 0 Box 1002
& Chief Nuclear Officer 6322 North FM 56 rafael.flores@luminant.com Glen Rose, TX 76043 Luminant T 254 897 5590 C 817 559 0403 F 254 897 6652 CP-201400209 REF 10 CFR 2.202 Log # TXX-14023 February 12, 2014 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
SUBJECT:
Comanche Peak Nuclear Power Plant (CPNPP), Docket No. 50-445, Request for Schedule Relaxation for the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements For Mitigation Strategies For Beyond-Design-Basis External Events (Order Number EA-12-049) (TAC NO. MF0860)
REFERENCES:
- 1. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events dated March 12, 2012
- 2. Luminant Generation Company LLC's Letter TXX-13030, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation strategies for Beyond-Design-Basis External events (Order Number EA-12-049), dated February 28, 2013
Dear Sir or Madam:
This letter transmits a request for relaxation of the schedule requirements contained in Nuclear Regulatory Commission ("NRC" or "Commission") Order EA-12-049. On March 12, 2012, the NRC issued an Order (Reference 1) to Luminant Generation Company, LLC (Comanche Peak Nuclear Power Plant, CPNPP). Reference 1 was immediately effective and directed Luminant Generation Company (Luminant Power) to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event (FLEX strategies).
Luminant Power submitted its Overall Integrated Plan on February 28, 2013 (Reference 2). In accordance with Reference 1, licensees are required to complete full implementation no later than two (2) refueling cycles after submittal of the Overall Integrated Plan, or December 31, 2016, whichever comes first. For CPNPP, the second refueling outages and current required FLEX implementation dates are Fall 2014 for Unit 1, and Fall 2015 for Unit 2. In accordance with Reference 1, the CPNPP Unit 1 first refueling outage started March 30, 2013. The CPNPP Unit 1 second refueling outage and FLEX implementation date is currently scheduled for October 2014.
A4/S A member of the STARS Alliance Callaway - Comanche Peak - Diablo Canyon
'ýcc-c-
U. S. Nudear ReguLatory Commission TXX-14023 Page 2 of 4 02/12/2014 Section IV of NRC Order EA-12-049 (Reference 1) states that licensees proposing to deviate from requirements contained in NRC Order EA-12-049 may request that the Director, Office of Nuclear Reactor Regulation, relax those requirements.
In accordance with Section IV of NRC Order EA-12-049, Luminant Power is requesting that the Director, Office of Nuclear Reactor Regulation, relax the requirement for completion of full implementation for CPNPP Unit 1 as prescribed in Section IV.A.2 of NRC Order EA-12-049 to the spring of 2016.
Luminant Power considers that, upon approval by the NRC, the alternative full implementation dates regarding NRC Order EA-12-049 proposed in the attachment will constitute a condition of the NRC Order EA-12-049 for CPNPP Unit 1. Therefore, there are no new regulatory commitments contained in this letter.
If you have any questions regarding this report, please contact Carl B. Corbin at 254-897-0121 or carl.corbin@luminant.com.
I state under penalty of perjury that the foregoing is true and correct.
Executed on February 12, 2014.
Sincerely, Luminant Generation Company LLC Rafael Flores By: /2K2 .TL .
- tred W. Madden Director, External Affairs Attachment Request for Relaxation of NRC Order EA-12-049 Requirement IV.A.2 for Comanche Peak Nuclear Power Plant Unit 1 c- Eric J. Leeds, Director, Office of Nuclear Reactor Regulation Steven A. Reynolds, Region IV Jessica A. Kratchman, NRR/JLD/PMB Balwant K. Singal, NRR Resident Inspectors, Comanche Peak
Attachment to TXX-14023 Page 1 of 2 Request for Relaxation of NRC Order EA-12-049 Requirement IV.A.2 for Comanche Peak Nuclear Power Plant Unit 1 Relaxation Request.
Pursuant to the procedure specified in Section IV of Nuclear Regulatory Commission (NRC) Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (Reference 1), Luminant Generation Company LLC (Luminant Power) hereby submits a request for schedule relaxation from the Order requirements for completion of full implementation for Comanche Peak Nuclear Power Plant Unit 1 either no later than two (2) refueling cycles after submittal of the Overall Integrated Plan, as required in Condition C.I.a of the Order, or December 31, 2016, whichever comes first.
Order Requirement from Which Relaxation is Requested:
NRC Order EA-12-049,Section IV.A.2 requires completion of full implementation of the Order requirements either no later than two (2) refueling cycles after submittal of the Overall Integrated Plan, as required by Condition C.l.a, or December 31, 2016, whichever comes first. In accordance with the requirements of the Order, Luminant Power submitted the Overall Integrated Plan for Comanche Peak Nuclear Power Plant (CPNPP) Unit 1 (Reference 2) on February 28, 2013. The Overall Integrated Plan milestone schedule identified the completion dates for full implementation of NRC Order EA-12-049 as completion of the fall 2014 refueling outage for CPNPP Unit 1.
NRC Order EA-12-049 requires the development, implementation, and maintenance of guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event (BDBEE). As described in the Overall Integrated Plan for CPNPP Unit 1, these mitigation strategies are dependent upon installation of Westinghouse low leakage Reactor Coolant Pump (RCP) shutdown seals (SHIELD@ seals). Recent post-operational testing of the SHIELD seals at another plant has resulted in the need to enhance the SHIELD design. The new seals will ensure the safety functions of containment integrity (during an extended loss of alternating current power or ELAP), and core cooling (RCS inventory and level) are maintained for beyond-design-basis external events (BDBEEs).
Justification for Relaxation Request:
As described in the Overall Integrated Plan, a key aspect of the Comanche Peak mitigating strategies is implementation of the Westinghouse Reactor Coolant Pump SHIELD passive thermal shutdown seals (low leakage RCP seals). The reduced seal leakage is a fundamental basis for the coping analysis, required modifications, and procedures to ensure core cooling, containment integrity and equipment functionality are adequately maintained during the event. Recent testing of SHIELD RCP seals has identified issues with the reliability of the current design to perform as assumed in the Comanche Peak FLEX strategies. Westinghouse has developed design changes to the SHIELD RCP seals to fully support seal performance consistent with Reference 2. Final design, testing, and qualification are in progress, with full involvement from utility customers. Westinghouse is expected to provide a white paper in February 2014 and Topical Report in March 2014 on the basis for crediting the low leakage seals to the NRC. These documents will be reviewed by the NRC for endorsement.
Attachment to TXX-14023 Page 2 of 2 Although Luminant Power remains confident that the SHIELD RCP seal design issues will be resolved to allow full credit in the FLEX strategies, there is uncertainty regarding the timing of this resolution.
Based on this timeline, Luminant Power is requesting a schedule relaxation of one refueling cycle for implementation of the mitigation strategies for CPNPP Unit 1. The extension would provide additional time to obtain NRC acceptance of the new RCP seals, and for Lunmnant Power to safely plan, schedule and install the new seals at CPNPP Unit 1. Luminant Power will continue to report on the status of all design and modification activities as part of the six month update process.
An extension of one additional refueling cycle for CPNPP Unit 1 is hereby requested, which would move the implementation date from the fall of 2014 to completion of the eighteenth Unit 1 refueling outage in the spring of 2016 (currently targeted for April 2016). The requested relaxation of the CPNPP Unit 1 schedule does not exceed the December 31, 2016 deadline. The schedule for CPNPP Unit 2 implementation would remain unchanged as the completion of the fifteenth Unit 2 refueling outage in the fall of 2015.
Conclusion As described above, compliance with the current NRC Order EA-12-049 schedule requirement for full completion of implementation of mitigation strategies would result in hardship or unusual difficulty without a compensating increase in the level of safety. Therefore, in accordance with the provisions of Section IV of the Order, Luminant Power requests relaxation of the requirement described in Section IV.A.2, as explained above.
References:
- 1. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events dated March 12, 2012
- 2. Luminant Generation Company LLC's Letter TXX-13030, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation strategies for Beyond-Design-Basis External events (Order Number EA-12-049), dated February 28, 2013