MONTHYEARPLA-5120, Forwards Change J to SSES Security Training & Qualification Plan.Without Encl1999-10-22022 October 1999 Forwards Change J to SSES Security Training & Qualification Plan.Without Encl ML18040B2951999-09-0808 September 1999 Requests Info Re Any NRC or Susquehanna Documented Concerns with MSIV Reliability Prior to Plant Trip & Assurance to Public That NRC Able to Detect Mgt Problems Early PLA-5094, Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl1999-08-24024 August 1999 Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl ML18040A9741999-07-0808 July 1999 Forwards Rev 30 to SSES Emergency Plan, Adding EAL to Account for Potential Conditions Associated with Dry Cask Storage Sys Being Installed at Plant ML20207G5051999-06-0707 June 1999 Informs That NRC Office of NRR Reorganized Effective 990328.As Part of Reorganization,Divison of Licensing Project Management Created PLA-5072, Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.211999-06-0404 June 1999 Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.21 ML18040A9731999-05-24024 May 1999 Submits Response to RAI Re Exemption from Biennial Exercise Schedule.Changing of Drill Date Will Not Reduce Level of Emergency Preparedness at Plant ML20195B2181999-05-20020 May 1999 Forwards Proprietary Decommissioning Status Rept for 10% Interest in Sses,Units 1 & 2.Proprietary Info Withheld,Per 10CFR2.790 ML18040B2901999-04-30030 April 1999 Forwards Summary Rept of Safety Evaluations Approved During Period from 961024-981029,per 10CFR50.59(b).Format of Rept, Listed PLA-5041, Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.7901999-03-29029 March 1999 Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.790 ML18040A9691999-03-12012 March 1999 Forwards Revised Proposed Amend 227 to License NPF-14, Proposing Changes to ANFB-10 Critical Power Correlation & MCPR Safety Limits ML17164A9891999-03-12012 March 1999 Informs That Util 990312 Ltr (PLA-5040) Submitted to NRC, Missing Encl C.Requests to Replace Package in Entirety with Encl ML18040A9721999-03-11011 March 1999 Requests That Date for full-participation SSES Exercise, Scheduled for Week of 991115,be Changed Due to FEMA Region III Scheduling Conflicts.Fema Requests That Exercise Date Be Changed to Week of 001031 PLA-4852, Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901999-02-18018 February 1999 Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 ML20203G5821999-02-17017 February 1999 Second Final Response to FOIA Request for Documents. Documents Listed in App C Being Released in Entirety. Documents Listed in App D Being Withheld in Part (Ref FOIA Exemption 5) ML20202F4761999-01-29029 January 1999 First Partial Response to FOIA Request for Documents.Records in App a Encl & Being Released in Entirety.App B Records Being Withheld in Part (Ref FOIA Exemption 7C) ML18040A9671999-01-29029 January 1999 Notifies That Util Implemented Severe Accident Mgt Strategy in Accordance with Ltr Dtd 950327.Emegency Plan Revs Which Were Required to Implement Strategy Were Submitted by Ltr Dtd 981125 ML18040A9681999-01-29029 January 1999 Requests Exemption from Requirements of 10CFR50 App E,Items IVF.2.b & C,To Allowed to Reschedule Federally Observed Full Participation Emergency Exercise for SSES from Wk of 991115 to Wk of 001031 ML18040A9651999-01-12012 January 1999 Submits Addl Info Re Proposed Amend 184 to License NPF-22 for ANFB-10 Critical Power Correlation & MCPR Safety Limits ML18030A1021998-12-16016 December 1998 Forwards Tables as Requested During 981202 Telcon Re Proposed Amend 184,dtd 980804,re ANFB-10 Critical Power Correlation & MCPR Safety Limits.Tables Provide Roadmap Identifying Applicability of References to TSs ML18030A4331998-11-25025 November 1998 Forwards Rev 29 to SSES Emergecny Plan.Changes Has Been Made Without Commission Approval as It Does Not Decrease Effectiveness of Plan & Plan as Changed Continues to Satisfy Applicable Requirements of App E to 10CFR50 ML20195J9101998-11-18018 November 1998 Forwards Notice of Withdrawal of Application for Amends to Facility Operating Licenses (Notice).Notice Has Been Filed with Ofc of Fr.Amends Would Have Revised TS to Eliminate HPCI Pump auto-transfer on High Suppression Pool Level ML20155F7201998-11-0303 November 1998 Final Response to FOIA Request for Documents.Documents Listed in App B Being Encl & Being Released in Entirety. Documents Listed in App C Being Withheld in Part (Ref Exemption 7C) ML18026A2941998-10-19019 October 1998 Forwards SSES ISI Outage Summary Rept for Unit 1 Tenth Refueling & Insp Outage ML18030A4321998-10-12012 October 1998 Forwards Rev 28 to SSES Emergency Plan, IAW Requirements of 10CFR50.54q.Change Is Summarized PLA-4993, Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.211998-10-12012 October 1998 Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.21 ML18030A1001998-10-12012 October 1998 Forwards Rev 27 to SSES Emergency Plan. Changes Become Effective Upon Implementation of Improved Tech Specs ML18030A4311998-09-29029 September 1998 Forwards Rev 27 & 28 to SSES Emergency Plan ML20151W4951998-09-10010 September 1998 Informs That as Part of NRC Probabilistic Risk Assessment Implementation Plan,Commission Assigned Two Senior Reactor Analysts (Sras) to Each Regional Ofc.T Shedlosky & J Trapp Has Been Assigned SRAs for Region I IR 05000387/19980081998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change is Approved ML18030A0991998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change Is Approved ML18026A4961998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations IR 05000387/19980031998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations ML20202F5501998-07-17017 July 1998 Responds to PP&L Corp Auditing Repts 739459-97,739459-1-97 & 739459-2-98 Re SSES Investigations Into Missed Alarm Tests ML20236P9451998-07-15015 July 1998 Forwards Emergency Response Data Sys Implementation Documents Including Data Point Library Updates for Oconee (Number 255),Dresden (Number 257) & Susquehanna (Number 258) ML18030A4291998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved TS of NUREG-1433.Implementation of Proposed Amend Is Predicted on NRC Issuance of Amends & Proposed to Not Exceed 90 Days from Date of Amend Issue ML18017A2181998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved Tech Specs of NUREG 1433.Implementation of Proposed Amend Is Predicated on NRC Issuance of Amends & Is Proposed to Not Exceed 90 Days from Date of Amend Issuance ML18026A2901998-06-0909 June 1998 Forwards Rev 26 to Emergency Plan IAW 10CFR50.54q.Summary of Changes Listed ML18026A2891998-05-22022 May 1998 Submits Withdrawal of Expedited Review/Approval of Tech Specs/Bases 3/4.3.7.11 & 3/4.11.2.6 & Response to Request for Addl Info Re Offgas Sys Mods ML18026A4941998-05-12012 May 1998 Responds to NRC Request to Resubmit Proposal to Change TS for Plant,Units 1 & 2,to Support Implementation of Improved TS & to Implement Provisions of GL 86-10 Re Relocation of Plant'S Fire Protection Program from TS to Another Document ML20202H1331998-04-16016 April 1998 Partially Deleted Ltr Re Concerns Raised to NRC Concerning PP&L Susquehanna Facility NUREG-0619, Informs That Staff Finds PP&L 980330 Request for Relief from Requirements of Section 4.3 of NUREG-0619,exams of Feedwater Nozzle Bore & Inner Radius for Another Operating Cycle to Be Acceptable1998-04-15015 April 1998 Informs That Staff Finds PP&L 980330 Request for Relief from Requirements of Section 4.3 of NUREG-0619,exams of Feedwater Nozzle Bore & Inner Radius for Another Operating Cycle to Be Acceptable ML20216B6811998-04-0101 April 1998 First Partial Response to FOIA Request for Documents. Forwards Documents Listed in App a Being Released in Entirety ML17159A2341998-03-30030 March 1998 Forwards LER 97-007-01,per 10CFR50.73(a)(2)(i)(B).Revised LER Submitted to Modify Previous Position W/Regards to Entry Into TS 3.0.3 for Event PLA-4865, Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901998-03-11011 March 1998 Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 ML17159A1781998-03-0202 March 1998 Forwards Proposed Amends 203 & 161 to License NPF-14 & NPF-22,revising Tech Specs to Be Consistent w/NUREG-1433,rev 1, Std Tech Specs for GE Plants,Bwr 4. PLA-4856, Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl1998-03-0202 March 1998 Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl PLA-4854, Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 9802131998-02-27027 February 1998 Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 980213 ML20203M5071998-02-26026 February 1998 Final Response to FOIA Request for Documents.Records in App a Being Placed in PDR & Encl.Records in App B Partially Withheld (Ref FOIA Exemption 6) ML20203B5931998-02-23023 February 1998 Ack Receipt of & Wire in Amount of $55,000 in Payment for Civil Penatly Proposed by NRC Ltr . Corrective Actions Will Be Examined During Future Inspections 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARPLA-5120, Forwards Change J to SSES Security Training & Qualification Plan.Without Encl1999-10-22022 October 1999 Forwards Change J to SSES Security Training & Qualification Plan.Without Encl ML18040B2951999-09-0808 September 1999 Requests Info Re Any NRC or Susquehanna Documented Concerns with MSIV Reliability Prior to Plant Trip & Assurance to Public That NRC Able to Detect Mgt Problems Early PLA-5094, Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl1999-08-24024 August 1999 Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl ML18040A9741999-07-0808 July 1999 Forwards Rev 30 to SSES Emergency Plan, Adding EAL to Account for Potential Conditions Associated with Dry Cask Storage Sys Being Installed at Plant PLA-5072, Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.211999-06-0404 June 1999 Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.21 ML18040A9731999-05-24024 May 1999 Submits Response to RAI Re Exemption from Biennial Exercise Schedule.Changing of Drill Date Will Not Reduce Level of Emergency Preparedness at Plant ML20195B2181999-05-20020 May 1999 Forwards Proprietary Decommissioning Status Rept for 10% Interest in Sses,Units 1 & 2.Proprietary Info Withheld,Per 10CFR2.790 ML18040B2901999-04-30030 April 1999 Forwards Summary Rept of Safety Evaluations Approved During Period from 961024-981029,per 10CFR50.59(b).Format of Rept, Listed PLA-5041, Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.7901999-03-29029 March 1999 Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.790 ML17164A9891999-03-12012 March 1999 Informs That Util 990312 Ltr (PLA-5040) Submitted to NRC, Missing Encl C.Requests to Replace Package in Entirety with Encl ML18040A9691999-03-12012 March 1999 Forwards Revised Proposed Amend 227 to License NPF-14, Proposing Changes to ANFB-10 Critical Power Correlation & MCPR Safety Limits ML18040A9721999-03-11011 March 1999 Requests That Date for full-participation SSES Exercise, Scheduled for Week of 991115,be Changed Due to FEMA Region III Scheduling Conflicts.Fema Requests That Exercise Date Be Changed to Week of 001031 PLA-4852, Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901999-02-18018 February 1999 Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 ML18040A9681999-01-29029 January 1999 Requests Exemption from Requirements of 10CFR50 App E,Items IVF.2.b & C,To Allowed to Reschedule Federally Observed Full Participation Emergency Exercise for SSES from Wk of 991115 to Wk of 001031 ML18040A9671999-01-29029 January 1999 Notifies That Util Implemented Severe Accident Mgt Strategy in Accordance with Ltr Dtd 950327.Emegency Plan Revs Which Were Required to Implement Strategy Were Submitted by Ltr Dtd 981125 ML18040A9651999-01-12012 January 1999 Submits Addl Info Re Proposed Amend 184 to License NPF-22 for ANFB-10 Critical Power Correlation & MCPR Safety Limits ML18030A1021998-12-16016 December 1998 Forwards Tables as Requested During 981202 Telcon Re Proposed Amend 184,dtd 980804,re ANFB-10 Critical Power Correlation & MCPR Safety Limits.Tables Provide Roadmap Identifying Applicability of References to TSs ML18030A4331998-11-25025 November 1998 Forwards Rev 29 to SSES Emergecny Plan.Changes Has Been Made Without Commission Approval as It Does Not Decrease Effectiveness of Plan & Plan as Changed Continues to Satisfy Applicable Requirements of App E to 10CFR50 ML18026A2941998-10-19019 October 1998 Forwards SSES ISI Outage Summary Rept for Unit 1 Tenth Refueling & Insp Outage ML18030A4321998-10-12012 October 1998 Forwards Rev 28 to SSES Emergency Plan, IAW Requirements of 10CFR50.54q.Change Is Summarized ML18030A1001998-10-12012 October 1998 Forwards Rev 27 to SSES Emergency Plan. Changes Become Effective Upon Implementation of Improved Tech Specs PLA-4993, Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.211998-10-12012 October 1998 Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.21 ML18030A4311998-09-29029 September 1998 Forwards Rev 27 & 28 to SSES Emergency Plan ML18030A0991998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change Is Approved IR 05000387/19980081998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change is Approved ML18026A4961998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations IR 05000387/19980031998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations ML18017A2181998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved Tech Specs of NUREG 1433.Implementation of Proposed Amend Is Predicated on NRC Issuance of Amends & Is Proposed to Not Exceed 90 Days from Date of Amend Issuance ML18030A4291998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved TS of NUREG-1433.Implementation of Proposed Amend Is Predicted on NRC Issuance of Amends & Proposed to Not Exceed 90 Days from Date of Amend Issue ML18026A2901998-06-0909 June 1998 Forwards Rev 26 to Emergency Plan IAW 10CFR50.54q.Summary of Changes Listed ML18026A2891998-05-22022 May 1998 Submits Withdrawal of Expedited Review/Approval of Tech Specs/Bases 3/4.3.7.11 & 3/4.11.2.6 & Response to Request for Addl Info Re Offgas Sys Mods ML18026A4941998-05-12012 May 1998 Responds to NRC Request to Resubmit Proposal to Change TS for Plant,Units 1 & 2,to Support Implementation of Improved TS & to Implement Provisions of GL 86-10 Re Relocation of Plant'S Fire Protection Program from TS to Another Document ML17159A2341998-03-30030 March 1998 Forwards LER 97-007-01,per 10CFR50.73(a)(2)(i)(B).Revised LER Submitted to Modify Previous Position W/Regards to Entry Into TS 3.0.3 for Event PLA-4865, Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901998-03-11011 March 1998 Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 PLA-4856, Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl1998-03-0202 March 1998 Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl ML17159A1781998-03-0202 March 1998 Forwards Proposed Amends 203 & 161 to License NPF-14 & NPF-22,revising Tech Specs to Be Consistent w/NUREG-1433,rev 1, Std Tech Specs for GE Plants,Bwr 4. PLA-4854, Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 9802131998-02-27027 February 1998 Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 980213 ML20216B7031998-02-22022 February 1998 Partially Deleted Ltr Requesting Copy of OI Rept on Plant, Unit 2,case 1-96-039 PLA-4851, Provides Info That Was Requested by Cj Anderson on 980213 Re Former Util Employee Concern on Radwaste Control Room Offgas Panel Alarm Testing1998-02-18018 February 1998 Provides Info That Was Requested by Cj Anderson on 980213 Re Former Util Employee Concern on Radwaste Control Room Offgas Panel Alarm Testing ML20203M5791998-02-10010 February 1998 Enters Appeal Due to Lack of Response to FOIA Request 97-473 ML18030A0971998-02-0202 February 1998 Forwards Proprietary Response to RAI Re Proposed License Amend 209 to TS Supporting Cycle 11 Reload.Proprietary Info Withheld,Per 10CFR2.790 ML20203G6071998-01-26026 January 1998 Forwards Redacted Version of Pp&L,Inc Corporate Auditings Interim Rept 739459-97,dtd 971015 & Affidavit Pursuant to 10CFR2.790 Justifying That Redacted Portions Be Withheld from Public Disclosure.Without Rept IR 05000387/19970031998-01-0606 January 1998 Provides Updated Response to Violations Noted in Insp Repts 50-387/97-03 & 50-388/97-03.Corrective Actions:Util Currently Scheduling Issuance of All Procedural Revs by End of First Quarter 1998 ML18017A2931998-01-0606 January 1998 Provides Responses to Improved TS Section 3.8 Per 970324 NRC Rai.Schedule 980628 for Improved TS Implementation. Submittal of Revised Specifications Is Planned for Jan 1998 ML18030A4071998-01-0606 January 1998 Provides Updated Response to Violations Noted in Insp Repts 50-387/97-03 & 50-388/97-03.Corrective Actions:Util Currently Scheduling Issuance of All Procedural Revs by End of First Quarter 1998 PLA-4828, Expresses Appreciation for Support Received by Former Project Manager C Poslusny1997-12-29029 December 1997 Expresses Appreciation for Support Received by Former Project Manager C Poslusny IR 05000387/19970041997-12-22022 December 1997 Resolves Commitments Made in Response to NOV Issued As Part of NRC Insp Repts 50-387/97-04 & 50-388/97-04 Dtd 970805. Proposed FSAR QA Program Description Changes,Reason for Changes & Basis Included for Approval ML18026A4901997-12-22022 December 1997 Resolves Commitments Made in Response to NOV Issued as Part of NRC Insp Repts 50-387/97-04 & 50-388/97-04 Dtd 970805. Proposed FSAR QA Program Description Changes,Reason for Changes & Basis Included for Approval ML20203M5741997-12-0505 December 1997 FOIA Request for Copy of Latest OI Rept on Susquehanna Ses Including All Exhibits & for Any Other Communication Between NRC & Susquehanna Ses/Pp&L PLA-4818, Forwards Redacted Version of Pp&L,Inc Corporate Auditings Rept 739459-1-97,dtd 971201 & Affidavit Pursuant to 10CFR2.790 Justifying That Redacted Portions Be Withheld from Public Disclosure.Without Rept1997-12-0404 December 1997 Forwards Redacted Version of Pp&L,Inc Corporate Auditings Rept 739459-1-97,dtd 971201 & Affidavit Pursuant to 10CFR2.790 Justifying That Redacted Portions Be Withheld from Public Disclosure.Without Rept 1999-09-08
[Table view] |
Text
Pennsylvania Power & Light Company Two North Ninth Street~Allentown, PA 18101-1179 ~ 610/774-5151 Robert G. Byram Scnlor Vlcc Prcsldcnt-Nuclear 610/774-7502 Fax: 610/774-5019 MAR 03 1997 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop P 1-137 Washington, D. C. 20555 SUSQUEHANNA STEAM ELECTRIC STATION REPLY TO A NOTICE OF VIOLATION (50-387/96-13-01; 50-388/96-13-01 AND 50-387/96-13-02; 50-388/96-13-02) Docket Nos. 50-387 and 50-388 Mis letter provides Pennsylvania Power and Light Company's response to the Notice of Violation (50-387/96-13-01; 50-388/96-13-01 and 50-387/96-13-02; 50-388/96-13-02) contained in NRC Combined Inspection Report 50-387/96-13 and 50-388/96-13 dated January 29, 1997.
The notice requires submittal of a written reply within thirty (30) days of the date of the letter.
However, as discussed with Dr. Walter J. Pasciak of NRC Region I on February 27, 1997, PP&L has been authorized to delay the response until March 7, 1997. We trust that the Commission will find the attached response acceptable.
Ifyou have additional questions, please contact Mr. R. D. Kichline at (610) 774-7705.
Very truly yours, R..B Attac copy: NRC Region I
~
Mr. K, Jenison, NRC Sr. Resident Inspector
~
~
Mr. C. Poslusny, Jr., NRC Sr. Project Manager
Mr. Robert G. Byram Distribution w/cy of Licensee's Response Letter:
Region I Docket Room (with concurrences)
D. Screnci, PAO PUBLIC W. Pasciak, DRP P. Swetland, DRP K. Gallagher, DRP C. Poslusny, NRR Project Manager J. Stolz, PDI-2, NRR W. Dean, OEDO Inspection Program Branch (IPAS)
DOCUMENT NAME: a:reply.sus ~ Copy without attachment/enclosure ~ Copy with attachment/enclosure To receive a copy of this document, Indicate In the box: C E N ~ No copy OFFICE RI:0 P NAME WPasc ak DATE 3/ '97 OFFICIAL RECORD COPY
0 I Yialati{uM (50-387/96-13-01; 50-388/96-1341)
ATTACHMENTTO PLA-4570 Page I of 4 10 CFR 50, Appendix B, Criterion XVI, "Corrective Action," requires licensees to assure that conditions adverse to quality, such as deficiencies and nonconformances, are promptly identified and corrected. In the case of significant conditions adverse to quality, the licensee shall assure that the corrective action is taken to preclude repetition, PP&L Nuclear Department Administrative Procedure NDAP-QA-0702, "Condition Reports,"
Revision l,-provides the program for identification, reporting, evaluating, and correcting conditions adverse to safety or quality.
Contrary to the above, on July 10 and December 9, 1996, PP&L failed to prevent the recurrence of a nonconforming condition created by workers blocking open a high energy line break room boundary door during on-line maintenance. The Condition Report actions for a previous occurrence, on June 19, 1996, did not result in effective corrective actions to prevent the subsequent events.
The violation occurred due to the failure to adequately communicate station guidance that HELB doors must remain closed pending establishment of proper administrative controls on their use. PP&L's response to the events of June 21 and July 10 was focused on the engineering evaluations necessary to establish these controls. These evaluations required engineering calculations of every HELB door at the station, After the July 10 event, action was taken to provide interim controls by retracting existing guidance pending completion of the engineering work; however, this action was not adequately communicated to affected station personnel.
2.
a) Upon identification of the noncompliances on July 10, 1996, and December 9, 1996, the HELB doors were closed, b) Following the event on December 9, 1996, an "all station personnel" letter dated December 12, 1996, was issued. Reading of this letter was required as "stand down" training. Since issuance of that letter, which discussed the control of station doors, no HELB door violations of the station door policy have been identified.
c) The responsibility for station HELB doors has been consolidated under the site engineering organization. This assignment provides a focal point for control of station doors.
ATTACHMENTTO PLA-4570 Page 2 of 4 A broad review of control of all station doors including HELB doors is being performed.
This review has evaluated Condition Report corrective actions associated with blocked open station doors, station policy concerning station doors, and the dissemination of information related to station doors. Recommendations from this review are currently being evaluated.
This review is expected to further enhance our control of HELB doors.
Based on 2.b above, PP&L is in full compliance.
ATTACHMENTTO PLA-4570 Page3 of4 Xhlafigagk (50-387/96-13-02) 50-388/96-13-02)
Technical Specification (TS) 6.8.1 requires that written procedures shall be established and implemented for applicable procedures recommended in Appendix 'A'f R'egulatory Guide 1.33, Revision 2, February 1978. Regulatory Guide 1.33 states that procedures for the control of maintenance, repair and replacement of safety related equipment including, a method for obtaining permission and clearance for operation personnel to work and for logging such work, should be covered by written procedures.
PP&L Nuclear Department Administrative Procedure NDAP-QA-322, Permit and Tag, implements the. tagging process at Susquehanna. Section 5.5. of NDAP-QA-322 defines a foreign potential as an energy source applied within the boundary of a blocked out system.'ection 6.2.3 states that the system operating (SO) representative, system permit supervisor and all sign-ons shall be notified by the person performing a foreign potential test and given their approval prior to application of the foreign potential. It further states that proper documentation shall be noted on the Permit Status Change Log, form NDAP-QA-0322-6.
Contrary to the above, on November 14, 1996, 110 Vac power (a foreign potential) was brought inside the boundaries of permit 1961264, Standby Gas Treatment System 07553A damper actuator, without the proper approvals and documentation.
Rxyurm The violation occurred because the work practice at the time identified a power source as a "foreign potential" only if the potential existed to backfeed power into the circuit. This potential did not exist since the circuit (damper actuator) was de-terminated (power removed).
Therefore, the appropriate authorizations to apply a foreign potential, required by the procedure, were not incorporated into the permit. Upon further review, PP&L has determined that this work practice is inconsistent with the intent of the Permit and Tag procedure. No personnel safety hazard existed as a result of this event.
a) .The concern related to the introduction of a foreign potential into a blocking boundary was identified after the work on the dampers was completed; therefore, no corrective action associated with the work activity was required.
b) Tailboard training was conducted with Electrical Maintenance personnel stressing the importance of identifying the introduction of a foreign potential in a blocking permit and adherence to the permit and tag procedure.
II ATTACHMENTTO PLA-4570 Page 4 of 4 a) Damper actuator work plans/procedures will be revised to annotate that utilization of power sources, other than permanent plant power, is a foreign potential. By annotating the appropriate work plans/procedures, the significance associated with the introduction of a foreign potential into a blocking boundary is enhanced. These work plans/procedures are scheduled to be revised by April 1, 1997.
b) The issues related to this event and the associated corrective actions will be incorporated into Licensed Operator training as part of the Manager of Operations Agenda training.
This training will be completed by June 14, 1997.
I Based on 2.a above PP&L is in full compliance, in that compliance was achieved upon removal of the foreign potential at the completion of the work ac'tivity.