Letter Sequence Approval |
---|
|
|
MONTHYEARML0710101322007-04-0404 April 2007 Response to a Request for Additional Information Re June 5, 2006 License Amendment Request Applicable to Technical Specification 3.8.1, AC Sources-Operating. Project stage: Response to RAI ML0717703102007-06-25025 June 2007 Issuance of Amendments Regarding Emergency Diesel Generator Testing (TAC Nos. MD3217 and MD3218) - Technical Specifications Project stage: Approval ML0715203202007-06-25025 June 2007 Issuance of Amendments Regarding Emergency Diesel Generator Testing (TAC Nos. MD3217 and MD3218) Project stage: Request ML0715203262007-06-25025 June 2007 Issuance of Amendments Regarding Emergency Diesel Generator Testing Project stage: Approval 2007-04-04
[Table View] |
|
---|
Category:Letter
MONTHYEARML24297A6222024-10-11011 October 2024 PCA Letter to NRC Catawba Hurricane Helene IR 05000413/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000413/2024011 and 05000414/2024011 ML24255A8312024-09-23023 September 2024 Project Manager Assignment ML24261B9782024-09-19019 September 2024 Notification of an NRC Fire Protection Team Inspection NRC Inspection Report 05000413-2024010, 05000414-2024010 and Request for Information IR 05000413/20243012024-09-16016 September 2024 Operator Licensing Examination Approval 05000413/2024301 and 05000414/2024301 IR 05000414/20240912024-09-0505 September 2024 Final Significance Determination of a White Finding and Nov and Assessment Followup Letter-NRC Inspection Report 05000414-2024091 IR 05000413/20240052024-08-26026 August 2024 Updated Inspection Plan for Catawba Nuclear Station (Report 05000413/2024005 & 05000414/2024005) ML24235A1542024-08-22022 August 2024 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000413-2024402 and 05000414-2024402) IR 05000413/20240022024-08-0808 August 2024 Integrated Inspection Report 05000413-2024002 and 05000414-2024002 and Apparent Violation IR 05000413/20244032024-08-0101 August 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000413/2024403; 05000414/2024403 ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24178A0552024-06-26026 June 2024 Requalification Program Inspection – Catawba Nuclear Station IR 05000414/20240902024-06-24024 June 2024 NRC Inspection Report 05000414/2024090 and Preliminary White Finding and Apparent Violation ML24170A8632024-06-11011 June 2024 Flowserve June 11, 2024, Part 21 Notification - Redacted Version for Publishing ML24149A1772024-05-28028 May 2024 NRC Response to Duke Energy 2025 FOF Schedule Change Request (Catawba and McGuire) ML24144A1162024-05-28028 May 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc IR 05000413/20240012024-05-10010 May 2024 Integrated Inspection Report 05000413/2024001 and 05000414/2024001 and Apparent Violation ML24095A1072024-04-0808 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report (C1R27) ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) IR 05000413/20230062024-02-28028 February 2024 Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - (NRC Inspection Report 05000413/2023006 and 05000414/2023006) IR 05000413/20230042024-02-0202 February 2024 – Integrated Inspection Report 05000413-2023004 and 05000414-2023004 ML24005A2512024-01-26026 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230102023-10-11011 October 2023 NRC Inspection Report 05000413/2023010 and 05000414/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000413/20230052023-08-25025 August 2023 Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) ML23233A1692023-08-17017 August 2023 EN 56683 - Curtiss Wright, Interim Notification Report for PotentialPurt2l IR 05000413/20230022023-07-25025 July 2023 Integrated Inspection Report 05000413/2023002 and 05000414/2023002 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined IR 05000413/20230012023-05-0505 May 2023 Integrated Inspection Report 05000413/2023001 and 05000414/2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000413/20230112023-04-25025 April 2023 Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 ML23107A2542023-04-14014 April 2023 301 Examination Report Letter and Report (Merged) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000413/20234012023-03-0101 March 2023 Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 IR 05000413/20220062023-03-0101 March 2023 Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) IR 05000413/20233012023-02-17017 February 2023 Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 IR 05000413/20220042023-01-31031 January 2023 Integrated Inspection Report 05000413/2022004 and 05000414/2022004 IR 05000413/20220112022-12-15015 December 2022 Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations IR 05000413/20224032022-11-17017 November 2022 Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22319A0942022-11-10010 November 2022 EN 56219 - Flowserve. 10 CFR Part 21 Report 38878-8 Solenoid Valve at Duke, Catawba Flowserve Evaluation 105 IR 05000414/20220032022-10-31031 October 2022 Integrated Inspection Report 05000414/2022003 and 05000414/2022003 IR 05000413/20224022022-10-28028 October 2022 Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 2024-09-05
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24192A3492024-07-10010 July 2024 Acceptance of Requested Licensing Action License Amendment Application to Revise Technical Specification 3.4.3, RCS Pressure and Temperature Limits ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22276A2492022-10-25025 October 2022 Completion of License Renewal Commitment No. 10, Aging Management of Environmentally Assisted Fatigue ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 ML21224A1012021-10-0707 October 2021 Issuance of Amendments to Revise the Technical Specification for Engineered Safety Feature Actuation System Instrumentation ML21155A2132021-08-26026 August 2021 Plant ML21131A0262021-06-23023 June 2021 Issuance of Amendments to Change Technical Specification 3.8.1, to Reduce Emergency Diesel Generator Maximum Voltage ML20258A2712020-09-21021 September 2020 Correction Letter to Amendment Nos. 301, 329, 307, 303, 178, 317, 296, 416, 418, 417, and 268 ML20083F9272020-08-12012 August 2020 Issuance of Amendments to Relocate the Unit/Facility/Plant Staff Qualification Requirements to the Duke Energy Quality Assurance Program Description ML20174A0452020-08-0404 August 2020 Issuance of Amendment No. 306 to Revise Technical Specification 3.4.3, RCS (Reactor Coolant System) Pressure and Temperature (P/T) Limits ML19296D1192020-01-31031 January 2020 Issuance of Amendment Nos. 305 and 301 to Revise Technical Specification 3.0, Surveillance Requirement (SR) Applicability ML19212A6552019-08-27027 August 2019 Issuance of Amendment Nos. 304 and 300 to Technical Specification 3.8.1, AC Sources - Operating ML19121A5512019-06-17017 June 2019 Issuance of Amendments Related to the Removal of Containment Valve Injection Water System Supply from Specified Containment Isolation Valves ML19050A2972019-04-18018 April 2019 McGuire Nuclear Station, Units 1 and 2, Shearon Harris Nuclear Power Plant, Unit 1, H B. Robinson Steam Electric Plant, Unit 2 - Issuance of Amendments Regarding Removal ML18275A2782018-11-28028 November 2018 Issuance of Amendments Related to the Nuclear Service Water System New Condition for Single Pond Return Header Configuration ML18172A1722018-08-15015 August 2018 Issuance of Amendments to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application ML17296A2082018-01-0404 January 2018 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-197-A, Revision 2 (CAC Nos. MF8971 & MF8972, EPID L-2016-LLA-0026) ML17254A1442017-10-23023 October 2017 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-352-A, Revision 1 (CAC Nos. MF8969 and MF8970; EPID L-2017-LLA-0031) ML17257A2972017-10-23023 October 2017 Issuance of Amendment Nos. 295 and 291, Adoption of TSTF-340-A, Revision 3, Allow 7-Day Completion Time for a Turbine-Driven AFW Pump Inoperable (CAC Nos. MF8979 and MF8980; EPID L-2017-LLA-0043) ML17261B2902017-10-23023 October 2017 Issuance of Amendment Nos. 296 and 292, Adopt TSTF-142-A, Revision 0, Increase the Completion Time When the Core Reactivity Balance Is Not within Limit (CAC Nos. MF8962 and MF8963); EPID L-2017-LLA-0024 ML17249A1352017-09-29029 September 2017 Issuance of Amendments Adopting Technical Specifications Task Force Travelers TSTF-349-A, Revision 1, TSTF-361-A, Revision 2, and TSTF-438-A, Revision 0 ML17188A3872017-08-21021 August 2017 Issuance of Amendments Regarding Application to Consolidate Emergency Operations Facilities and Associated Emergency Plan Changes (CAC Nos. MF7650 Through MF7660) ML17172A4282017-07-26026 July 2017 Issuance of Amendments Adopting Technical Specification Task Force Traveler TSTF-315-A, Revision 0 ML17144A0342017-06-19019 June 2017 Correction Letter to Amendment Nos. 287 and 283 National Fire Protection Association Standard NFPA 805 ML17055A6472017-05-0808 May 2017 Brunswick, Catawba, McGuire, Shearon Harris, and H. B. Robinson - Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-522, Revision 0 (CAC Nos. MF8422, MF8423, MF8424, MF8425, MF8426, MF8427, MF8428, and MF8429) ML17066A3742017-04-26026 April 2017 Issuance of Amendments Re. Application to Revise TSs to Adopt TSTF-427, Rev. 2, Using the Consolidated Line Item Improvement Process (CAC Nos. MF8039 Through MF8049) ML16137A3082017-02-0808 February 2017 Issuance of Amendments Regarding National Fire Protection Association Standard NFPA 805 ML16229A1132016-09-12012 September 2016 Issuance of Amendments Regarding Extension of the Containment Integrated Leak Rate Test Intervals ML16159A3362016-07-19019 July 2016 Issuance of Amendments Regarding Request to Use an Alternate Fission Gas Gap Release Fraction (CAC Nos. MF6480 Through MF6486) ML16174A0722016-06-27027 June 2016 Correction to License Pages Issuance of Amendments Regarding Adoption of TSTF-523 (Cac Nos. MF6413 Through MF6422) ML16105A3262016-06-21021 June 2016 Issuance of Amendments Regarding Use of Optimized Zirlo ML16124A6942016-06-0202 June 2016 Issuance of Amendments Regarding Changes to Technical Specification 3.4.1, RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits ML16081A3332016-04-29029 April 2016 Issuance of Amendments Regarding Measurement Uncertainty Recapture Power Uprate ML16085A1132016-04-29029 April 2016 1 & 2; Shearon Harris Nuclear Power Plant 1; Catawba Nuclear Station 1 & 2; Mcguire Nuclear Station 1 & 2; and Oconee Nuclear Station 1, 2, & 3: Issuance of Amendments Regarding Adoption of TSTF-523 (CAC Nos. MF6413-MF6422) ML16075A3012016-04-26026 April 2016 Issuance of Amendments Regarding the Revision of the Steam Generator Technical Specifications to Reflect the Adoption of TSTF-510(CAC Nos. MF6139,MF6140,MF6141,MF6142,MF6143,MF6144. ML16082A0382016-04-18018 April 2016 Issuance of License Amendment Regarding Emergency Action Level Scheme Change ML16067A2292016-04-0808 April 2016 Issuance of Amendments Regarding Removal of Obsolete Technical Specification Requirements ML15320A3332015-12-18018 December 2015 Issuance of Amendments Regarding Non-Conservative Technical Specifications Allowable Value ML15133A4532015-06-11011 June 2015 McGuire Nuclear Station, Oconee Nuclear Station - Issuance of Amendments Regarding Changes to Cyber Security Plan Implementation Schedule Milestone 8 ML15063A2712015-04-14014 April 2015 Issuance of Amendments Technical Specification 3.1.3, Moderator Temperature Coefficient and TS 5.6.5, Core Operating Limits Report. ML15027A3662015-03-25025 March 2015 Issuance of Amendments DPC-NE-3001-P, Multidimensional Reactor Transients and Safety Analysis Physics Parameters Methodology ML15002A3242015-02-12012 February 2015 McGuire Nuclear Station, and Oconee Nuclear Station - Issuance of Amendments Regarding Changes to Organization, Unit Staff Responsibility, Unit Staff Qualifications, Programs and Manuals, and High Radiation Areas ML14056A2172014-02-27027 February 2014 Issuance of Amendments Regarding Exigent License Amendment Request to Revise Technical Specification 3.3.4, Remote Shutdown System (TAC MF3473&74) ML13169A1392013-08-0909 August 2013 Issuance of Amendments Regarding Technical Specifications Changes for Nuclear Service Water System 2024-07-10
[Table view] Category:Safety Evaluation
MONTHYEARML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 ML24017A0652024-03-0808 March 2024 Issuance of Amendment Nos. 319 and 315 to Technical Specification 3.7.11, Control Room Area Chill Water System (Cracws) ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition ML22213A2532022-08-31031 August 2022 Authorization and Safety Evaluation for Alternative Request RA-21-0144 to Use Reactor Vessel Head Penetration Embedded Flaw Repair Method ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22010A2812022-03-0404 March 2022 Issuance of Amendments to Adopt TSTF-577, Rev. 1 Revised Frequencies for Steam Generator Tube Inspections (EPID L-2021-LLA-0161 ML22007A3452022-01-11011 January 2022 Proposed Alternative to Use the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-885 ML21266A0112021-10-0505 October 2021 Staff Evaluation Related to Aging Management Program and Inspection Plan of Reactor Vessel Internals Per MRP-227, Revision 1-A ML21253A0822021-09-20020 September 2021 Proposed Alternative Request RA-21-0145 to Use Reactor Vessel Head Penetration Embedded Flaw Repair Method ML21155A2132021-08-26026 August 2021 Plant ML21131A0262021-06-23023 June 2021 Issuance of Amendments to Change Technical Specification 3.8.1, to Reduce Emergency Diesel Generator Maximum Voltage ML21113A0132021-05-0606 May 2021 Request for Use of a Later Edition of ASME Boiler and Pressure Vessel Code, Section XI for Repair and Replacement Activities ML21029A3352021-02-16016 February 2021 Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20300A2062020-11-0909 November 2020 Duke Fleet - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML20258A2712020-09-21021 September 2020 Correction Letter to Amendment Nos. 301, 329, 307, 303, 178, 317, 296, 416, 418, 417, and 268 ML20083F9272020-08-12012 August 2020 Issuance of Amendments to Relocate the Unit/Facility/Plant Staff Qualification Requirements to the Duke Energy Quality Assurance Program Description ML20174A0452020-08-0404 August 2020 Issuance of Amendment No. 306 to Revise Technical Specification 3.4.3, RCS (Reactor Coolant System) Pressure and Temperature (P/T) Limits ML19296D1192020-01-31031 January 2020 Issuance of Amendment Nos. 305 and 301 to Revise Technical Specification 3.0, Surveillance Requirement (SR) Applicability ML19254A6202019-09-17017 September 2019 Duke Energy Fleet (Brunswick, Catawba, Robinson, McGuire, Oconee, and Shearon Harris) - Alternative to Use Encoded Phased Array Ultrasonic Examination in Lieu of Radiography ML19212A6552019-08-27027 August 2019 Issuance of Amendment Nos. 304 and 300 to Technical Specification 3.8.1, AC Sources - Operating ML19191A0612019-07-15015 July 2019 Review of the Steam Generator Tube Inservice Inspection Report for the Fall 2018 Refueling Outage 24 ML19058A6322019-07-0101 July 2019 Issuance of Amendments to Revise Emergency Action Level Schemes to Incorporate Clarifications Provided by Emergency Preparedness FAQs ML19128A3262019-06-20020 June 2019 Alternative to Depth Sizing Qualification Examination of Welds ML19121A5512019-06-17017 June 2019 Issuance of Amendments Related to the Removal of Containment Valve Injection Water System Supply from Specified Containment Isolation Valves ML19050A2972019-04-18018 April 2019 McGuire Nuclear Station, Units 1 and 2, Shearon Harris Nuclear Power Plant, Unit 1, H B. Robinson Steam Electric Plant, Unit 2 - Issuance of Amendments Regarding Removal ML18275A2782018-11-28028 November 2018 Issuance of Amendments Related to the Nuclear Service Water System New Condition for Single Pond Return Header Configuration ML18172A1722018-08-15015 August 2018 Issuance of Amendments to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application ML18016A1782018-01-24024 January 2018 Request for Relief No. 17-CN-001, Regarding Category B-J Pressure Retaining Welds for the Third 10-Year Inservice Testing Interval (CAC Nos. MF9807 and MF9808; EPID L-2017-LLA-0032) ML17296A2082018-01-0404 January 2018 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-197-A, Revision 2 (CAC Nos. MF8971 & MF8972, EPID L-2016-LLA-0026) ML17331A0862017-12-26026 December 2017 Alternative to Inservice Inspection Regarding Reactor Pressure Vessel Threads ML17254A1442017-10-23023 October 2017 Issuance of Amendments Adopting Technical Specifications Task Force Traveler TSTF-352-A, Revision 1 (CAC Nos. MF8969 and MF8970; EPID L-2017-LLA-0031) ML17261B2902017-10-23023 October 2017 Issuance of Amendment Nos. 296 and 292, Adopt TSTF-142-A, Revision 0, Increase the Completion Time When the Core Reactivity Balance Is Not within Limit (CAC Nos. MF8962 and MF8963); EPID L-2017-LLA-0024 ML17257A2972017-10-23023 October 2017 Issuance of Amendment Nos. 295 and 291, Adoption of TSTF-340-A, Revision 3, Allow 7-Day Completion Time for a Turbine-Driven AFW Pump Inoperable (CAC Nos. MF8979 and MF8980; EPID L-2017-LLA-0043) ML17249A1352017-09-29029 September 2017 Issuance of Amendments Adopting Technical Specifications Task Force Travelers TSTF-349-A, Revision 1, TSTF-361-A, Revision 2, and TSTF-438-A, Revision 0 ML17188A3872017-08-21021 August 2017 Issuance of Amendments Regarding Application to Consolidate Emergency Operations Facilities and Associated Emergency Plan Changes (CAC Nos. MF7650 Through MF7660) ML17172A4282017-07-26026 July 2017 Issuance of Amendments Adopting Technical Specification Task Force Traveler TSTF-315-A, Revision 0 ML17165A4412017-07-21021 July 2017 Issuance of Amendments Adopting Technical Specification Task Force Traveler TSTF-269-A, Revision 2 (CAC Nos. MF8983 and MF8984). 08/10/2017 ML17055A6472017-05-0808 May 2017 Brunswick, Catawba, McGuire, Shearon Harris, and H. B. Robinson - Issuance of Amendments to Revise Technical Specifications to Adopt TSTF-522, Revision 0 (CAC Nos. MF8422, MF8423, MF8424, MF8425, MF8426, MF8427, MF8428, and MF8429) ML17066A3742017-04-26026 April 2017 Issuance of Amendments Re. Application to Revise TSs to Adopt TSTF-427, Rev. 2, Using the Consolidated Line Item Improvement Process (CAC Nos. MF8039 Through MF8049) ML16137A3082017-02-0808 February 2017 Issuance of Amendments Regarding National Fire Protection Association Standard NFPA 805 ML16277A4042016-10-20020 October 2016 Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16208A2832016-08-0808 August 2016 Correction to Issuance of Amendments Regarding Use of Optimized Zirlo ML16159A3362016-07-19019 July 2016 Issuance of Amendments Regarding Request to Use an Alternate Fission Gas Gap Release Fraction (CAC Nos. MF6480 Through MF6486) 2024-07-12
[Table view] |
Text
June 25, 2007
Mr. J. R. Morris Site Vice President Catawba Nuclear Station Duke Power Company LLC
4800 Concord Road York, SC 29745
SUBJECT:
CATAWBA NUCLEAR STATION, UNITS 1 AND 2, ISSUANCE OF AMENDMENTS REGARDING EMERGENCY DIESEL GENERATOR TESTING (TAC NOS. MD3217 AND MD3218)
Dear Mr. Morris:
The Nuclear Regulatory Commission has issued the enclosed Amendment No. 236 to Renewed Facility Operating License NPF-35 and Amendment No. 232 to Renewed Facility Operating License NPF-52 for the Catawba Nuclear Station, Units 1 and 2, respectively. The amendments consist of changes to the Technical Specifications (TSs) in response to your application dated June 5, 2006, as supplemented April 4, 2007.
The amendments revise TS 3.8.1, "AC Sources -
Operating," surveillance requirement (SR) 3.8.1.13. The changes revise the SR 3.8.1.13 and its associated Bases to state that the SR only verifies that non-emergency diesel generator (DG) trips are bypassed. The licensee stated that this change is based upon and consistent with Industry Technical Specification Task Force (TSTF), Standard TS Traveler, TSTF-400-A, Revision 1, "Clarify Surveillance Requirement on Bypass of DG Automatic Trips."
A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included
in the Commission's biweekly Federal Register notice.
Sincerely,
/RA/ John Stang, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-413 and 50-414
Enclosures:
- 1. Amendment No. 236 to NPF-35
- 2. Amendment No. 232 to NPF-52
- 3. Safety Evaluation cc w/encls: See next page June 25, 2007
Mr. J. R. Morris Vice President Catawba Nuclear Station Duke Power Company LLC
4800 Concord Road York, SC 29745
SUBJECT:
CATAWBA NUCLEAR STATION, UNITS 1 AND 2 - ISSUANCE OF AMENDMENTS REGARDING EMERGENCY DIESEL GENERATOR TESTING (TAC NOS. MD3217 AND MD3218)
Dear Mr. Morris:
The Nuclear Regulatory Commission has issued the enclosed Amendment No. 236 to Renewed Facility Operating License NPF-35 and Amendment No. 232 to Renewed Facility Operating License NPF-52 for the Catawba Nuclear Station, Units 1 and 2, respectively. The amendments consist of changes to the Technical Specifications (TSs) in response to your application dated June 5, 2006, as supplemented April 4, 2007.
The amendments revise TS 3.8.1, "AC Sources -
Operating," surveillance requirement (SR) 3.8.1.13. The changes revise the SR 3.8.1.13 and its associated Bases to state that the SR only verifies that non-emergency diesel generator (DG) trips are bypassed. The licensee stated that this change is based upon and consistent with Industry Technical Specification Task Force (TSTF), Standard TS Traveler, TSTF-400-A, Revision 1, "Clarify Surveillance Requirement on Bypass of DG Automatic Trips."
A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included
in the Commission's biweekly Federal Register notice.
Sincerely, /RA/ John Stang, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket Nos. 50-413 and 50-414
Enclosures:
- 1. Amendment No. 236 to NPF-35 2. Amendment No. 232 to NPF-52
- 3. Safety Evaluation
cc w/encls: See next page
DISTRIBUTION: Public RidsAcrsAcnwMailCenter RidsNrrDeEeeb (GWilson) LPL2-1 R/F GHill (4 hard copies) RidsNrrDorlLpl2-1 (EMarinos) RidsNrrDirsItsb (TKobetz) RidsNrrPMJStang (hard copy) RidsRgn2MailCenter (JMoorman) RidsNrrLAMO'Brien (hard copy) RidsNrrDorlDpr RidsOgcRp RidsNrrDeEeeb(APal)
Package No.: ML071520320 Amendment No.: ML071520326 Tech Spec No.: ML *SE transmitted by memo dated NRR-058 OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/EEEB/BC OGC NRR/LPL2-1/BC
NAME JStang:nc MO'Brien GWilson* DRoth EMarinos DATE 6/25/07 6/11/07 05/31/07 6/25/07 6/25/07 OFFICIAL RECORD COPY
Catawba Nuclear Station, Units 1 & 2 Page 1 of 2
cc: Site Vice President Catawba Nulcear Station Duke Power Company, LLC
4800 Concord Road York, SC 29745 Associate General Counsel and Managing Attorney
Duke Energy Carolinas, LLC
526 South Church Street - EC07H Charlotte, North Carolina 28202
Regulatory Compliance Duke Energy Corporation
4800 Concord Road York, South Carolina 29745
North Carolina Municipal Power Agency Number 1 1427 Meadowwood Boulevard P.O. Box 29513 Raleigh, North Carolina 27626
County Manager of York County
York County Courthouse York, South Carolina 29745 Piedmont Municipal Power Agency 121 Village Drive Greer, South Carolina 29651
Assistant Attorney General North Carolina Department of Justice P.O. Box 629 Raleigh, North Carolina 27602
NCEM REP Program Manager 4713 Mail Service Center Raleigh, North Carolina 27699-4713
North Carolina Electric Membership Corp.
P.O. Box 27306 Raleigh, North Carolina 27611
Senior Resident Inspector U.S. Nuclear Regulatory Commission 4830 Concord Road York, South Carolina 29745
Assistant Director Division of Waste Management Bureau of Land and Waste Management
Dept. of Health and Environmental Control
2600 Bull Street Columbia, South Carolina 29201-1708 Manager Nuclear Regulatory Issues
and Industry Affairs Duke Energy Corporation 526 South Church Street Mail Stop EC05P Charlotte, North Carolina 28202
Saluda River Electric P.O. Box 929 Laurens, South Carolina 29360
Vice President Customer Relations and Sales Westinghouse Electric Company 6000 Fairview Road 12th Floor Charlotte, North Carolina 28210
Owners Group (NCEMC)
Duke Energy Corporation 4800 Concord Road York, South Carolina 29745
Senior Counsel
Duke Energy Carolinas, LLC 526 South Church Street - EC07H Charlotte, NC 28202
Catawba Nuclear Station, Units 1 & 2 Page 2 of 2 cc: Division of Radiation Protection NC Dept. of Environment, Health, and Natural Resources 3825 Barrett Drive Raleigh, North Carolina 27609-7721 Group Vice President, Nuclear Generation and Chief Nuclear Officer P.O. Box 1006-EC07H
Charlotte, NC 28201-1006
DUKE POWER COMPANY LLC NORTH CAROLINA ELECTRIC MEMBERSHIP CORPORATION SALUDA RIVER ELECTRIC COOPERATIVE, INC.
DOCKET NO. 50-413 CATAWBA NUCLEAR STATION, UNIT 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE
Amendment No. 236 Renewed License No. NPF-35
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment to the Catawba Nuclear Station, Unit 1 (the facility) Renewed Facility Operating License No. NPF-35 filed by the Duke Power Company LLC, acting for itself, North Carolina Electric Membership Corporation and Saluda River Electric Cooperative, Inc. (licensees), dated June 5, 2006 as supplemented April 4, 2007, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations as set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is hereby amended by page changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-35 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 236, which are attached hereto, are hereby incorporated into this license. Duke Power Company LLC shall operate the facility in accordance with the Technical Specifications.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 30 days of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/ Evangelos C. Marinos, Chief Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to License No. NPF-35 and the Technical Specifications Date of Issuance: June 25, 2007 DUKE POWER COMPANY LLC NORTH CAROLINA MUNICIPAL POWER AGENCY NO. 1
PIEDMONT MUNICIPAL POWER AGENCY
DOCKET NO. 50-414
CATAWBA NUCLEAR STATION, UNIT 2
AMENDMENT TO RENEWED FA CILITY OPERATING LICENSE Amendment No. 232 Renewed License No. NPF-52
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment to the Catawba Nuclear Station, Unit 2 (the facility) Renewed Facility Operating License No. NPF-52 filed by the Duke Power Company LLC, acting for itself, North Carolina Municipal Power Agency No. 1 and Piedmont Municipal Power Agency (licensees), dated June 5, 2006 as supplemented April 4, 2007, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations as set
forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is hereby amended by page changes to the Technical Specifications as indicated in the attachment to this license amendment, and Paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-52 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 232, which are attached hereto, are hereby incorporated into this license. Duke Power Company LLC shall operate the facility in accordance with the Technical Specifications.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 30 days of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/ Evangelos C. Marinos, Chief Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to License No. NPF-52 and the Technical Specifications Date of Issuance: June 25, 2007 ATTACHMENT TO LICENSE AMENDMENT NO. 236 RENEWED FACILITY OPERATING LICENSE NO. NPF-35
DOCKET NO. 50-413
AND LICENSE AMENDMENT NO. 232
RENEWED FACILITY OPERATING LICENSE NO. NPF-52
DOCKET NO. 50-414
Replace the following pages of the Renewed Facility Operating Licenses and the Appendix A Technical Specifications (TSs) with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License Pages License Pages NPF-35 page 4 NPF-35 page 4 NPF-52 page 4 NPF-52 page 4 TSs TSs 3.8.1-11 3.8.1-11
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 236 TO RENEWED FACILITY OPERATING LICENSE NPF-35 AND AMENDMENT NO. 232 TO RENEWED FACILITY OPERATING LICENSE NPF-52 DUKE POWER COMPANY LLC
CATAWBA NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS. 50-413 AND 50-414
1.0 INTRODUCTION
By application dated June 5, 2006 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML061640346), as supplemented by letter dated April 4, 2007 (ADAMS Accession No. ML071010132), Duke Power Company LLC (Duke, the licensee),
requested changes to the Technical Specifications (TSs) for the Catawba Nuclear Station, Units 1 and 2 (Catawba 1 and 2). The supplement dated April 4, 2007, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the Nuclear Regulatory Commission (NRC) staff's original proposed no significant hazards consideration determination as published the Federal Register on December 5, 2006 (71 FR 70555).
The proposed changes would revise TS 3.8.1, "AC Sources - Operating," surveillance requirement (SR) 3.8.1.13. The proposed changes would revise the SR 3.8.1.13 and its associated Bases to state that the SR only verifies that non-emergency diesel generator (DG) trips are bypassed. The licensee stated that this change is based upon and consistent with Industry Technical Specification Task Force (TSTF), Standard TS Traveler, TSTF-400-A, Revision 1, "Clarify Surveillance Requirement on Bypass of DG Automatic Trips."
2.0 REGULATORY EVALUATION
The regulatory requirements which the NRC staff applied in its review of the application include:
Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Appendix A, General Design Criteria (GDC) 17 requires, in part, that nuclear power plants have an onsite and offsite electric power system to permit the functioning of structures, systems and components important to safety. The onsite system is required to have sufficient independence, redundancy and testability to perform its safety function, assuming a single failure, and the offsite system is required to be supplied by two independent circuits. In addition, these criteria require 3 provisions to minimize the probability of losing electric power from the remaining electric power supplies as the result of loss of power from the unit, the offsite transmission network, or the onsite power supplies.
GDC-18, "Inspection and testing of electric power systems," requires that electric power systems that are important to safety must be designed to permit appropriate periodic inspection and testing.
Section 50.36, "Technical Specifications," of Part 50 requires TS with Limiting Condition of Operations (LCOs) and SRs for equipment that is required for safe operation of the facility.
3.0 TECHNICAL EVALUATION
Currently, SR 3.8.1.13 reads:
"Verify each DG's automatic trips are bypassed on actual or simulated loss of voltage signal on the emergency bus concurrent with an actual or simulated engineered safety feature (ESF)
actuation signal except:
- a. Engine overspeed;
- b. Generator differential current; c. Low -low lube oil pressure; and d. Voltage-controlled overcurrent relay scheme."
The licensee proposed to change SR 3.8.1.13 as follows:
"Verify each DG's non-emergency automatic trips are bypassed on actual or simulated loss of voltage signal on the emergency bus concurrent with an actual or simulated engineered safety feature ESF actuation signal."
The licensee stated that the current SR 3.8.1.13 and Bases imply that two tests are required: 1) verification that non-emergency trips are bypassed, and 2) verification that emergency trips are not bypassed. This is not correct and has led to confusion at nuclear power plants implementing the SR. Only the first verification is the correct intent of this SR. In order to address this confusion the nuclear industry's TSTF proposed TSTF-400-A, Revision 1, "Clarify Surveillance Requirement on Bypass of DG Automatic trips." The NRC approved TSTF-400-A, Revision 1 by letter and a safety evaluation report dated November 13, 2004.
The NRC staff finds that Branch Technical Positi on (BTP) Instrumentation and Control System Branch (ICSB) -17, "Diesel Generator Protecti ve Trip Circuit Bypasses," was replaced in 1981 by a position established in Regulatory Guide (RG) 1.9, "Selection, Design, Qualification, and Testing of Emergency Diesel Generator Units Used as Class 1E Onsite Electrical Power Systems at Nuclear Power Plants." Section 2.2.12 of RG 1.9, Rev. 3, only requires verification that the non-critical trips (e.g., jacket water temperature high, engine bearing temperature high) are bypassed and does not require verification that the critical trips (e.g., engine over-speed, generator differential current) are not bypassed. This test is intended to verify that the bypass function is OPERABLE so that a spurious actuation of a non-critical trip does not trip the DG during an emergency. Testing to verify that critical DG trips are not bypassed is not required to 4 satisfy the requirements of 10 CFR 50.36(c)(3).
The NRC staff was concerned about removing testing of DG critical trips. Generic Letter (GL) 96-01 requires that all portions of the logic circuitry, including the parallel logic, interlocks, bypasses and inhibit circuits are adequately covered in the surveillance procedures to fulfill the requirements. In a request for additional info rmation, the NRC staff asked the licensee to discuss how the NRC staff can be assured that these emergency trips will function (trips DG when the condition is present in order to avert substantial damage to the DG unit and do not trip when condition is not present) unless these trips are periodically tested. In response to the above concern, the April 4, 2007, supplement stated that currently, DG emergency automatic trips are tested periodically per the station periodic maintenance program. The licensee provided details regarding testing and calibration of emergency trips for Catawba 1 and
- 2. The NRC staff finds that DG emergency automatic trips are tested at least once every 18 months to ensure proper functioning. The licensee committed to add the statement: " DG emergency automatic trips will be tested periodically per the station periodic maintenance program" to the end of the first paragraph of the revised TS Bases SR 3.8.1.13 for Catawba and McGuire. Based on the above, the NRC staff's concern is resolved.
The licensee is making an editorial deviation from TSTF-400-A in that this amendment request uses the term "emergency" trips and "non-emergency" trips in lieu of "critical" trips and "non-critical" trips for Catawba 1 and 2. This is being done for human factors considerations because both stations use these terms in operator training and on labeling on the actual DG equipment. The NRC staff finds that this deviation does not affect the technical aspect of this proposed change and, therefore, is acceptable.
4.0
SUMMARY
The NRC staff concludes that the proposed change will have no adverse effect on the availability or operation of the associated equipment and there will have no adverse effect on plant operation. The proposed changes are consistent with the guidance in RG 1.9 and NUREG 1434. The staff also concludes that the proposed changes to the SRs do not affect Catawba 1 and 2 compliance with the requirements of GDC 17 and GDC 18 as described in the licensee's Updated Final Safety Analysis and therefore, the proposed change is acceptable.
5.0 STATE CONSULTATION
In accordance with the Commission's regulations, the South Carolina State official was notified of the proposed issuance of the amendments. The State official had no comments.
6.0 ENVIRONMENTAL CONSIDERATION
The amendments change surveillance requirements. The NRC staff has determined that the amendments involve no significant increase in the amounts and no significant change in the types of any effluents that may be released offsite and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration, and there has been no public comment on such finding (71 FR 70555). The amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Accordingly, 5 pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
7.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributor: A. Pal
Date: June 25, 2007