MONTHYEARML24295A0362024-10-23023 October 2024 Regulatory Audit Plan in Support of Relief Request No. 71; Resubmittal of Relief Request-30 IR 05000528/20244022024-10-22022 October 2024 Security Baseline Inspection Report 05000528/2024402 and 05000529/2024402 and 05000530/2024402 ML24296B2142024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 02: Alternative Request Allowing Normally Closed Valves with a Safety Function to Close to Be Exercise Tested Once Per Refueling Cycle ML24296B2152024-10-22022 October 2024 Transmittal of Valve Relief Request (VRR) - 03: Alternative Request Allowing Removal of the Lower Acceptance Criteria Threshold from Solenoid-Operated Valves ML24296B2172024-10-18018 October 2024 Submittal of Unit 1 Core Operating Limits Report, Revision 34, Unit 2 Core Operating Limits Report, Revision 26, and Unit 3 Core Operating Limits Report, Revision 3 ML24292A2192024-10-18018 October 2024 Core Operating Limits Report Revision 34, 26 and 33 ML24292A0322024-10-17017 October 2024 Th Refueling Outage Steam Generator Tube Inspection Report ML24285A2562024-10-11011 October 2024 License Renewal - Alloy 600 Management Program Plan Response to Request for Additional Information IR 07200044/20244012024-10-0808 October 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200044/2024401 ML24269A1542024-09-27027 September 2024 Summary of Presubmittal Meeting with Arizona Public Service Company to Discuss Proposed Life-of-Plant Alternatives for a Pressurizer Thermowell Nozzle Repair at Palo Verde Nuclear Generating Station, Unit 1 ML24262A0972024-09-23023 September 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000529/2024011) ML24241A2542024-08-28028 August 2024 Inservice Inspection Request for Information ML24241A2782024-08-28028 August 2024 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24240A2682024-08-27027 August 2024 Transmittal of Technical Specification Bases Revision 79 IR 05000528/20240052024-08-22022 August 2024 Updated Inspection Plan for Palo Verde Nuclear Generating Station - Units 1, 2, and 3 (Report 05000528/2024005, 05000529/2024005, 05000530/2024005) 05000530/LER-2024-001-01, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-08-21021 August 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24208A0612024-08-20020 August 2024 Issuance of Amendment Nos. 224, 224, and 224 Regarding Revision to Technical Specifications 3.5.1, 3.5.2 and 3.6.5 IR 05000528/20244042024-08-0808 August 2024 Cybersecurity Inspection Report 05000528/2024404, 05000529/2024404 and 05000530/2024404 ML24213A3232024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 71: Re-Submittal of RR-30 ML24213A3292024-07-31031 July 2024 Transmittal of Relief Request (RR) No. 72: Re-Submittal of RR-39 IR 05000528/20240022024-07-29029 July 2024 Integrated Inspection Report 05000528/2024002 and 05000529/2024002 and 05000530/2024002 ML24173A3302024-07-24024 July 2024 Pressurizer Surge Line Inspection Program ML24159A4702024-07-17017 July 2024 Issuance of Amendment Nos. 223, 223, and 223 Revision to Technical Specifications 3.5.1 and 3.5.2 Using Risk Informed Process for Evaluations ML24198A0662024-07-16016 July 2024 Program Review - Simulator Testing Methodology ML24193A3442024-07-11011 July 2024 Fourth 10-Year Interval, Second Period Owner’S Activity Report Number 3R24 ML24129A0522024-07-0303 July 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report IR 05000528/20240042024-06-25025 June 2024 Notification of Inspection (NRC Inspection Report 05000528/2024004, 05000529/2024004, 05000530/2024004) 05000530/LER-2024-002, Invalid Specified System Actuation of Train B Emergency Diesel Generator2024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24177A3212024-06-25025 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canisters Identification Numbers AMZDFX180, AMZDFX181, AMZDFX182 Vertical Concrete Cask Identification Nu ML24177A3222024-06-25025 June 2024 Invalid Specified System Actuation of Train B Emergency Diesel Generator ML24170A9962024-06-18018 June 2024 Response to Second Request for Additional Information to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) – Operating, TS 3.5.2, Safety Injection Tanks (Sits) – Shutdown a ML24129A2062024-06-14014 June 2024 Issuance of Amendment Nos. 222, 222, and 222 Revision to Technical Specifications to Adopt TSTF-266-A 05000530/LER-2024-001, Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation2024-06-0505 June 2024 Inoperable Boron Dilution Alarm System(Bdas) with Technical Specification Violation ML24159A0262024-06-0303 June 2024 Annual Report of Guarantee of Payment of Deferred Premium 05000529/LER-2024-001, Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater2024-05-23023 May 2024 Valid Specified System Actuations of Unit 2 Train B Emergency Diesel Generator and Train B Auxiliary Feedwater ML24135A2482024-05-14014 May 2024 Response to Second Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24164A2582024-05-0909 May 2024 10-PV-2024-04 Post-Exam Comments ML24129A1482024-05-0707 May 2024 And Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Casks with Applied Changes ML24128A2702024-05-0707 May 2024 Docket Nos. Stn 50-528/529/530 - Response to NRC Regulatory Issue Summary (RIS) 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000528/20240012024-05-0202 May 2024 Independent Spent Fuel Storage Installation, Integrated Inspection Report 05000528/2024001, 05000529/2024001, 05000530/2024001, 07200044/2024001, and Exercise of Enforcement Discretion ML24119A0022024-04-26026 April 2024 2023 Annual Environmental Operating Report ML24116A2082024-04-24024 April 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2023 ML24109A0712024-04-22022 April 2024 NRC Initial Operator Licensing Examination Approval 05000528/2024301, 05000529/2024301, and 05000530/2024301 IR 05000528/20244012024-04-22022 April 2024 Security Baseline Inspection Report 05000528/2024401 and 05000529/2024401 and 05000530/2024401 (Cover Letter) ML24112A0012024-04-19019 April 2024 Core Operating Limits Report, Revision 32 ML24108A1982024-04-16016 April 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Casks with Applied Changes Authorized by an Amended Certificate of Compliance ML24103A2482024-04-12012 April 2024 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2023 ML24131A0972024-04-10010 April 2024 Annual Radiological Environmental Operating Report 2023 ML24096A2202024-04-0505 April 2024 Transmittal of Technical Specification Bases Revision 78 ML24032A1542024-04-0303 April 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) 2024-09-27
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24297A6212024-10-22022 October 2024 Request for Additional Information Relief Request (RR) No. 72: Re-Submittal of RR-39/ASME Code X1 IWC-3420, IWA-3300 ML24257A1012024-09-11011 September 2024 Request for Additional Information License Renewal Commitment for AMP of Alloy 600 Components ML24143A1112024-05-20020 May 2024 Draft 2nd Round Request for RAIs Concerning LAR to Modify LCO for TS 3.5.2, LCO for TS 3.6.5, and Surveillance Requirements 3.5.1.2 and 3.5.2.2 for TS 3.5.1 and TS 3.5.2 ML24123A2002024-05-0101 May 2024 (E-Mail) Draft 2nd Round Request for Additional Information Concerning License Amendment Request to Modify Limiting Condition for Operation (LCO) for Technical Specification (TS) 3.5.2, LCO for TS 3.6.5, 3.5.1.2 and 3.5.2.2 for TS 3.5.1, a ML24114A2812024-04-19019 April 2024 Request for Additional Information (RAI-10150-R1) ML24011A1002024-01-10010 January 2024 March 2024 Emergency Preparedness Program Inspection - Request for Information ML23334A1612023-11-30030 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - RAIs Associated with License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23334A0072023-11-29029 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR That Revises TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23298A1232023-10-25025 October 2023 NRR E-mail Capture - Palo Verde, Unit 1 - RAIs for Relief Request 70, Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle ML23031A3392023-01-31031 January 2023 In-service Inspection Request for Information ML23013A0632023-01-13013 January 2023 NRR E-mail Capture - Palo Verde Unit 1 -Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22348A1672022-12-14014 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22339A2372022-12-0505 December 2022 NRR E-mail Capture - Palo Verde Unit 1 – Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22272A3252022-09-29029 September 2022 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML22209A1752022-07-28028 July 2022 Inservice Inspection Request for Information ML22187A2632022-07-0606 July 2022 Notification of Inspection (NRC IR 05000528/2022004, 05000529/2022004 and 05000530/2022004) and Request for Information ML22067A2292022-03-0202 March 2022 Inservice Inspection Inspection PWR Request for Information ML22055A5842022-02-24024 February 2022 NRR E-mail Capture - Palo Verde, Unit 3 - Final RAIs for 22nd Refueling Outage (Spring 2021) Steam Generator Tube Inservice Inspection Report ML22035A3302022-02-10010 February 2022 Requests for Confirmation of Information for Exemption to Delete Diverse Auxiliary Feedwater Actuation System Based on Risk-Informed Process for Evaluations ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information ML21245A2222021-09-0101 September 2021 Request for Information ML21200A2392021-07-20020 July 2021 Docs Request AC - AA August 2021 ML21154A0082021-05-26026 May 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Official RAIs for LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21042B9692021-02-18018 February 2021 Notification of NRC Design Bases Assurance Inspection and Initial Request for Information ML21043A1462021-02-11011 February 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAI for an Order Associated with Indirect License Transfer from Public Service Company of New Mexico to Avangrid, Inc ML21023A0212021-01-13013 January 2021 PVNGS PI&R Request for Information RA ML21011A1972021-01-12012 January 2021 Unit 2, and Unit 3 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012) and Request for Information ML20227A0992020-08-14014 August 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20118D1362020-04-28028 April 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20049A0992020-02-14014 February 2020 Notification of Cyber Security Inspection (NRC Inspection Report 05000528/2020401; 05000529/2020401; and 05000530/2020401) and Request for Information ML20049A0252020-02-12012 February 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for License Amendment Request Associated with Changes to Emergency Plan Staffing Requirements ML20021A3172020-01-21021 January 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for Relief Request 64, Impractical Examinations for the Third 10-Year ISI Interval ML19317D0782019-11-13013 November 2019 NRR E-mail Capture - Palo Verde 1 - Requests for Additional Information on Unit 1 21st Refueling Outage Steam Generator Tube Inspection Report ML19234A3202019-08-29029 August 2019 Redacted - Request for Additional Information for Amendment and Exemption Request to Support the Implementation of Framatome High Thermal Performance Fuel (EPID L-2018-LLA-0194; EPID L-2018-LLE-0010) ML19155A1842019-05-30030 May 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mvib Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19095A6552019-04-0404 April 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mphb Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19044A7342019-02-13013 February 2019 NRR E-mail Capture - Palo Verde1, 2, and 3 - Official Requests for Additional Information for RR 62, Third and Fourth 10-Year ISI Intervals, Proposed Alternative - Pressurizer Heat Sleeve Repairs ML19008A3612019-01-0808 January 2019 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR Associated with Response Time Testing of Pressure Transmitters ML18341A0252018-12-0303 December 2018 Notification of NRC Design Bases Assurance Inspection (Teams)(05000528/2019011, 05000529/2019011, and 05000530/2019011) and Initial Request for Information ML18271A0392018-10-0202 October 2018 Non Proprietary - Supplemental Information Needed for Acceptance of Requested License Amendments and Exemptions Implementation of Framatome High Thermal Performance Fuel (Epids L-2018-LLA-0194 and L-2018-LLE-0010) ML18221A5102018-08-23023 August 2018 Request for Additional Information License Amendment Request to Adopt Risk-Informed Completion Times (CAC Nos. MF6576, MF6577, and MF6578; EPID: L-2015-LLA-0001) ML18229A3132018-08-17017 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 - Second Se ML18227A8672018-08-15015 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 ML18124A0112018-05-0303 May 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official Eeob RAIs for TSTF-505 (4b) LAR (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001) ML18099A0072018-04-0606 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for 10 CFR 50.69 LAR (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276) ML18094B1122018-04-0404 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAIs for TSTF-505 (Initiative 4b) LAR (CAC Nos. MF6576, MF6577, and MF6578: EPID L-2015-LLA-0001) ML18066A7032018-03-0707 March 2018 Notification of Nrc Design Bases Assurance Inspection (Programs) 05000528/2018011, 05000529/2018011, and 05000530/2018011 Initial Request for Information ML17248A0162017-08-31031 August 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAI for RRs PRR-03, PRR-04 and PRR-05, Pump Testing ML17107A0052017-04-14014 April 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Ngf LAR and Exemption RAIs (CAC Nos. MF8076 to MF8081) 2024-09-11
[Table view] |
Text
May 23, 2012
SUBJECT:
PALO VERDE NUCLEAR GENERATING STATION - INITIAL INFORMATION REQUEST FOR NRC TRIENNIAL BASELINE COMPONENT DESIGN BASES INSPECTION NRC INSPECTION REPORT 05000528; 05000529; 05000530/2012008
Dear Mr. Edington:
On November 13, 2012, the NRC will begin a triennial baseline Component Design Bases Inspection at the Palo Verde Nuclear Generating Station. A seven-person team will perform this inspection using NRC Inspection Procedure 71111.21, "Component Design Bases Inspection."
The inspection focuses on components, operating experience, and operator actions that have high risk and low design margins. The samples reviewed during this inspection will be identified during an information gathering visit and during the subsequent in-office preparation week. In addition, a number of operating experience issues will also be selected for review.
The inspection will include an information gathering site visit by the team leader and a senior reactor analyst. This will be followed by 3-weeks of onsite inspection by the team. The inspection will consist of five NRC inspectors and two contractors, of which four will focus on engineering and one on operations. The current inspection schedule is as follows:
Onsite information gathering visit: Week of October 29, 2012 Preparation Week: November 5, 2012 Onsite weeks: November 13, 2012 November 26, 2012 December 10, 2012
The purpose of the information gathering visit is to meet with members of your staff to identify potential risk-significant components and operator actions. The lead inspector will also request a tour of the plant with members of your operations staff and probabilistic safety assessment staff. During the onsite weeks, several days of time will be needed on the plant-referenced simulator in order to facilitate the development of operator action-based scenarios. Additional information and documentation needed to support the inspection will be identified during the inspection, including interviews with engineering managers, engineers, and probabilistic safety assessment staff. UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV1600 EAST LAMAR BLVDARLINGTON, TEXAS 76011-4511 Our experience with these inspections has shown that they are extremely resource intensive, both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the site and to ensure a productive inspection, we have enclosed a request for information needed for the inspection. The request has been divided into three groups. The first group lists information necessary for the information gathering visit, general preparation, and sample selection. This information should be available to the regional office no later than October 15, 2012. If possible, this information should be provided electronically to the lead inspector. Since the inspection will be concentrated on high risk/low margin components, calculations associated with your list of high risk components should be available to review during the information gathering visit to assist in our selection of components based on available design margin.
The second group of documents requested is those items that the team will need access to the first day of onsite inspection to complete the required inspection samples. The third group lists information necessary to aid the inspection team in tracking issues identified as a result of the inspection. It is requested that this information be provided to the lead inspector as the information is generated during the inspection. Additional requests by inspectors will be made throughout all three onsite weeks for specific documents needed to complete the review of that component/selection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection. In order to facilitate the inspection, we request that a contact individual be assigned to each inspector to ensure information requests, questions, and concerns are addressed in a timely manner.
During the onsite portion of our inspection, we request that you make available a conference room large enough to accommodate the inspection team. In that conference room, please make available a computer with access to a printer, your condition reporting database, and your documentation database.
The lead inspector for this inspection is Matthew Young. We understand that our licensing engineer contact for this inspection is Del Elkinton. If there are any questions about the inspection or the requested materials, please contact the lead inspector at (817) 200-1545 or via e-mail at matt.young@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Thomas Farnholtz, Chief Engineering Branch 1 Division of Reactor Safety Docket: 50-528; 50-529; 50-530 License: NPF-41; NPF-51; NPF-74
Enclosure: Component Design Basis Inspection Document Request cc w/enclosure:
Electronic Distribution for Palo Verde Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Art.Howell@nrc.gov) DRP Director (Kriss.Kennedy@nrc.gov) DRP Deputy Director (Troy.Pruett@nrc.gov) Acting DRS Director (Tom.Blount@nrc.gov) Acting DRS Deputy Director (Patrick.Louden@nrc.gov) Senior Resident Inspector (Tony.Brown@nrc.gov) Resident Inspector (Mica.Baquera@nrc.gov) Resident Inspector (Dustin.Reinert@nrc.gov) Branch Chief, DRP/D (Ryan.Lantz@nrc.gov) Senior Project Engineer (Nick.Taylor@nrc.gov) Project Engineer, DRP/D (David.You@nrc.gov) Project Engineer, DRP/D (Brian.Parks@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov) Project Manager (Balwant.Singal@nrc.gov) Acting Branch Chief, DRS/TSB (Dale.Powers@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Technical Support Assistant (Loretta.Williams@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov) OEMail Resource Inspection Reports/MidCycle and EOC Letters to the following:
ROPreports Only inspection reports to the following: RIV/ETA: OEDO (Michael.McCoppin@nrc.gov) DRS/TSB STA (Dale.Powers@nrc.gov)
SUNSI Review Completed: _Yes_ ADAMS: Yes No Initials: MRY Publicly Available Non-Publicly Available Sensitive Non-Sensitive MLXXXXXXXXXX RIV:RI:DRS/EB1 RIV:BC/EB1 M. Young T. Farnholtz
/RA/ /RA/ 05/21/2012 5/22/12
- 1 - Enclosure INFORMATION REQUEST FOR PALO VERDE NUCLEAR GENERATING STATION COMPONENT DESIGN BASES (CDBI) INSPECTION
Inspection Report: 0500050528/2012008 0500050529/2012008 0500050530/2012008 Information Gathering Dates: October 30 - November 1, 2012
On-site Inspection Dates: November 13 - 16, 2012 November 26 - 30, 2012 December 10 - 14, 2012 Inspection Procedure: IP 71111.21, "Component Design Bases Inspection" Lead Inspector/Team Leader: Matthew Young 817-200-1545 matt.young@nrc.gov
I. Information Requested Prior to the information Gathering Visit (October 15, 2012)
The following information (Section I of this enclosure) should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com or compact disc, preferred), in care of Matthew Young, by October 15, 2012, to facilitate the reduction in the items to be selected for a final list during the preparation week November 5, 2012. The specific items selected from the lists shall be available and ready for review on the day indicated in this request. *Please provide requested documentation electronically in "pdf" files, Excel, or other searchable formats, if possible. The information should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood by someone who has knowledge of pressurized water reactor technology. If requested documents are large and only hard copy formats are available, please inform the inspectors, and provide subject documentation during the first day of the onsite inspection.
1. An excel spreadsheet of equipment basic events (with definitions) including importance measures sorted by risk achievement worth (RAW) and Fussell-Vesely (FV) from your internal events probabilistic risk assessment (PRA). Include basic events with RAW value of 1.3 or greater.
2. Provide a list of the top 500 cut-sets from your PRA.
3. Copies of PRA "system notebooks," and the latest PRA summary document.
4. An excel spreadsheet of PRA human action basic events or risk ranking of operator actions from your site specific PSA sorted by RAW and FV. Provide copies of your human reliability worksheets for these items.
- 2 - Enclosure 5. If you have an external events or fire PSA model, provide the information requested in items 1-4 for external events and fire.
6. Site top 10 issues list.
7. Any pre-existing evaluation or list of components and associated calculations with low design margins, (i.e., pumps closest to the design limit for flow or pressure, diesel generator close to design required output, heat exchangers close to rated design heat removal, etc.).
8. List of motor operated valves (MOVs) in the valve program, with design margin and risk ranking.
9. List of air operated valves (AOVs) in the valve program, with design margin and risk ranking.
10. List of high risk maintenance rule systems/components and functions; based on engineering or expert panel judgment.
11. Structure, system and components in the Maintenance Rule (a)(1) category.
12. A list of operating experience evaluations for the last 2 years.
13. A list of all time-critical operator actions in procedures.
14. A list with description of permanent and temporary modifications sorted by the top 50 components identified in Item 1.
15. List of current "operator work arounds/burdens." 16 List of root cause evaluations associated with component failures or design issues initiated/completed in the last 5 years.
17. Current management and engineering organizational charts.
18. Palo Verde Nuclear Generating Station IPE and IPEEE, if available electronically.
19. Mechanical piping drawings for:
Engineered safety features Emergency core cooling systems Emergency diesel generators
- 3 - Enclosure 20. Electrical one-line drawings for:
Offsite power/switchyard supplies Normal AC power systems Emergency AC/DC power systems including 120VAC power, and 125VDC/24VDC safety class systems 21. List of any common-cause failures of components in the last 3 years.
22. An electronic copy of the licensing basis documents (i.e., Updated Final Safety Analysis Report, Technical Specifications).
23. An electronic copy of the System Health notebooks.
24. System Description Manuals with simplified drawings of plant systems
II. Information Requested to be Available on First Day of the Onsite Week (November 13, 2012)
1. List of condition reports (corrective action documents) associated with each of the selected components for the last 5 years.
2. The corrective maintenance history associated with each of the selected components for the last 2 years.
3. Copies of calculations associated with each of the selected components (if not previously provided), excluding data files. Please review the calculations and also provide copies of reference material (such as drawings, engineering requests, and vendor letters).
4. Copies of operability evaluations associated with each of the selected components and plans for restoring operability, if applicable.
5. Copies of selected operator work-around evaluations associated with each of the selected components and plans for resolution, if applicable.
6. Copies of any open temporary modifications associated with each of the selected components, if applicable.
7. Trend data on the selected electrical/mechanical components' performance for last 3 years (for example, pumps' performance including in-service testing, other vibration monitoring, oil sample results, etc., as applicable).
8. A copy of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection.
9. A copy of engineering/operations related audits completed in the last 2 years.
- 4 - Enclosure 10. Procedures used to accomplish selected operator actions.
11. List of licensee contacts for the inspection team with pager or phone numbers.
III. Information Requested to be provided throughout the inspection.
1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection.
2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member).
3. Reference materials (available electronically and as needed during all onsite weeks): General set of plant drawings Procurement documents for components selected Plant procedures (normal, abnormal, emergency, surveillance, etc.) Vendor manuals
Inspector Contact Information
- Matthew Young Reactor Inspector (817) 200-1545 matt.young@nrc.gov Mailing Address
US NRC, Region IV Attn: Matthew Young 1600 East Lamar Blvd Arlington, TX 76011-4511