IR 0500400-13-404, 10/3/2013, Shearon Harris Nuclear Plant - NRC Temporary Instruction 2515/186 Inspection Report - Cover Letter
ML13305B047
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 10/31/2013
From: Mark Franke
Division of Reactor Safety II
To: Hamrick G
Carolina Power & Light Co
References
IR-13-404
Download: ML13305B047 (5)


See also: IR 05000400/2013404

Text

OFFICIAL USE ONLY

- SECURITY RELATED INFORMATION

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257

Enclosure transmitted herewith contains SUNSI. When separated from enclosure, this

transmittal document is decontrolled.

LIMITED INTERNAL

DISTRIBUTION PERMITTED

OFFICIAL USE ONLY

- SECURITY RELATED INFORMATION

October 31, 2013

Mr. George T. Hamrick Vice President

Shearon Harris Nuclear Power Plant

Carolina Power and Light Company

P.O. Box 165, Mail Code: Zone 1

New Hill, NC 27562-0165

SUBJECT: SHEARON HARRIS NUCLEAR PLANT - NRC TEMPORARY INSTRUCTION 2515/186 INSPECTION REPORT 0500400/2013404

Dear Mr. Hamrick: On October 3, 2013 , the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Shearon Harris Nuclear Plant using Temporary Instruction 2515/186, "Inspection of

Procedures and Processes for Responding to Potential Aircraft Threats". The enclosed

inspection report documents the inspection results which were discussed on October 3, 2013,

with Mr. John Onfner and other members of your staff.

The objective of this inspection was to assess the implementation procedures and processes of

Shearon Harris Nuclear Plant that are required by Title 10 of the

Code of Federal Regulations (CFR), Part 50.54(hh)(1), which provides the requirements for responding to a potential aircraft

threat. The results from this inspection, along with the results from this inspection performed at

other operating commercial nuclear plants in the United States, will be used to evaluate the U.S.

nuclear industry's readiness to safely respond to similar events. These results will also help the

NRC to determine if additional regulatory actions are warranted.

No findings were identified during this inspection.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component

of NRC's document system, ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of

OFFICIAL USE ONLY

- SECURITY RELATED INFORMATION

G. Hamrick 2

OFFICIAL USE ONLY

- SECURITY RELATED INFORMATION

NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from public disclosure under 10 CFR 2.390" in accordance

with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390 (b)(1).

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.

Sincerely,

/RA/

Mark E. Franke, Chief

Operations Branch 2

Division of Reactor Safety

Docket No. 50-400

License No. NPF-64

Enclosure: Inspection Report 0500400/2013404 w/Attachment: Supplemental Information (Official Use Only)

cc: (See page 3)

_________________________ x SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS RII:DRS RII;DRS RII:DRS SIGNATURE RA RA RA RA RA NAME DLANYI AGOLDAU BBONSER BDESAI MFRANKE DATE 10/31/2013 10/31/2013 10/24/2013 10/29/2013 10/31/2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICIAL USE ONLY

- SECURITY RELATED INFORMATION

G. Hamrick 3

OFFICIAL USE ONLY

- SECURITY RELATED INFORMATION

cc: Lara S. Nichols

Deputy General Counsel

Duke Energy Corporation

550 S.Tyron Street

Mail Code DEC45A

Charlotte, NC 28202

Ernest J. Kapopoulos Jr.

Plant General Manager

Carolina Power and Light Company Shearon Harris Nuclear Power Plant

5413 Shearon Harris Road

New Hill, NC 27562

Terrence E. Slake

Manager

Nuclear Plant Security

Shearon Harris Nuclear Power Plant

5413 Shearon Harris Road

New Hill, NC 27562

Progress Energy Carolinas, Inc.

ATTN: Mr. Donald L. Griffith

Training Manager

Harris Energy & Env. Center Shearon Harris Nuclear Power Plant P.O. Box 327, State Road 1127

New Hill, NC 27562-0165

OFFICIAL USE ONLY

- SECURITY RELATED INFORMATION

OFFICIAL USE ONLY

- SECURITY RELATED

INFORMATION

Letter to George T. Hamrick from Mark E. Franke dated October 31, 2013.

SUBJECT: SHEARON HARRIS NUCLEAR PLANT - NRC TEMPORARY INSTRUCTION 2515/186 INSPECTION REPORT 0500400/2013404

Distribution:

RidsNrrPMShearonHarris Resource

C. Evans, RII EICS

L. Douglas, RII EICS

RIDSNRRDIRS

PUBLIC S. Coker, NSIR/DSO/DDSO/ST T. Dimitriadis, RI

R. Albert, NSIR B. Desai, RII

B. Huffman, NSIR/DPR/DDIR/OB