ML13036A249

From kanterella
Revision as of 23:42, 28 April 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
2013/01/21 Watts Bar 2 OL - 2012-01-21 - WBN Project Plan - Unit 2.pdf
ML13036A249
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 01/21/2013
From:
- No Known Affiliation
To:
Division of Operating Reactor Licensing
References
Download: ML13036A249 (12)


Text

1 WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Monday, January 21, 2013 8:02 AM To: Poole, Justin; Arent, Gordon; Br yan, Robert H Jr; Hon, Andrew Cc: Boyd, Desiree L

Subject:

2012-01-21 - WBN Project Plan - Unit 2.pdf Attachments:

2013-01-21 - WBN Project Plan - Unit 2.pdf Please see attached for today's 9:15 phone call.

Thank you

~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 769 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF3A75FCFA)

Subject:

2012-01-21 - WBN Project Plan - Unit 2.pdf Sent Date: 1/21/2013 8:02:23 AM Received Date: 1/21/2013 8:03:11 AM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients: "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None "Arent, Gordon" <garent@tva.gov> Tracking Status: None "Bryan, Robert H Jr" <rhbryan@tva.gov> Tracking Status: None "Hon, Andrew" <Andrew.Hon@nrc.gov> Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov

Files Size Date & Time MESSAGE 259 1/21/2013 8:03:11 AM 2013-01-21 - WBN Project Plan - Unit 2.pdf 222260 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date: Recipients Received:

WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 2 of 38 SOURCE: POD UPDATES, COMMITMENTS I. SUBMITTAL LOOK-AHEAD Item No. Description Resp. Person Due Date License Amendments / Technical Specifications

1. Common Service Station Transformer (CSST) A & B Credit Shea March 7, 2013
2. SSER Open Item 32: Revise Diesel Generator Frequency Allowable Value. [Commitment 113676066] Hilmes March 29, 2013 Revised Proposal from Flowserve to Bechtel FlowServe January 14, 2013 Issue Purchase Order Wiggall Tentative - January 18, 2013 Provide Runout Analysis FlowServe 6 weeks after purchase order Westinghouse draft evaluation of analysis impacts Complete Westinghouse final analysis impact evaluation Morgan TBD Add Flowserve and Westinghouse evaluations to LAR write-up Wiggall TBD Finalize and Submit LAR to NRC Licensing TBD WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 3 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date SSER Appendix HH Open Items (requiring submittal)
1. SSER Open Item 1: Following completion of cable pulls, submit letter to NRC either: Affirming no power assisted cable pulls were made, or Documenting any power assisted cable pulls. [Commitment 113676047] Hilmes January 17, 2014
2. SSER Open Item 13: Submit an ASME Section XI Inservice Test Program for the first ten year interval six months before receiving an Operating License. [Commitment NCO080008033: Item 017 of Enclosure 2 of letter T90 080128 001] McDonald / Crouch June 12, 2014
3. SSER Open Item 25: Submit documentation of liability insurance coverage pursuant to 10 CFR 140.11(a)(4). [Commitment 113676162] Bryan January 31, 2013
4. SSER Open Item 37: Submit changes to the Emergency Plan (REP) prior to fuel load. [Commitment 111032952] Detchemendy November 15, 2013
5. SSER Open Item 41:

Update the following to provide two unit capability: Plant design displays

[Commitment 111033086], and dose assessment models [Commitment 113841821] Hilmes / Koontz November 15, 2013

6. SSER Open Item 43: Submit Emergency Plan implementing procedures no less than 180 days before schedule issuance of Operating License.

[Commitment 113841955] Detchemendy November 15, 2013 WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 4 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date 7. SSER Open Item 50: Submit letter to update scope and plans for actions involving anchor bolt pull tests and records. Charlton January 31, 2013

8. SSER Open Item 61: Fuel Thermal Conductivity Degradation Model (PAD Code) - Note: currently this is a License Condition - tracking PWROG activity to update code. [Commitment 113676152] Koontz March 31, 2013
9. SSER Open Item 79:

Perform an EMI survey of the containment high range radiation monitors after they are installed in WBN Unit 2, and submit the results to the NRC within two weeks of the survey being completed. [Commitment 112177753] Hilmes March 4, 2014

10. SSER Open Item 83:

Provide Letter verifying completion of data storm test on DCS. [Commitment 113676093] Hilmes August 30, 2013

11. SSER Open Item 134: Modifications for Cherokee and Douglas Dams will be designed and implemented prior to WBN Unit 2 Startup. [Commitment 113880166] Williams July 1, 2014

WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 5 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Other Submittals

1. As-Constructed Fire Protection Report [Commitment 113461862] Hilmes July 18, 2014
2. U2 FSAR With As-Constructed Figures

[Commitment 112068531] Arent September 12, 2014

3. Prior to fuel load, a final report will be submitted following certain validation activities as described in the IPEEE Design Report (Enclosure 1).

[Commitment 111027893]

Koontz / Enis July 18, 2014

4. Submit a merged U2 FSAR / U1 UFSAR [Commitment 111360889] Licensing April 2016
5. As-Constructed PRA [Commitment 111029124] Guey / Koontz July 18, 2014
6. TMI Commitment Review Letter [Commitment 113967286] Licensing January 24, 2014
7. Letter to terminate Part 30/40 License after receipt of Part 50 License [Commitment 113967302] Licensing December 4, 2015
8. ASME Section III N-3 Report [Commitment 113967305] Crouch September 2014
9. Letter to NRC for notification of Vital Area Boundary Restoration [Commitment 110850749] Licensing January 24, 2014
10. Unit 2 Completion Letter [Commitment 113967311] Licensing August 8, 2014
11. PAM variable Calculation for EOP reviews [Commitment 113967317] Partch March 31, 2013
12. Submit an update to the Multiple Spurious Operation Evaluation Report that addresses the commitments made in TVAs letter dated 08-20-2010 (Commitment 111905993) and in TVAs letter dated May 6, 2011 (Commitment 112331509) Crouch February 7, 2013 WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 6 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Other Submittals
13. Submit letter documenting that plant modifications to add high VCT level alarm to main control room annunciator system have been completed. [Commitment 113111704] Arent / Wallace May 24, 2013
14. Submit letter documenting that procedure changes associated with limiting the number of operating primary water pumps and isolating potential boron dilution paths have been made. [Commitment 113111705] Arent / Wallace May 24, 2013
15. TMI Action Item Status Letter Arent April 30, 2014
16. Misc TS & TS Bases Changes Fuel Storage, CSST, DG Frequen cy, RCS Dose Equivalent Iodine Bryan February 9, 2013
17. Facility Operating License No. NPF-90, Unit 1 Arent December 12, 2013
18. Bulletin 2011-01 Bushnell February 14, 2013
19. Commercial Grade Dedication 60 Day Report 50.55(e) written report Stockton February 2, 2013

WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 7 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Regional Submittals

1. Unit Differences Update Letter [Commitment 112145218 - 01] Stockton January 25, 2013

WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 8 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Fukushima

1. NRC Order EA-12-049; Mitigating Strategies Order: Licensees to develop, implement, and maintain gui dance and strategies to maintain or restore core cooling, containment and SFP cooling capabilities following a beyond-design-basis external event. Must be implemented in all modes. [Commitment 113868651] Williams/Spink NRC Update February 28, 2013
2. NRC Order EA-12-049; Mitigating Strategies Order: Strategies must be capable of mitigating a simultaneous loss of all alternating current (AC) power and loss of normal access to the ultimate heat sink and have adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site. [Commitment 113871962] Williams/Spink NRC Update February 28, 2013
3. NRC Order EA-12-049; Mitigating Strategies Order: Provide reasonable protection for the associated equipment from external events. Such protection must demonstrate that there is adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site.

[Commitment 113871973] Williams/Spink NRC Update February 28, 2013

4. NRC Order EA-12-051; Order: Licensees to provide instrumentation, able to withstand design-basis natural phenomena and remain reliable at temperature, humidity and radiation levels at saturation conditions, to monitor SFP water level from the control room. DCN 59683, Spent Fuel Pool Level Indication 10% of package [Commitment 113872005] Williams/Spink NRC Update February 28, 2013
5. 10 CFR 50.54 F Letter Request for Information: Licensees to reevaluate the seismic hazards at their sites against current NRC requirements and guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards. [Commitment 113872017] Williams/Spink January 29, 2013 WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 9 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Fukushima
6. 10 CFR 50.54 F Letter Request for Information: Licensees to reevaluate the flooding hazards at their sites against current NRC requirements and guidance, and if necessary, update the design basis and SSCs important to safety to protect against the updated hazards. [Commitment 113872029] Williams/Spink January 29, 2013
7. 10 CFR 50.54 F Letter Request for Information: Recommendation 9.3 requires licensees to evaluate communication and staffing needs for multi-unit events. [Commitment 113872040] Williams/Spink April 30, 2013

WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 10 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Waste Confidence

1. TVA actions on Waste Confidence Finalize contractor outputs on reports for Waste Confidence Plan Vigluicci / Baker March 31, 2013

WBN UNIT 2 PROJECT PLAN: 01/21/2013 Page 11 of 38 SOURCE: POD UPDATES, COMMITMENTS Item No. Description Resp. Person Due Date Significant New Regulatory Issues

1. New Station Blackout Rule Ongoing rulemaking Hilmes Spring 2013
2. 10 CFR 50.46 Rule Change Oxidation limits Ongoing rulemaking Koontz/Westinghouse Spring 2013
3. DOEL Reactor Vessel Issues Hemmer TBD
4. Shutdown Seals - Westinghouse Submits Topical Report Koontz March 13, 2013