IR 05000245/2007006

From kanterella
Revision as of 06:40, 24 October 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
IR 05000245-07-006, on 03/19/21-2007, Dominion Nuclear Connecticut, Millstone Power Station Unit 1, Waterford, Connecticut
ML071060224
Person / Time
Site: Millstone Dominion icon.png
Issue date: 04/16/2007
From: Hansell S L
Decommissioning Branch I
To: Dobson D W, Price J A
Dominion Nuclear Connecticut
References
IR-07-006
Download: ML071060224 (13)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I475 ALLENDALE ROADKING OF PRUSSIA, PENNSYLVANIA 19406-1415 April 16, 2007Docket No. 05000245License No. DPR-21 J. Allan PriceSite Vice President Millstone Power Station, Unit 1 Dominion Nuclear Connecticut c/o Mr. D. W. Dobson, Supervisor -

Station Nuclear Licensing Rope Ferry Road Waterford, CT 06385

SUBJECT: INSPECTION 05000245/2007006, DOMINION NUCLEAR CONNECTICUT,MILLSTONE POWER STATION UNIT 1, WATERFORD, CONNECTICUT

Dear Mr. Price:

On March 19-21, 2007, Robert Prince of this office conducted an inspection of your MillstoneUnit 1 nuclear reactor facility at Waterford, Connecticut. The inspection was an examination of your activities related to the maintenance of Unit 1 in a SAFSTOR status. The inspection consisted of observations by the inspector, interviews with personnel, and a selected examination of representative records. The findings of the inspection were discussed with Mr. Skip Jordan and members of your staff on March 21, 2007.Within the scope of this inspection, no violations were identified. Activities associated withmaintaining Unit 1 in a safe condition to ensure the safe storage of spent fuel were implemented effectively .In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and itsenclosure will be available electronically for public inspection in the NRC Public DocumentRoom of from the Publically Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC web site at http://www/nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room). No reply to this letter is required. Your cooperation with us is appreciated.

Sincerely,/RA/Samuel Hansell, ChiefDecommissioning Branch Division of Nuclear Materials Safety April 16, 2007Docket No. 05000245License No. DPR-21J. Allan PriceSite Vice President Millstone Power Station, Unit 1 Dominion Nuclear Connecticut c/o Mr. D. W. Dobson, Supervisor -

Station Nuclear Licensing Rope Ferry Road Waterford, CT 06385

SUBJECT: INSPECTION 05000245/2007006, DOMINION NUCLEAR CONNECTICUT,MILLSTONE POWER STATION UNIT 1, WATERFORD, CONNECTICUT

Dear Mr. Price:

On March 19-21, 2007, Robert Prince of this office conducted an inspection of your MillstoneUnit 1 nuclear reactor facility at Waterford, Connecticut. The inspection was an examination of your activities related to the maintenance of Unit 1 in a SAFSTOR status. The inspection consisted of observations by the inspector, interviews with personnel, and a selected examination of representative records. The findings of the inspection were discussed with Mr. Skip Jordan and members of your staff on March 21, 2007.Within the scope of this inspection, no violations were identified. Activities associated withmaintaining Unit 1 in a safe condition to ensure the safe storage of spent fuel were implemented effectively .In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and itsenclosure will be available electronically for public inspection in the NRC Public DocumentRoom of from the Publically Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC web site at http://www/nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room). No reply to this letter is required. Your cooperation with us is appreciated.

Sincerely,/RA/Samuel Hansell, ChiefDecommissioning Branch Division of Nuclear Materials SafetySUNSI Review Complete: RPrinceAfter declaring this document "An Official Agency Record" it will be released to the Public.To receive a copy of this document, indicate in the box:

"C" = Copy w/o attach/encl "

E" = Copy w/ attach/encl "

N" = No copyOFFICEDNMS/RI NDNMS/RIDNMS/RINAMERPrinceSHansellDATE4/16/074/16/07OFFICIAL RECORD COPYAccession Number: ML071060224 J. Price2 2

Enclosure:

1. NRC Region I Inspection Report No. 05000245/2007006 cc:D. A. Christian, Senior Vice President - Nuclear Operations and Chief Nuclear Officer W. R. Matthews, Vice President and Senior Nuclear Executive - Millstone P. J. Parulis, Manager - Nuclear Oversight L. M. Cuoco, Senior Nuclear Counsel State of Connecticut SLO Designee First Selectman, Town of Waterford D. Katz, Citizens Awareness Network (CAN)

R. Bassilakis, CAN J. M. Block, Attorney, CAN G. Winslow, Citizens Regulatory Commission (CRC)

E. Woollacott, Co-Chair, NEAC P. Rathbun, MIDAC