BYRON 2003-0093, Issuance of Core Operating Limits Report for Byron Unit One Cycle 13 | 7 October 2003 | Issuance of Core Operating Limits Report for Byron Unit One Cycle 13 | Shutdown Margin |
BYRON 2003-0094, September 2003 Monthly Operating Report for Byron Station, Units 1 and 2 | 15 October 2003 | September 2003 Monthly Operating Report for Byron Station, Units 1 and 2 | Offsite Dose Calculation Manual |
BYRON 2003-0110, October 2003 Monthly Operating Report for Byron Station, Units 1 and 2 | 14 November 2003 | October 2003 Monthly Operating Report for Byron Station, Units 1 and 2 | Offsite Dose Calculation Manual |
BYRON 2003-0114, Sixty-Day Response to NRC Bulleting 2003-02, Leakage from Reactor Pressure Vessel Lower Head Penetrations and Reactor Coolant Pressure Boundary Integrity. | 12 December 2003 | Sixty-Day Response to NRC Bulleting 2003-02, Leakage from Reactor Pressure Vessel Lower Head Penetrations and Reactor Coolant Pressure Boundary Integrity. | Boric Acid VT-2 Through-Wall Leak |
BYRON 2003-0115, Sixty-Day Response to NRC Order EA-03-009, Issuance of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors. | 12 December 2003 | Sixty-Day Response to NRC Order EA-03-009, Issuance of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors. | Boric Acid VT-2 |
BYRON 2003-0116, November 2003 Monthly Operating Report for Byron Station Units 1 and 2 | 15 December 2003 | November 2003 Monthly Operating Report for Byron Station Units 1 and 2 | Offsite Dose Calculation Manual |
IR 05000454/2003006 | 30 October 2003 | IR 05000454-03-006, IR 05000455-03-006; on 07/01/2003-09/30/2003; Byron Station; Units 1 & 2; Maintenance Effectiveness, Access Control to Radiologically Significant Areas | Boric Acid High Radiation Area Fire Barrier Stroke time Internal Flooding Hydrostatic Temporary Modification Locked High Radiation Area Significance Determination Process Job Performance Measure Foreign Material Exclusion Operability Determination Substantial potential for an overexposure Power change Overexposure |
IR 05000454/2003008 | 30 October 2003 | IR 05000454-03-008, on 10/01/03 - 10/03/03, Byron Station, Unit 1; Special Inspection for Fuel Movement Incident | Condition Adverse to Quality Significance Determination Process Fuel cladding |
IR 05000454/2003010 | 29 December 2003 | IR 05000454-03-010(DRS); 05000455-03-010(DRS); 12/01/03 - 12/05/03; Byron Station; Units 1 and 2; Emergency Preparedness Specialist Report | |
ML032820247 | 2 October 2003 | Request for a License Amendment to Revise Psv Lift Settings - Byron/Braidwood Units 1 and 2 | |
ML032820506 | 7 October 2003 | Questions Regarding SX AOT Extension Request | Probabilistic Risk Assessment Large early release frequency |
ML032830094 | 30 October 2003 | Request for Additional Information Regarding a One Time Extension of the Essential Service Water Completion time....MB9547, MB9548, MB9545, and MB9546 | Probabilistic Risk Assessment Large early release frequency |
ML032830455 | 19 November 2003 | Units 1 and 2, Package, Re Completion Time from 24 Hours to 7 Days for One Inoperable Instrument Bus Inverter | Safe Shutdown High winds Probabilistic Risk Assessment Large early release frequency Earthquake |
ML032880457 | 3 October 2003 | Notification of Pending Changes to the Emergency Response Data System | |
ML032890578 | 30 October 2003 | Revision to Safety Evaluation Supporting License Amendments Approving an Increase in Reactor Power | |
ML032930100 | 20 October 2003 | Re Public Meeting to Discuss Operation Above the Licensed Thermal Power Limits at the Byron Station | Power change |
ML032950646 | 23 October 2003 | La Salle, Units 1 & 2, Limerick, Units 1 & 2, Oyster Creek, Peach Bottom, Units 2 & 3, Quad Cities, Units 1 & 2, Three Mile Island - Reply to Response to Order | Fitness for Duty |
ML032970102 | 19 November 2003 | Orders Modifying Licenses for Revised Design Basis Threat and for Training and Physical Fitness Enhancements Applicable to Security Force Personnel | |
ML033110224 | 6 November 2003 | GFES-NO Ltr Re October 2003 Results | Generic Fundamentals Examination |
ML033160520 | 21 November 2003 | Notice of Meeting with Exelon Generation Company, LLC Re Licensing Activities | |
ML033180436 | 9 November 2003 | G20030685/LTR-03-0729 - Bob Meyer Ltr. Fatigue Rule - 16 Hour Wording | Fatigue Rule |
ML033230225 | 12 November 2003 | Submittal of WCAP-16084-NP, Development of Risk-Informed Safety Analysis Approach and Pilot Application. | Anticipated operational occurrence Probabilistic Risk Assessment Fuel cladding Coast down |
ML033230277 | 18 November 2003 | Letter to Licensees Confirming Public Meeting on Byron Station Dtd 12/02/03 | |
ML033230280 | 18 November 2003 | Notice of Licensee Meeting with Exelon Generation Co., LLC Re Licensee Decision-Making Process | |
ML033240164 | 18 November 2003 | Response to Request for Additional Information - WCAP-15872-NP, Rev. 0 Use of Alternate Decay Heat Removal in Mode 6 Refueling. | Ultimate heat sink |
ML033250556 | 19 November 2003 | Units 1 and 2, Technical Specifications, Re Completion Time from 24 Hours to 7 Days for One Inoperable Instrument Bus Inverter | |
ML033300211 | 20 November 2003 | FOIA/PA-2003-0444 - Resp 1 - Final | |
ML033350269 | 3 December 2003 | G20030688, G20030689, G20030691 - 12/18/03, Visit by Mr. John Skolds, Chief Nuclear Officer for Exelon Nuclear and Mr. Jeffrey A. Benjamin, Vice President, Licensing and Regulatory Affairs; Nrc'S Oversight & Assess Chart | |
ML033360688 | 2 December 2003 | Response to Order for Compensatory Measures Related to Access Authorization | |
ML033390140 | 31 October 2003 | OI-3-2001-044, Byron, Release of OI Synopsis | |
ML033420151 | 12 December 2003 | Bryon, Unit 1, Evaluation of Steam Generator Inservice Inspection Summary Report, TAC No. MC0962 | |
ML033421289 | 5 December 2003 | Westinghouse - NSAL 03-12 - 12/05/03 Crossflow Ultrasonic Measurement System | |
ML033440348 | 9 December 2003 | Meeting Handout to Discuss Licensing Issues and Upcoming Licensing Activities with the Exelon Fleet of Nuclear Plants | Surveillance Frequency Control Program |
ML033520560 | 18 December 2003 | Re Information Request for an NRC Biennial Permanent Modifications and 10 CFR 50.59 Baseline Inspection | Commercial Grade Dedication |
ML033560302 | 9 December 2003 | Exelon/Amergen 180-Day Response to NRC Generic Letter 2003-01, Control Room Habitability. | Safe Shutdown Reactor Vessel Water Level Fire Barrier Safe Shutdown Earthquake Probabilistic Risk Assessment Design basis earthquake Fire Protection Program Power Uprate |
ML040090133 | 17 December 2003 | GFE Registration Letter 12/17/04 Re March 2004 Examination (Multiple Addressees) | Generic Fundamentals Examination |
ML040130815 | 10 December 2003 | Initial RO Examination 12/2003 | Safe Shutdown Loop seal Power change |
ML040130816 | 10 December 2003 | Initial SRO Examination 12/2003 | Safe Shutdown Shutdown Margin Loop seal Power change |
ML040140551 | 1 December 2003 | Initial Submittal of Administrative Jpms for Byron Initial Examination - Dec 2003 | Shutdown Margin Nuclear Accident Reporting System Job Performance Measure |
ML040140723 | 1 December 2003 | Initial Submittal of Walkthrough Jpms for Byron Initial Examination - Dec 2003 | Job Performance Measure |
ML040140746 | 1 December 2003 | Initial Submittal of the Scenarios for Byron Initial Examination - Dec 2003 | Boric Acid Post Accident Monitoring Power change |
ML040140752 | 1 December 2003 | Initial Submittal of Written Exam for Byron Initial Examination - Dec 2003 | Safe Shutdown Shutdown Margin Loop seal Deep Dose Equivalent Power change |
ML040140778 | 1 December 2003 | Final As-Administered Administrative Jpms for Byron Initial Examination - Dec 2003 | Shutdown Margin Nuclear Accident Reporting System Job Performance Measure |
ML040140786 | 1 December 2003 | Final As-Administered Walkthrough Jpms for Byron Initial Examination - Dec 2003 | Job Performance Measure |
ML040140787 | 1 December 2003 | Final as Administered Scenarios for Byron Initial Examination - Dec 2003 | Boric Acid Post Accident Monitoring Power change |
ML040280015 | 1 December 2003 | Various Checklist for Byron Initial Examination - December 2003 | |
ML040280018 | 1 December 2003 | Miscellaneous Correspondence for Byron Initial Examination - December 2003 | Job Performance Measure Generic Fundamentals Examination |
ML040280020 | 1 December 2003 | Examination Outline Submittal for Byron Initial Examination - December 2003 | Shutdown Margin Job Performance Measure |
ML040280021 | 1 December 2003 | Documents Related to Initial Exam Submittal and NRC Comments on Operating Test and ES-401-9 for NRC Comments on Written Exam for Byron Initial Examination - December 2003 | Power change |
ML072680178 | 23 October 2003 | E-mail from G. Cwalina, NRR to J. Calvo, NRR and T. Quay, NRR on Letter with Questions to Westinghouse Concerning Challenges to the Crossflow Instrument Design |