Requests CESSAR-F Ser,Section 5.4.3, Shutdown Cooling Sys, Be Changed to Reflect Commitment to Perform Boron Mixing Testing on First Sys 80 Reactor
ML20071A645
Person / Time
Site: 05000470
Issue date: 02/18/1983
From: Scherer A
ABB COMBUSTION ENGINEERING NUCLEAR FUEL (FORMERLY
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
LD-83-008, LD-83-8, NUDOCS 8302240290
Download: ML20071A645 (1)


Text

C-E Power Systems Tel. 203/688-1911 Combustion Engineenng. Inc. Telex: 99297 1000 Prospect Hill Road Windsor, Connecticut 06095 POWER M SYSTEMS Februa ry 18,1983 Docket No. STN-50-470F LD-83-008 Mr. Darrell G. Eisenhut, Director Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

CESSAR-F, Confirmatory Item Number 10.

Reference:

(A) Letter LD-81-069, A. E. Scherer to D. G. Eisenhut, dated October 8, 1981.

(B) Letter James R. Miller to A. E. Scherer, dated September 11, 1981 (C) Letter ANPP-22841-WFQ/TFQ, E. E. Van Brunt Jr. to G. Knighton, dated January 27, 1983.

Dear Mr. Eisenhut:

Reference (A) provided Combustion Engineering's (C-E's) response to Reactor Systems Branch question 440.6 (Reference B) regarding the boration capability of the System 80" Nuclear Steam Supply System (NSSS). C-E commited to confirm the adequacy of boron mixing fcr System 80 by referencing the results of tests performed on the San Onofre Unit 2 reactor and demonstrating their applicability to the Sytem 80 NSSS. The staff concluded in the CESSAR-F SER that demonstrating the applicability of those tests to CESSAR-F would be an acceptable alternative to conducting specific boron mixing tests at Palo Verde.

Since that commitment was made, Arizona Public Service Company has comited via Reference (C) to verify boron mixing during natural circulation testing on Palo Verde Nuclear Generating Station (PVNGS) Unit 1. Hence the boron nixing capat'ility of the System 80 NSSS will be prototypically demonstrated on the lead System 80 plant.

In light of the above we would like the CESSAR-F SER, Section 5.4.3 (Shutdown Cooling System), to be changed to reflect the committment to perform boron mixing testing on the first System 80 reactor. These tests will demonstrate the boration capability of the System 80 design and therefore, should close out confirmatory item number ten (10) of the CESSAP,-F SER.

If I can be of any further assistance in this matter please contact either myself )f Mr. G. A. Davis of my staff at (203) 688-1911 extension 2803.

Very truly yours, COMBUSTION ENGINEERING, INC.

'o03 8302240290 830218 PDR ADOCK 05000470 g(M) #

E PDR A. E. Scherer Director Licensing AES:tmr