Letter Sequence Approval |
---|
EPID:L-2020-LLA-0135, Request for License Amendment for Vacuum Relief Valve Technical Specification Changes (LAR-20-005) (Approved, Closed) |
|
|
|
---|
Category:Letter
MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public ML24029A0592024-01-30030 January 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 ML24016A1132024-01-30030 January 2024 Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23347A2092024-01-17017 January 2024 Voluntary Requests for Data, Information, And/Or Observation ML23279A0042024-01-17017 January 2024 Amendment No. 194 to Remove Combined License Appendix C NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23317A2072023-12-22022 December 2023 Issuance of Amendments 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448 ML23335A1222023-12-19019 December 2023 Safety Evaluation Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 (EPID L-2023-LRQ-0002) - Letter ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23338A2182023-12-0606 December 2023 Project Manager Reassignment NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23306A3552023-11-0808 November 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 052000/262023008 ML23268A0572023-11-0707 November 2023 Issuance of Amendments 194 & 191 Request for License Amendment Relocation of Technical Specification 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23263A9852023-10-12012 October 2023 Issuance of Amendments Nos. 221 and 204, Regarding Technical Specification 5.5.11.C, Acceptance Criteria for Charcoal Filter Testing ML23283A0472023-10-0808 October 2023 Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report ML23234A2352023-09-0808 September 2023 Request for Withholding Information from Public Disclosure Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) ML23243B0252023-08-30030 August 2023 Exam Corporate Notification Letter (210 Day) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) 2024-02-05
[Table view] Category:License-Combined License (COL) (New/Renewal/Amendments) DKT 52
MONTHYEARML23243B0542023-12-19019 December 2023 VEGP Unit 4 Amendment No. 193 - Enclosure 2 ML23243A9682023-12-19019 December 2023 VEGP Unit 3 Amendment No. 197 - Enclosure 1 ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action ML23159A0972023-07-31031 July 2023 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 23-001) ML23072A2722023-05-0101 May 2023 Enclosure 1 - LAR 22-005 Amendment No. 191 Vogtle Unit 3 ML23072A2732023-05-0101 May 2023 Enclosure 2 - LAR 22-005 Amendment No. 188 Vogtle, Unit 4 ML23072A2762023-05-0101 May 2023 Attachment to Enclosure 2 - VEGP U4 Amendment 188 LAR-22-005 ML23037A0892023-02-0808 February 2023 Amendment - Vogtle Unit 3 Amendment No. 190, Tech Spec Exceptions for In-Containment Refueling Water Storage Tank Operability Prior to Initial Criticality (Exigent Circumstances) ML20290A2822022-08-0303 August 2022 Finding That Acceptance Criteria in the Combined License Are Met (10 CFR 103g - Finding) ML21237A2342021-10-15015 October 2021 Amendment Unit 3 - Vogtle Electric Generating Plant LAR 21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2352021-10-15015 October 2021 Attachment Unit 3 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2372021-10-15015 October 2021 Attachment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21237A2362021-10-15015 October 2021 Amendment Unit 4 - Vogtle Electric Generating Plant LAR-21-001: Clarification of ITAAC Regarding Invessel Components ML21217A0242021-09-17017 September 2021 Amendment No. 187 - Vogtle Electric Generating Plant Unit 3 ML21217A0252021-09-17017 September 2021 Amendment No. 185 - Vogtle Electric Generating Plant Unit 4 ML21217A0272021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment No. 185 ML21217A0262021-09-17017 September 2021 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment No. 187 ML20314A0132020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-005) ML20314A0142020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 184 (LAR-20-005) ML20314A0112020-12-0707 December 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 186 (LAR-20-005) ML20314A0102020-12-0707 December 2020 License Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-005) ML20247J4612020-10-14014 October 2020 Amendment 183 - Vogtle Electric Generating Plant Unit 4 (LAR 20-004) ML20247J4592020-10-14014 October 2020 Amendment 185 - Vogtle Electric Generating Plant Unit 3 (LAR 20-004) ML20237F4922020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 184 (LAR-20-003) ML20237F4942020-09-24024 September 2020 Attachment - Vogtle Electric Generating Plant Unit 4 Amendment 182 (LAR-20-003) ML20237F4932020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 20-003) ML20237F4912020-09-24024 September 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 20-003) ML20196L6772020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 Amendment 183 for LAR-20-002 ML20196L6782020-08-11011 August 2020 Amendment 181 - Vogtle Electric Generating Plant Unit 4 for LAR 20-002 ML20196L6792020-08-11011 August 2020 Attachment - Vogtle Electric Generating Plant Unit 4 for Amendment 181 for LAR-20-002 ML20132A0762020-08-0404 August 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 20-001) ML20059N7792020-05-12012 May 2020 Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20059N7822020-05-12012 May 2020 Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1632020-05-12012 May 2020 Attachment to Amendment 180 - LAR-19-010: Auxiliary Building Room Heatup ML20106F1622020-05-12012 May 2020 Attachment to Amendment 181 - LAR-19-010: Auxiliary Building Room Heatup ML20120A0072020-04-30030 April 2020 Attachment for Amendment 178 Cyber Security Plan Changes (LAR-19-020) ML20106F1592020-04-30030 April 2020 Attachment for Amendment 179 Cyber Security Plan Changes (LAR-19-020) ML20057E1172020-04-30030 April 2020 Amendment 178 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20057E1062020-04-30030 April 2020 Amendment 179 - Issuance of Amendments for Cyber Security Plan Changes (LAR-19-020) ML20064E6682020-03-23023 March 2020 Enclosure 4: Supplemental Attachment to License Amendment No. 148 for COL No. NPF-91 ML20064E6802020-03-23023 March 2020 Enclosure 5: Supplemental Attachment to License Amendment No. 147 for COL No. NPF-92 ML20064E5722020-03-23023 March 2020 Supplemental Attachment to License Amendment No. 36 for COL No. NPF-92 ML20064E6122020-03-23023 March 2020 Enclosure 2: Supplemental Attachment to License Amendment No. 125 for COL No. NPF-91 ML20064E6282020-03-23023 March 2020 Enclosure 3: Supplemental Attachment to License Amendment No. 124 for COL No. NPF-92 ML20013G6882020-02-0303 February 2020 Amendment - Vogtle Electric Generating Plant Unit 4 ML19350C7142020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 4 (LAR 19-015) ML19350C6862020-01-28028 January 2020 Amendment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015) ML19350C7002020-01-28028 January 2020 Attachment - Vogtle Electric Generating Plant Unit 3 (LAR 19-015).d 2023-07-31
[Table view] |
Text
SOUTHERN NUCLEAR OPERATING COMPANY, INC.
GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MEAG POWER SPVM, LLC MEAG POWER SPVJ, LLC MEAG POWER SPVP, LLC CITY OF DALTON, GEORGIA VOGTLE ELECTRIC GENERATING PLANT, UNIT 3 DOCKET NO.52-025 AMENDMENT TO FACILITY COMBINED LICENSE Amendment No. 186 License No. NPF-91
- 1. The Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Southern Nuclear Operating Company (SNC),
dated June 19, 2020, as supplemented by letter dated September 18, 2020, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B. The facility will be constructed and will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations, and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to Appendix A, Technical Specifications, of the facility Combined License, as indicated in the attachment to this license amendment. Paragraph 2.D(8) of facility Combined License No. NPF-91 is hereby amended to read as follows:
(8) Incorporation The Technical Specifications, Environmental Protection Plan, and ITAAC in Appendices A, B, and C, respectively of this license, as revised through Amendment No. 186, are hereby incorporated into this license.
- 3. This license amendment is effective as of the date of its issuance and shall be implemented within 30 days of the date of issuance. SNC shall submit the changes authorized by this amendment with the next update of the UFSAR in accordance with 10 CFR 50.71(e).
FOR THE NUCLEAR REGULATORY COMMISSION:
/RA/
Omar Lpez-Santiago, Chief Vogtle Project Office Office of Nuclear Reactor Regulation Date of Issuance: December 7, 2020
Attachment:
Page 7 of the Facility Combined License and affected pages of Appendix A