MONTHYEARND-22-0881, License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002)2023-01-0303 January 2023 License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002) Project stage: Request ML23065A0782023-03-0303 March 2023 Final RAIs Regarding the Beaver Valley Emergency LAR (EPID L-2023-LLA-002) - Email Project stage: RAI ML23137A2172023-05-17017 May 2023 COL Docs - FW Re Revised Draft RAI for SNC Vogtle LAR-22-002, TS 3.8.3 Inverters - Operating, Completion Time Extension Project stage: Request NL-23-0339, Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1)2023-06-13013 June 2023 Response to Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters - Operating, Completion Time Extension (LAR-22-002S1) Project stage: Response to RAI ML23164A0422023-06-13013 June 2023 ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number C.2.6.09.06 (Index No. 666) for Vogtle Unit 4 Combined License (VOG4) Project stage: Request PMNS20230576, Notice of Meeting with Southern Nuclear Operating Company2023-06-28028 June 2023 Notice of Meeting with Southern Nuclear Operating Company Project stage: Request ML23188A1512023-08-0909 August 2023 Round 2 RAIs for LAR 22-002 TS 3.8.3 Inverters-Operating, Completion Time Extension Project stage: RAI ML23187A5742023-08-22022 August 2023 Summary of June 29, 2023, Meeting with Southern Nuclear Operating Company Project stage: Meeting NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters – Operating, Completion Time Extension (LAR-22-002S2) Project stage: Request ML23275A1002023-10-0202 October 2023 COL Docs - Re Action Summary of 9.27.23 Clarification Call with Southern Nuclear Company on LAR-22-0002, TS 3.8.3 Inverters - Operating Completion Time Project stage: Request ML23243A9562023-12-19019 December 2023 VEGP Units 3 and 4 LAR 22-002, Technical Specification 3.8.3, Inverters Operating, Completion Time Extension Amendments 197/193 Project stage: Request ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter Project stage: Approval ML23243B0572023-12-19019 December 2023 VEGP Unit 4 Amendment Attachment Project stage: Other ML23243B0542023-12-19019 December 2023 VEGP Unit 4 Amendment No. 193 - Enclosure 2 Project stage: Other ML23243A9682023-12-19019 December 2023 VEGP Unit 3 Amendment No. 197 - Enclosure 1 Project stage: Other ML23243A9802023-12-19019 December 2023 VEGP Unit 3 Amendment Attachment Project stage: Other ML23243B0492023-12-19019 December 2023 VEGP Units 3 and 4, Safety Evaluation, LAR-22-002, TS 3.8.3 Inverters Operating, Completion Time Extension - Enclosure 3 Project stage: Approval 2023-05-17
[Table View] |
Text
December 19, 2023 Ms. Jamie M. Coleman, Director Fleet Regulatory Affairs Southern Nuclear Operating Company, Inc.
3535 Colonnade Parkway, Bin N-226-EC Birmingham, AL 35243
SUBJECT:
VOGTLE ELECTRIC GENERATING PLANT, UNITS 3 AND 4ISSUANCE OF AMENDMENT REGARDING LICENSE AMENDMENT REQUEST: TECHNICAL SPECIFICATION 3.8.3, INVERTERS - OPERATING, COMPLETION TIME EXTENSION (EPID L-2023-LLA-0002)
Dear Ms. Coleman:
The U.S. Nuclear Regulatory Commission (the Commission or NRC) has issued the enclosed Amendment Nos. 197 and 193 to Combined License (COL) Nos. NPF-91 and NPF-92 for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4, respectively. The amendments consist of changes to COL Appendix A, Technical Specifications designated by Southern Nuclear Operating Company as License Amendment Request (LAR)22-002. The amendments involve changes to the VEGP, Units 3 and 4, COL Appendix A, TS, specifically to revise the VEGP, Units 3 and 4, COL Appendix A, Technical Specifications (TS) 3.8.3, Inverters - Operating, to extend the completion time for Required Action A.1 from 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to 14 days. There is an additional unrelated change to correct a misspelling in VEGP, Units 3 and 4, TS 3.3.9, Engineered Safety Feature Actuation System (ESFAS) Manual Initiation.
A copy of the related safety evaluation, which includes the evaluation of the changes, is also enclosed. A Notice of Issuance associated with the amendment will be published in the Federal Register.
In accordance with Title 10 of the Code of Federal Regulations, Part 2, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA/
William (Billy) Gleaves, Senior Project Manager Vogtle Project Office Office of Nuclear Reactor Regulation Docket Nos.: 52-025,52-026
Enclosures:
- 1. Amendment No. 197 to VEGP Unit 3 COL NPF-91
- 2. Amendment No. 193 to VEGP Unit 4 COL NPF-92
- 3. Safety Evaluation cc: Listserv
Package: ML23243A956 Vogtle Unit 3 & 4 Letter: ML23353A170 Amendment No. 197: ML23243A968 Attachment Unit 3: ML23243A980 Amendment No. 193: ML23243B054 Attachment Unit 4: ML23243B057 Safety Evaluation: ML23243B049 Concurred by email NRR-106 OFFICE NRR/VPO/PM NRR/DORL/LPL2-2/LA NRR/DEX/EEEB/BC NRR/DSS/STSB/BC NAME BGleaves RButler VGoel*