MONTHYEARML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24134A1532024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Exemption ML24102A2572024-04-25025 April 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - March 2024 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-23-198, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0707 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20326A0002020-11-23023 November 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0211 (COVID-19)) ML20288A6402020-11-0606 November 2020 Temporary Exemption from Biennial Emergency Preparedness Exercise Frequency Requirements of 10 CFR Part 50, Appendix E, Section IV L-20-279, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-10-28028 October 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic ML20283A7722020-10-0909 October 2020 Submittal of Pennsylvania Letter Requesting Exemption from Biennial Exercise Requirements for Pennsylvania Nuclear Power Plants in Calendar Year 2020 ML20275A2032020-09-30030 September 2020 Acceptance of Requested Licensing Action, One-Time Acceptance for Review: Beaver Valley of Exemption from 10 CFR 50, Appendix E, Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Pandemic ML20119B0862020-05-19019 May 2020 Letter with Exemption Request from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) ML20119B0832020-05-19019 May 2020 Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) ML20119B0842020-05-19019 May 2020 FRN - Beaver Valley Power Station, Units 1 and 2 - Request for Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0033 (COVID-19)) ML20119A5242020-05-0707 May 2020 FRN: Notice of Issuance of Multiple Exemptions Regarding 10 CFR Part 26 (COVID-19) ML20109A0002020-04-20020 April 2020 Exemption from Select Requirements of 10 CFR Part 26 (EPID L-2020-LLE-0025)(COVID-19)) L-20-140, Work Hour Rule Exemption Request Due to Pandemic (L-20-140)2020-04-18018 April 2020 Work Hour Rule Exemption Request Due to Pandemic (L-20-140) ML20109A0102020-04-18018 April 2020 Verbal Part 26 Exemption - Delivered 4/18/20 at 7:00 P.M ML19126A1952019-06-0505 June 2019 Transmittal Letter: Beaver Valley Power Station, Unit 2 - Exemption from the Regulations in 10 CFR Part 50, Appendix H ML19067A0212019-06-0404 June 2019 FENOC Fleet - Exemption from the Requirements of 10 CFR 73.55(p)(1)(i) and (II) Related to the Suspension of Security Measures in an Emergency or During Severe Weather ML17313A5542018-03-0101 March 2018 FRN Exemption from the Requirements of 10 CFR 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Clad Fuel Rods (CAC Nos. MF9582 and MF9583; EPID L-2017-LLE-0011) ML17313A5502018-03-0101 March 2018 Exemption from the Requirements of 10 CFR 50.46 and Appendix K to 10 CFR Part 50 to Allow the Use of Optimized Zirlo Fuel Rod Cladding (CAC Nos. MF9582 and MF9583; EPID L-2017-LLE-0011) ML1002300042010-03-0101 March 2010 Part 73 Exemption Request ML0205001382002-02-19019 February 2002 Exemption from the Requirements of 10 CFR 50.60(a) and Appendix G 2024-09-17
[Table view] Category:Letter
MONTHYEARIR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 05000334/LER-2024-004, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 05000334/LER-2024-003, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations 05000334/LER-2024-002, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation 05000334/LER-2024-001, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000334/20240102024-05-15015 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000334/2024010 and 05000412/2024010 L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee 05000412/LER-2023-003-01, Missile Barrier Door Left Open Resulting in a Loss of Safety Function2024-02-20020 February 2024 Missile Barrier Door Left Open Resulting in a Loss of Safety Function IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection 2024-09-17
[Table view] |
Text
April 20, 2020 Mr. Rod L. Penfield Site Vice President Energy Harbor Nuclear Corp.
Beaver Valley Power Station Mail Stop P-BV-SSEB P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - EXEMPTION FROM SELECT REQUIREMENTS OF 10 CFR PART 26 (EPID L-2020-LLE-0025 [COVID-19])
Dear Mr. Penfield:
On April 18, 2020, the U.S. Nuclear Regulatory Commission (NRC) provided verbal authorization of your requested exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 26, Fitness for Duty Programs, Section 26.205, Work hours (documentation of the verbal authorization may be found at Agencywide Documents Access and Management System (ADAMS) Accession No. ML20109A010). This action was taken in response to your application dated April 18, 2020 (ADAMS Accession No. ML20109A008), which cited the March 28, 2020 (ADAMS Accession No. ML20087P237),
letter from Mr. Ho Nieh describing a process to request expedited review of certain exemptions from 10 CFR Part 26 during the COVID-19 Public Health Emergency (PHE). This letter provides a written evaluation of your request and the NRCs approval of your exemption.
In your letter, you provided the following information:
- A statement that you can no longer meet the work-hour controls of 10 CFR 26.205(d) for certain positions;
- A list of positions for which you will maintain current work-hour controls under 10 CFR 26.205(d)(1)-(d)(7);
- The date and time when you will begin implementing site-specific COVID-19 PHE fatigue-management controls for personnel specified in 10 CFR 26.4(a);
- A statement that your site-specific COVID-19 fatigue-management controls are consistent with the constraints outlined in the March 28, 2020, letter; and
R. Penfield
- A statement that you have established alternative controls for the management of fatigue during the period of the exemption and, at a minimum, the controls ensure that, for individuals subject to these alternative controls:
o Individuals will not work more than 16 work hours in any 24-hour period and not more than 86 work hours in any 7-day period, excluding shift turnover; o A minimum 10-hour break is provided between successive work periods; o 12-hour shifts are limited to not more than 14 consecutive days; o A minimum of 6 days off are provided in any 30-day period; and o Requirements have been established for behavioral observation and self-declaration during the period of the exemption.
Therefore, the NRC finds that the technical basis for an exemption described in the March 28, 2020, letter is applicable to your specific request.
Section 26.9, Specific exemptions, allows the NRC to grant exemptions from the requirements of 10 CFR Part 26. The NRC staff has determined that granting the licensees requested exemption is authorized by law, will not endanger life or property or the common defense and security, and is otherwise in the public interest.
The underlying purpose of 10 CFR 26.205(d) is to prevent impairment from fatigue due to duration, frequency, or sequestering of successive shifts. Based on the evaluation provided in the NRCs March 28, 2020, letter and the criteria discussed above, no new accident precursors are created by utilizing whatever licensee staff resources may be necessary or available during the term of this exemption to respond to a plant emergency and to ensure that the plant maintains a safe and secure status. Therefore, the probability of postulated accidents is not increased. Also, the consequences of postulated accidents are not increased because there is no change in the types of accidents previously evaluated. The requested exemption would allow the utilization of licensee staff resources as may be necessary to maintain safe operation of the plant and to respond to a plant emergency. Therefore, the NRC finds that there is no undue risk to public health and safety from granting the requested exemption.
The requested exemption would allow the utilization of licensee security staff resources as may be necessary to ensure the common defense and security. Therefore, the NRC finds that there is no impact on common defense and security from granting the requested exemption.
Due to the impacts that the COVID-19 PHE has had on the licensees ability to comply with the work hour controls of 10 CFR 26.205(d), the importance of maintaining the operations of the Beaver Valley Power Station, Units 1 and 2, and the controls the licensee has established, the NRC finds that granting the requested exemption is in the public interest.
NRC approval of this exemption request is categorically excluded under 10 CFR 51.22(c)(25)(vi)(I), and there are no extraordinary circumstances present that would preclude reliance on this exclusion. The NRC staff has determined that approval of this exemption involves no significant hazards consideration; no significant change in the types or significant increase in the amounts of any effluents that may be released offsite; no significant increase in individual or cumulative public or occupational radiation exposure; no significant construction impact; and no significant increase in the potential for or consequences from radiological accidents. In addition, the NRC staff has determined that there would be no significant impacts to biota, water resources, historic properties, cultural resources, or
R. Penfield socioeconomic conditions in the region. As such, there are no extraordinary circumstances present that would preclude reliance on this categorical exclusion. Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the approval of this exemption.
Based on the above, the NRC staff finds that (1) the exemption is authorized by law, (2) the exemption will not endanger life or property or the common defense and security, and (3) the exemption is otherwise in the public interest.
This exemption is effective until 12:00 a.m. on June 18, 2020.
Sincerely,
/RA/
Craig G. Erlanger, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: Listserv
ML20109A000 *via e-mail OFFICE NRR/DORL/LPL1/PM* NRR/DORL/LPL1/LA* NRR/DORL/LPL1/BC* NSIR/DPCP/RSB/BC*
NAME JTobin LRonewicz JDanna ABowers DATE 04/18/20 04/18/20 04/18/20 3/30/20 OFFICE NMSS/REFS/ERLRB/BC* NRR/DRO/D* OGC (NLO w/edits)* NRR/DORL/D NAME RElliott CMiller TCampbell CErlanger DATE 3/31/20 3/30/20 04/20/20 04/20/20