Ltr 12/21/15 Monticello Nuclear Generating Plant Follow-Up to Disputed Violations of NRC Inspection Report 05000263/2015007 (Nja)
ML15355A533
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/21/2015
From: Lipa C A
NRC/RGN-III/DRS/EB2
To: Gardner P A
Northern States Power Co
References
EA-15-206 IR 2015007
Download: ML15355A533 (2)


See also: IR 05000263/2015007

Text

December 21, 2015

EA-15-206 Mr. Peter Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT FOLLOW-UP TO DISPUTED VIOLATION OF NRC INSPECTION REPORT 05000263/2015007

Dear Mr. Gardner:

This is a follow-up letter to the U.S. Nuclear Regulatory Commission (NRC) acknowledgement of disputed violation of NRC Inspection Report (IR) 05000263/2015007. Specifically, on October 28, 2015, the NRC acknowledged your letter sent to the NRC, dated October 2, 2015, that contested a Non-Cited Violation (NCV) documented in our IR issued on September 2, 2015. The contested NCV is "Failure to Review for Suitability of Application Safety-Related Relays Installed Beyond their Service Life." The NRC seeks to provide a thorough response to disputed violations within 90 days of receipt of licensee's points of contention, as described in Section 2.2.8 of the NRC Enforcement Manual, Part I. However, the NRC review of this disputed violation is expected to take longer than 90 days because of ongoing activities related to the subject of this disputed violation. We will inform you as soon as we complete our evaluation, which is expected to occur during the first quarter of calendar year 2016. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA Benny Jose Acting for/ Christine A. Lipa, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-263 License No. DPR-22 cc: Distribution via LISTSERV December 21, 2015 EA-15-206 Mr. Peter Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota 2807 West County Road 75 Monticello, MN 55362-9637

SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT FOLLOW-UP TO DISPUTED VIOLATION OF NRC INSPECTION REPORT 05000263/2015007

Dear Mr. Gardner:

This is a follow-up letter to the U.S. Nuclear Regulatory Commission (NRC) acknowledgement of disputed violation of NRC Inspection Report (IR) 05000263/2015007. Specifically, on October 28, 2015, the NRC acknowledged your letter sent to the NRC, dated October 2, 2015, that contested a Non-Cited Violation (NCV) documented in our IR issued on September 2, 2015. The contested NCV is "Failure to Review for Suitability of Application Safety-Related Relays Installed Beyond their Service Life." The NRC seeks to provide a thorough response to disputed violations within 90 days of receipt of licensee's points of contention, as described in Section 2.2.8 of the NRC Enforcement Manual, Part I. However, the NRC review of this disputed violation is expected to take longer than 90 days because of ongoing activities related to the subject of this disputed violation. We will inform you as soon as we complete our evaluation, which is expected to occur during the first quarter of calendar year 2016. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA Benny Jose Acting for/ Christine A. Lipa, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-263 License No. DPR-22 cc: Distribution via LISTSERV DISTRIBUTION: Janelle Jessie RidsNrrDorlLpl3-1 Resource RidsNrrPMMonticello RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15355A533 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME BJose for NFeliz-Adorno:cl BJose for CLipa DATE 12/21/15 12/21/15 OFFICIAL RECORD COPY