ML080100408

From kanterella
Revision as of 17:11, 12 July 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Er 05000321-07-301 & Er 05000366-07-301; on 12/03 - 06, 2007 & 12/10, 2007, Southern Nuclear Operating Company, Inc.; E. I. Hatch, Units 1 & 2, NRC Examination Report
ML080100408
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/10/2008
From: Widmann M
NRC/RGN-II/DRS/OLB
To: Madison D
Southern Nuclear Operating Co
References
50-321/07-301, 50-366/07-301
Download: ML080100408 (13)


See also: IR 05000321/2007301

Text

January 10, 2008Southern Nuclear Operating Company, Inc.ATTN:Mr. Dennis R. MadisonVice President - HatchEdwin I. Hatch Nuclear Plant

11028 Hatch Parkway North

Baxley, GA 31513SUBJECT:EDWIN I. HATCH NUCLEAR PLANT- NRC EXAMINATION REPORT05000321/2007301 AND 05000366/2007301Dear Mr. Madison:

During the period December 3 - 6, 2007, the Nuclear Regulatory Commission (NRC)administered operating tests to employees of your company who had applied for licenses to

operate the Edwin I. Hatch Nuclear Plant Units 1 and 2. At the conclusion of the tests, the

examiners discussed the tests and preliminary findings with those members of your staff

identified in the enclosed report. The written examination was administered by your staff on

December 10, 2007.Four Senior Reactor Operator (SRO) applicants passed both the written examination andoperating test. One Reactor Operator (RO) and one SRO applicant failed the written

examination. One RO applicant failed both the written examination and the operating test.

There were five post examination comments. The NRC resolutions to these comments are

summarized in Enclosure 2. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letterand its enclosure will be available electronically for public inspection in the NRC PublicDocument Room or from the Publicly Available Records (PARS) component of NRC's

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

SNC2Should you have any questions concerning this letter, please contact me at (404) 562-4550.Sincerely,

Malcolm T. Widmann, ChiefOperations Branch

Division of Reactor SafetyDocket Nos.: 50-321, 50-366License Nos.: DPR-57, NPF-5Enclosures:1. Report Details2. NRC Resolution to the Facility Commentscc: See Page 3

SNC3J. T. GasserExecutive Vice President

Southern Nuclear Operating Company, Inc.

Electronic Mail DistributionDavid H. JonesVice President - Engineering

Southern Nuclear Operating Company, Inc.

P.O. Box 1295

Birmingham, AL 35201-1295L. M. Stinson, Vice President,Fleet Operations Support

Southern Nuclear Operating Company, Inc.

11028 Hatch Parkway North

Baxley, GA 31513

Raymond D. Baker

Manager Licensing - Hatch

Southern Nuclear Operating Company, Inc.

Electronic Mail DistributionArthur H. Domby, Esq.Troutman Sanders

Electronic Mail DistributionLaurence BergenOglethorpe Power Corporation

Electronic Mail DistributionMoanica CastonSouthern Nuclear Operating Company, Inc.

Bin B-022

P. O. Box 1295

Birmingham, AL 35201-1295DirectorDepartment of Natural Resources

205 Butler Street, SE, Suite 1252

Atlanta, GA 30334Manager, Radioactive Materials ProgramDepartment of Natural Resources

Electronic Mail DistributionChairmanAppling County Commissioners

69 Tippins St., Suite 201

Baxley, GA 31513Resident ManagerOglethorpe Power Corporation

Edwin I. Hatch Nuclear Plant

Electronic Mail DistributionSenior Engineer - Power SupplyMunicipal Electric Authority

of Georgia

Electronic Mail DistributionReece McAlisterExecutive Secretary

Georgia Public Service Commission

244 Washington Street, SW

Atlanta, GA 30334John C. Lewis,Training Managerc/o Edwin C. Hatch Nuclear

Generating Plant

Southern Nuclear Operating Company

11028 Hatch Parkway North

Baxley, GA 31513

OFFICERII:DRSRII:DRSRII:DRSRIV:DRS

SIGNATUR * / RA / * /RA /* /RA/* /RA /NAMERAiello:pmdRBaldwinBCaballeroMWidmannDATE1/4/08 1/4/08 1/4/08 1/10/08

E-MAIL YESNO YESNO YESNO YESNO

Enclosure 1 U . S. NUCLEAR REGULATORY COMMISSIONREGION IIDocket Nos.:50-321, 50-366

License Nos.:DPR-57, NPF-5Report No.:05000321/2007301 and 05000366/2007301

Licensee:Southern Nuclear Power Company (SNPCO)

Facility:Edwin I. Hatch Nuclear Plant, Units 1 & 2

Location:11030 Hatch Parkway N.Baxley, GA, 31513Dates:Operating Tests - December 3 - 6, 2007Written Examination - December 10, 2007Examiners:R. Aiello, Chief, Senior Operations EngineerR. Baldwin, Senior Operations Engineer

B. Caballero, Operations EngineerApproved by:Malcolm T. Widmann, ChiefOperations Branch

Division of Reactor Safety

Enclosure 1SUMMARY OF FINDINGSER05000321/2007301 and ER05000366/2007301; 12/03 - 06, 2007 & 12/10, 2007; Edwin I.Hatch Nuclear Plant, Units 1& 2, Licensed Operator Examinations.The NRC examiners conducted operator licensing initial examinations in accordance with theguidance in NUREG-1021, Revision 9, "Operator Licensing Examination Standards for Power

Reactors." This examination implemented the operator licensing requirements of 10 CFR

§55.41, §55.43, and §55.45.The NRC administered the operating tests during the period of December 3 - 6, 2007. Members of the Edwin I. Hatch training staff administered the written examination on December

10, 2007. The written examination was developed by the NRC and the operating test was

developed by the Edwin I. Hatch Training Department. Four Senior Reactor Operator (SRO) applicants passed both the written examination andoperating test. One Reactor Operator (RO) and one SRO applicant failed the written

examination. One RO applicant failed both the written examination and the operating test.

There were five post examination comments. The NRC resolutions to these comments are

summarized in Enclosure 2. No findings of significance were identified.

Enclosure 1Report Details4.OTHER ACTIVITIES

4OA5Operator Licensing Initial Examinations

a.Inspection ScopeThe facility developed the operating test and the NRC developed the written

examination in accordance with NUREG-1021, "Operator Licensing Examination

Standards for Power Reactors," Revision 9. The NRC reviewed the proposed operating

test. Examination changes agreed upon between the NRC and the licensee were made

according to NUREG-1021 and incorporated into the final version of the test materials. The examiners reviewed the licensee's examination and test security measures whilepreparing and administering the examinations and tests to ensure examination and test

security and integrity complied with 10 CFR 55.49, "Integrity of examinations and tests." The examiners evaluated two RO and five SRO applicants who were being assessedunder the guidelines specified in NUREG-1021. The examiners administered the

operating tests during the period of December 3 - 6, 2007. The written examination was

administered by the Edwin I. Hatch training staff on December 10, 2007. The

evaluations of the applicants and review of documentation were performed to determine

if the applicants, who applied for licenses to operate the Edwin I. Hatch Nuclear Plant,

met requirements specified in 10 CFR 55, "Operators' Licenses." b.Findings

No findings of significance were identified.The licensee and the NRC reviewed the final version of the written examination andoperating test, and indicated that these exams were within the range of acceptability

expected for the proposed examination and test respectively. Four SRO applicants

passed both the written examination and operating test. One RO and one SRO

applicant failed the written examination. One RO applicant failed both the written

examination and the operating test. Each applicant who passed the operating test and

written examination with an overall score greater than 82% and SRO-only score greater

than 74%, as applicable, was issued an operator license commensurate with the level of

examination administered. The combined RO and SRO written examinations with knowledge and abilities (K/As)question references/answers and examination references may be accessed in theADAMS system (ADAMS Accession Numbers, ML

080040289 and ML080040296).

4Enclosure 14OA6MeetingsExit Meeting Summary

On December 6, 2007, the examination team discussed generic issues with Mr. Dennis

Madison, Site Vice President, and members of his staff. The examiners asked the

licensee whether any materials examined during the examination should be considered

proprietary. No proprietary information was identified.PARTIAL LIST OF PERSONS CONTACTEDLicensee personnelS. Bargeron, Plant ManagerC. Edmund, Nuclear Operations Instructor

S. Grantham, Operation Training Supervisor

J. Lewis, Training Manager

D. Madison, Plant Hatch Vice President

R. Musgrove, Operations Superintendent

K. Wainwright, Initial License Senior InstructorNRC personnel

J. Hickey, Senior Resident inspector

P. Niebaum, Resident Inspector

S. Shaeffer, NRC Branch Chief

Enclosure 2

NRC Resolution to the Facility CommentA complete Text of the licensee's post examination comments can be found in ADAMS underAccession Number ML080040300.RO QUESTION # 18LICENSEE COMMENT:This question deals with a loss of condenser vacuum with the unit at 20% and asks theapplicant for the status of the main steam isolation valves (MSIVs) and the appropriate

procedure for depressurizing the reactor to cold shutdown.The licensee contends that the stem lacks sufficient focus to ensure that only choice "D" iscorrect. The licensee contends that choice "C" is also correct based on the fact that at 20%

rated thermal power (RTP), when the MSIVs close on low vacuum, reactor pressure will

increase above the scram setpoint, requiring entry into the EOP RC flowchart. Once the EOP

RC flow chart is entered, guidance in the RC/P path at location F2 states:"If desired use one or more of the following: Low Low Set (LLS) or Alternate Reactorpressure control system(s) in Table 1 per 31EO-EOP-107-2."The licensee also contends that the systems used to cooldown in both procedures are basicallythe same. The licensee recommended that both choices, "C" and "D" be accepted as correct

answers.NRC DISCUSSION:The NRC disagrees with the licensee's comments. When the EOP RC flow chart is enteredbecause of reactor pressure rising above the scram setpoint, the guidance in the RC/P path at

location F2 fully states:"Stabilize reactor pressure below 1074 psig with main turbine bypass valves. If desiredused one or more of the following: Low Low Set (LLS) or Alternate Reactor pressure

control system(s) in Table 1 per 31EO-EOP-107-2."Further down the RC/P path at location G2, the guidance in the RC/P path also states:"Begin reactor pressure reduction per 34GO-OPS-013-1 AND maintain the cooldownrate below 100 °F/hr-"The question stem provided sufficient focus to ensure only "D" is correct because it specificallyasked for the procedure to depressurize the reactor to cold shutdown

.Furthermore, a procedure note in section 7.5 (Reactor Depressurization) on page 25 of 34GO-OPS-013-1, version 26.13 states:"31EO-EOP-107-2, Alternate RPV Pressure Control, will be used IF this section is beingperformed per the EOP's AND the following

systems are NOT available.

2Enclosure 21) Bypass Valves (~22% total steam flow

)2)HPCI per 34SO-E41-001-2, (~10% total steam flow)

3)RCIC per 34SO-E51-001-2 (~2% total steam flow)

4)Main steam line drains (<1% total steam flow)

5)RHR per 34SO-E11-010-2

6)Manually lifting safety relief valves per 34SO-B21-001-2"Since the question did not specify that the relief valves, HPCI, and RCIC were unavailable, theapplicant must assume that these systems were available. Therefore, the Alternate RPV

Pressure Control procedure, 31EO-EOP-107-2, was not the correct procedure to cooldown and

depressurize the plant in accordance with the note on page 25 of 34GO-OPS-013-1, version

26.13.NRC RESOLUTION:Based on the above discussion, the licensee's recommendation is not accepted and answerchoice "D" will be considered as the only correct answer.RO QUESTION # 31LICENSEE COMMENT

This question deals with unloading Diesel Generator "2A" when offsite power has been restoredfollowing a loss of offsite power on Unit 2. The question asks the applicant to identify the

synchroscope direction as the control room operator transfers the Bus "2E" load (300 kw) from

the Diesel Generator "2A" to the offsite power supply.The licensee contends that the stem lacks sufficient focus to ensure that only choice "C"(counterclockwise) is correct because the stem failed to identify the choices as being "in

accordance with procedure." The licensee also contends that unstated assumptions can be

made that also support choice "A" (clockwise) because the procedure states that

counterclockwise at less than 500 KW is "desirable"; i.e., not the required direction.

Additionally, the licensee contends that paralleling at 300 KW with the rotation in the clockwise

direction would not be enough to result in reverse power.Based on the above discussion, the licensee requests that answer choices "A" and "C" both beaccepted as correct.NRC DISCUSSION:The NRC disagrees with the licensee's comment because the question stem asked for the"required" synchroscope direction. The word "requirement" implies a procedural requirement.

The procedure step in 34SO-R43-001-2, Diesel Generator Standby AC System, Section 7.3.1,

Transferring Power From Diesel Generator 2A To Normal Or Alternate Power states:

3Enclosure 27.3.1.8Using Diesel Gen 2A (2C) Speed Adjust switch, adjust diesel speed to attain aslow synchroscope rotation in the desired direction (1 to 3 RPM)The caution preceding this step states:

"IF THE DIESEL GENERATOR LOAD IS

LESS THAN 500 KW, IT IS DESIRABLE TOHAVE THE SYNCHROSCOPE ROTATING IN THE COUNTERCLOCKWISEDIRECTION TO AVOID OPERATING THE DIESEL AT LOW LOADS WHENPARALLELED TO THE GRID."Because of the procedure step 7.3.1.8 requirement, then counterclockwise is the requiredsynchroscope direction.NRC RESOLUTION:Based on the above discussion, the licensee's recommendation is not accepted and choice "C"will be considered as the only correct answer.RO QUESTION # 59 LICENSEE COMMENT:This question deals with a plant event which causes conditions that require an emergencydepressurization when torus level is very low (55") and the 4160 V busses "2A" and "2B" are

de-energized. The question asks the applicant to choose one system to emergency

depressurize the reactor given these circumstances.The licensee contends that the stem lacks sufficient focus because it contained neither anevents timeline nor the current value of condenser vacuum. Consequently, an applicant may

reasonably assume that torus water level was approaching the heat capacity temperature limit

(HCTL) before the 4160 VAC busses became de-energized. In this case, the bypass valves

may still be available until low vacuum conditions eventually prevented their use. This

reasonable assumption makes choice "B" correct. Additionally, the licensee also contends that the stem did not specify the initial power level. Consequently, if the initial power level was low, and the 4160 VAC busses became

de-energized after a scram, then it could take some time for the condenser vacuum to diminish.

In this case the bypass valves would continue to be used until low vacuum conditions prevented

their use. Per 31EO-EOP-108-1, Alternate RPV Depressurization, the NOTE before step 3.1.1

states that if >10 inches of vacuum exists, then the bypass valves could be used as long as asteam line break did not exist outside secondary containment (which was not the case). This

procedure (31EO-EOP-108-1), implies that the circulating water system should be in service IF

possible. Therefore, the licensee contends that a low initial power level assumption also makes

choice "B" correct.Based on the above discussion, the licensee requests that both choices "B" and "C" beaccepted as correct.

4Enclosure 2NRC DISCUSSION:The NRC disagrees with the licensee's comment because the question stem required theapplicant to choose ONE system to accomplish the emergency depressurization. Additionally,

the applicants must not assume any unstated conditions in the stem, i.e., NUREG 1021, Rev 9,

Appendix E, Policies and Guidelines for Taking NRC Examinations, Section B.7 states:"When answering a question, do not make assumptions regarding conditions that arenot specified in the question unless they occur as a consequence of other conditions

that are stated in the question."The question did not state that the 4160 VAC busses de-energized subsequent to the low toruswater level condition. The question is technically correct since the condenser is not availablefollowing the loss of 4160 VAC busses "2A" and "2B" and the SRVs and HPCI are unavailable

due to the very low torus level (55"). Furthermore, none of the applicants asked the exam

proctors to clarify the sequence of events or the initial power level when the exam was being

administered.NRC RESOLUTION:

Based on the above discussion, the licensee's recommendation is not accepted and choice "C"will be considered as the only correct answer.SRO QUESTION # 85LICENSEE COMMENT

This question deals with a rod that was inadvertently withdrawn from position 16 to 22, versusan intended position 18 during a startup when reactor power was 14%. The question asked the

SRO applicants to determine whether Tech Spec 3.1.6, "Rod Pattern Control," contained a

required action statement applicable to these plant conditions.The licensee contends that the stem lacked sufficient focus to ensure that only choice "D" iscorrect because it did not exclude the initiation of a "tracking" required action statement. As an

example, the licensee referenced a previous question (#79) which did include a statement in

the stem that instructed the applicants to not consider a "tracking" required action statementwhen choosing their answer. Because this question (#85) did not include a similar statement,

the licensee contends that the applicants thought the question was asking if an actual or a

"tracking" required action statement existed for this rod movement error.The licensee contends that this rod movement error constituted a failure to meet bankedposition withdrawal sequence (BPWS) requirements and required the implementation of a

"tracking" required action statement. The licensee contends that if power decreased below

10% (when the TS limiting condition of operation was exceeded) then an actual required action

statement would be required.

5Enclosure 2Based on the above discussion, the licensee requests that both choices "C" and "D" beaccepted as correct.NRC DISCUSSION:The NRC disagrees with the licensee's comment because the stem asked specifically whetherTech Spec 3.1.6, "Rod Pattern Control", contained a required action statement when reactorpower was greater than 10%. There are no required action statements for Tech Spec 3.1.6,

"Rod Pattern Control", when reactor power is 14%. Additionally, at the time the exam was

being administered, none of the applicants asked the exam proctors to clarify an "actual" or

"tracking" required action statement.NRC RESOLUTION:Based on the above discussion, the licensee's recommendation is not accepted and choice "D"will be considered as the only correct answer. SRO QUESTION # 86LICENSEE COMMENT:This question deals with an inadvertent HPCI low steam supply pressure isolation that occursas the MSIVs are being opened during a Unit 2 plant heatup and pressurization (during the

pressure equalization process across the MSIVs, reactor pressure drifts from 170 psig to 125

psig).The licensee contends that the question is not valid because HPCI was no longer required to beoperable when reactor pressure is lowered to 125 psig. The licensee contends that the

applicants stated that there is no correct answer because at 125 psig, there is no required

action statement for HPCI.The licensee requests that this question be deleted because there is no correct answer.NRC DISCUSSION:The NRC agrees with the licensee. The stem for the original question (submitted by the NRC)included a sequence of events where reactor pressure lowered to 125 psig and then was

allowed to return to 160 psig without having HPCI re-aligned. The original question was

subsequently modified during the review processes by the exam team such that reactor

pressure remained at 125 psig (versus returning to a point greater than 150 psig). HPCI is not

required operable less than 150 psig, therefore the question, as presented to the applicants,

had no correct answer.NRC RESOLUTION:Based on the above discussion, the licensee's recommendation is accepted and this question isdeleted from the SRO exam.