MONTHYEARIR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. ML24012A0652024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000321/20233012024-01-17017 January 2024 NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems IR 05000321/20234022023-11-29029 November 2023 Security Baseline Inspection Report 05000321/2023402, 05000366/2023402, and 07200036/2023401 NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal IR 05000321/20230112023-11-17017 November 2023 Biennial Problem Identification and Resolution Inspection Report 050003212023011 and 050003662023011 ML23324A4472023-11-14014 November 2023 302 Exam Approval Letter IR 05000321/20230032023-11-0202 November 2023 Integrated Inspection Report 05000321/2023003, and 05000366/2023003 IR 05000321/20234032023-10-26026 October 2023 Cyber Security Inspection Report 05000321/2023403 and 05000366/2023403 IR 05000321/20234012023-10-17017 October 2023 Security Baseline Inspection Report 05000321 2023401 and 05000366 2023401 ML23250A0472023-09-20020 September 2023 Request for Additional Information Regarding License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts in Technical Specifications Table 1.1-1, Modes ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report IR 05000321/20230052023-08-27027 August 2023 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 & 2 - Report 05000321/2023005 and 05000366/2023005 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 IR 05000321/20230022023-08-0808 August 2023 Integrated Inspection Report 07200036/2023001, 05000321/2023002, and 05000366/2023002 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23201A0292023-07-20020 July 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement ML23178A0012023-06-27027 June 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000321 2023403 and 05000366 2023403 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use IR 05000321/20230102023-06-0909 June 2023 Focused Engineering Inspection Report 05000321 2023010 and 05000366 2023010 NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 ML23123A2222023-05-0101 May 2023 Notification of Licensed Operator Initial Examination 05000321/2023301, and 05000366/2023301 IR 05000321/20230012023-04-26026 April 2023 Integrated Inspection Report 05000321/2023001 and 05000366/2023001 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-23-0179, National Pollutant Discharge Elimination System (NPDES) Permit Renewal2023-03-13013 March 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal ML23065A1092023-03-0808 March 2023 Correction of Relief Request HNP-ISI-RR-05-02 Allowing to Continue Operation with a Flaw Indication on One Reactor Pressure Vessel Closure Bolt Until December 31, 2025 ML23053A2182023-03-0303 March 2023 Correction of Amendment Nos. 321 and 266 Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program IR 05000321/20220062023-03-0101 March 2023 Annual Assessment Letter Edwin I. Hatch Nuclear Plant, Units 1 and 2 - NRC Inspection Report 05000321/2022006 and 05000366/2022006 NL-23-0101, Cycle 28 Core Operating Limits Report Version 12023-02-23023 February 2023 Cycle 28 Core Operating Limits Report Version 1 ML23034A2462023-02-21021 February 2023 Audit Summary for License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML22363A3932023-02-15015 February 2023 Issuance of Amendments Nos. 321 and 266, Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program ML22346A1482023-02-0909 February 2023 Issuance of Amendments 320 and 265, Regarding LAR to Revise Technical Specifications to Adopt TSTF-208 and Administrative Correction for Duplicate Technical Specifications 3.4.10 2024-01-31
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000321/20233012024-01-17017 January 2024 NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23206A0542023-07-25025 July 2023 2A, Exam Administrative Items (Hatch 2021-301) ML23206A0502023-07-25025 July 2023 2A, Exam Final Items (Hatch 2021-301) IR 05000321/20213022022-01-21021 January 2022 NRC Operator License Examination Report 05000321/2021302 and 05000366/2021302 ML21111A0292021-04-19019 April 2021 301, Exam Report ML20231A2362020-08-18018 August 2020 301, Corporate Notification Letter (210-day Letter) IR 05000321/20193012019-10-17017 October 2019 NRC Operator License Examination Report 05000321/2019301 and 05000366/2019301 IR 05000321/20173012018-01-23023 January 2018 NRC Operator License Examination Report 05000321/2017301 and 05000366/2017301 IR 05000321/20153012015-04-30030 April 2015 Er 05000321/2015301 and 05000366/2015301; March 23 - 30, 2015, and April 9, 2015; Edwin I. Hatch Nuclear Plant, Units 1 and 2; Operator License Examinations ML15084A5512015-03-20020 March 2015 Operator Licensing Written Examination Approval 05000321/2015301 and 05000366/2015301 IR 05000321/20123012012-08-0909 August 2012 Er 05000321-12-301 & 05000366-12-301, on 06/18-20/12 - 06/28/12, Edwin I. Hatch, Units 1 & 2 IR 05000321/20113012011-07-28028 July 2011 Er 05000321/11-301 and 05000366/11-301, on June 6 - 10, 2011, and June 23, 2011, Edwin I. Hatch Nuclear Plant, Units 1 and 2, Operator License Examinations IR 05000321/20093022009-12-0303 December 2009 Er 05000321-09-302 and 05000366-09-302, on October 26 - 30, 2009, & November 12, 2009; Edwin I. Hatch Nuclear Plant, Units 1 & 2; Operator License Examinations ML0914802702009-05-28028 May 2009 NRC Operator License Examination Report 05000321-09-301 and 05000366-09-301 ML0911800212009-04-27027 April 2009 April Exam 05000321/2009301 & 05000366/2009301 Approval Letter 4-27-2009 ML0801004082008-01-10010 January 2008 Er 05000321-07-301 & Er 05000366-07-301; on 12/03 - 06, 2007 & 12/10, 2007, Southern Nuclear Operating Company, Inc.; E. I. Hatch, Units 1 & 2, NRC Examination Report 2024-01-17
[Table view] |
Text
August 18, 2020 Edwin D. Dean Site Vice President Southern Nuclear Operating Co., Inc.
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT:
EDWIN I. HATCH - NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION 05000321/2021301 AND 05000366/2021301
Dear Mr. Dean:
In a telephone conversation on July 29, 2020, between Mr. Anthony Ball, Operations Instructor -
Lead Examination Author, and Mr. Joseph Viera, Operations Engineer, arrangements were made for the administration of licensing examinations at the Edwin I. Hatch Nuclear Plant. The on-site preparatory week is scheduled for the week of January 25, 2021. The operating test is scheduled to be administered during the week of March 1, 2021. The written examination is scheduled to be administered the week of March 15, 2021.
As agreed during the telephone conversation, your staff will prepare both the operating test and written examination based on the guidelines in Revision 11 to NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory Commission (NRC) regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff has also agreed to make copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the operating test outline and the supporting reference materials identified in Attachment 3 to ES-201 by October 2, 2020. Mr. Viera provided the written examination outline to your staff on January 23, 2020.
The written examination will be due by December 30, 2020 and the operating test will be due by December 16, 2020. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or Safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be cancelled or rescheduled.
To conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and
E. Dean 2 to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver and/or excusal requests (Office of Management and Budget (OMB) approval number 3150-0090) at least 60 days before the first examination date (if possible). Contact Mr. Viera to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB approval number 3150-0090) and medical certifications (OMB approval number 3150-0024) should be submitted at least 30 days before the first examination date. If the preliminary applications are not received at least 30 days before the examination date, a postponement may be necessary. Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the guidelines for receiving waiver or excusal requests call for at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.
Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398, Personal Qualifications StatementLicensee, or as directed by Mr. Viera when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.
Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.
The burden to the public for these mandatory information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. You may submit comments on any aspect of the information collections, including suggestions for reducing the burden, to FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by electronic mail to infocollects.resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
E. Dean 3 Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information, unless the document requesting or requiring the collection displays a currently valid OMB control number.
In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding, of the agencys Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection through the Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible on the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Anthony Ball has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Viera at (404) 997-4643, (Internet E-mail: joseph.viera@nrc.gov), or me at (404) 997-4662, (Internet E-mail:
eugene.guthrie@nrc.gov).
Sincerely,
/RA/
Eugene F. Guthrie, Chief Operations Branch 2 Division of Reactor Safety Docket Nos.: 50-321, 50-366 License Nos.: DPR-57, NPF-5 cc: Distribution via ListServ
_ML20231A236_____ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII/DRS/OB1 RII/DRS/OB2 SIGNATURE JXV3 NAME J. Viera G. Guthrie DATE 7/ 27/ 2020 8/18 / 2020 E-MAIL COPY? YES NO YES NO